'''Location of the site''':<br> | '''Location of the site''':<br> | ||
− | *Country: Ethiopia | + | *Country: Ethiopia |
− | *District: Bona Zuria | + | *District: Bona Zuria |
− | *Kebele: Beshiro Gute | + | *Kebele: Beshiro Gute |
*GPS coordinate: 6º33’26.8’’N 38º40’8.4’’ E | *GPS coordinate: 6º33’26.8’’N 38º40’8.4’’ E | ||
*Start of Construction: August 2009 | *Start of Construction: August 2009 | ||
Line 12: | Line 12: | ||
<br> | <br> | ||
− | '''Technical Specification:''' | + | '''Technical Specification:'''<br> |
− | |||
− | <br> | ||
*Canal: Lined stone masonry having a length of 53m | *Canal: Lined stone masonry having a length of 53m | ||
*Penstock: Mild stell having a diameter of 400mm and a length of 42m/locally manufactured | *Penstock: Mild stell having a diameter of 400mm and a length of 42m/locally manufactured | ||
*Turbine:<br>T-15 cross flow turbine /Manufactured locally | *Turbine:<br>T-15 cross flow turbine /Manufactured locally | ||
− | *Generator: | + | *Generator: |
*Grid:<br>Wooden pole, ABC cable(2.76Km) | *Grid:<br>Wooden pole, ABC cable(2.76Km) | ||
− | |||
− | |||
{| class="FCK__ShowTableBorders" cellspacing="1" cellpadding="1" width="100%" border="0" | {| class="FCK__ShowTableBorders" cellspacing="1" cellpadding="1" width="100%" border="0" |
Revision as of 14:36, 20 December 2010
Location of the site:
- Country: Ethiopia
- District: Bona Zuria
- Kebele: Beshiro Gute
- GPS coordinate: 6º33’26.8’’N 38º40’8.4’’ E
- Start of Construction: August 2009
- Date of Commissioning:
- Ownership:
Robot Electric Users Cooperative/community based cooperative society - Tariff Structure:
Flat rate/monthly based per appliance
Technical Specification:
- Canal: Lined stone masonry having a length of 53m
- Penstock: Mild stell having a diameter of 400mm and a length of 42m/locally manufactured
- Turbine:
T-15 cross flow turbine /Manufactured locally - Generator:
- Grid:
Wooden pole, ABC cable(2.76Km)