= Checklist for building a biogas plant  =
+
= Overview =
  
#'''Finishing the planning''', i.e. [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/siting.html site evaluation], [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/detincdem.html determination of energy demand and biomass supply] / biogas yield, [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/sizing.html plant sizing], selection of plant [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/design/digestypes2.html#APPRDES design], how and where to use the biogas, etc., in accordance with the [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/planguide.html planning guide]<br>
+
The checklist for the construction of a biogas plant is summarized below.
#'''Stipulate the plant's location and elaborate a site plan''', including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry  
+
 
#'''Draft a technical drawing showing all plant components''', i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage<br>  
+
<br/>
#'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':  
+
 
#*bricks / stones / blocks for walls and foundation  
+
= Checklist for the Construction =
#*sand, gravel  
+
 
#*inlet / outlet pipes  
+
*<u>'''Planning of the Biogas Plant'''</u><ul style="margin-left: 40px;">
#*metal parts (sheet metal, angle irons, etc.)  
+
<li>i.e. [[Siting of the Biogas Unit|site evaluation]],</li>
#*gas pipes and fittings  
+
<li>[[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield,</li>
#*paint and sealants  
+
<li>[[Sizing of the Biogas Plant|plant sizing]],</li>
#*gas appliances  
+
<li>selection of plant [[Types of Biogas Digesters and Plants#Biogas Plant Types and Design|design]],</li>
#*tools  
+
<li>how and where to use the biogas, etc., in accordance with the [[Planning Guide for Biogas Plants|planning guide]]</li>
#*mason and helper  
+
</ul>
#*unskilled labor  
+
</ul>
#*workshop for metal (gas-holder) and pipe installation  
+
 
#'''Material / personnel assignment planning''', i.e. procedural planning and execution of:  
+
<br/>
#*excavation  
+
 
#*foundation slab  
+
*<u>'''Stipulate the plant's location and elaborate a site plan'''</u><ul style="margin-left: 40px;">
#*digester masonry  
+
<li>including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry</li>
#*gasholder  
+
</ul>
#*rendering and sealing the masonry  
+
</ul>
#*mixing pit - slurry storage pit  
+
 
#*drying out the plant  
+
<br/>
#*installing the gas pipe  
+
 
#*acceptance inspection  
+
*<u>'''Draft a technical drawing showing all plant components'''</u><ul style="margin-left: 40px;">
#'''Regular building supervision'''  
+
<li>i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage</li>
#'''Commissioning'''  
+
</ul>
#*functional inspection of the biogas plant and its components  
+
</ul>
#*starting the plant  
+
 
#'''Filling the plant'''  
+
<br/>
#'''Training the user'''
+
 
 +
*<u>'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':</u><ul style="margin-left: 40px;">
 +
<li>bricks / stones / blocks for walls and foundation<br/></li>
 +
<li>sand, gravel<br/></li>
 +
<li>inlet / outlet pipes<br/></li>
 +
<li>metal parts (sheet metal, angle irons, etc.)<br/></li>
 +
<li>gas pipes and fittings<br/></li>
 +
<li>paint and sealants<br/></li>
 +
<li>gas appliances<br/></li>
 +
<li>tools<br/></li>
 +
<li>mason and helper<br/></li>
 +
<li>unskilled labor<br/></li>
 +
<li>workshop for metal (gas-holder) and pipe installation<br/></li>
 +
</ul>
 +
</ul>
 +
 
 +
<br/>
 +
 
 +
*<u>'''Material / personnel assignment planning''', i.e. procedural planning and execution of:</u><ul style="margin-left: 40px;">
 +
<li>excavation<br/></li>
 +
<li>foundation slab<br/></li>
 +
<li>digester masonry<br/></li>
 +
<li>gasholder<br/></li>
 +
<li>rendering and sealing the masonry<br/></li>
 +
<li>mixing pit - slurry storage pit<br/></li>
 +
<li>drying out the plant<br/></li>
 +
<li>installing the gas pipe<br/></li>
 +
<li>acceptance inspection<br/></li>
 +
</ul>
 +
</ul>
 +
 
 +
<br/>
 +
 
 +
*<u>'''Regular building supervision''' '''Commissioning'''</u><ul style="margin-left: 40px;">
 +
<li>functional inspection of the biogas plant and its components<br/></li>
 +
<li>starting the plant<br/></li>
 +
</ul>
 +
</ul>
 +
 
 +
<br/>
 +
 
 +
*<u>'''Filling the plant'''</u>
 +
 
 +
'''​'''<br/>
 +
 
 +
*<u>'''Training the user'''</u>
 +
 
 +
<br/>
 +
 
 +
= Further Information =
 +
 
 +
*[[Checklist for the Planning of a Biogas Plant|Checklist for the Planning of a Biogas Plant]]
 +
 
 +
<br/>
 +
 
 +
= References =
 +
 
 +
<references /><br/>
 
</div>
 
</div>
 +
 +
[[Category:Biogas]]

Latest revision as of 09:25, 7 December 2015

Overview

The checklist for the construction of a biogas plant is summarized below.


Checklist for the Construction


  • Stipulate the plant's location and elaborate a site plan
    • including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry


    • Draft a technical drawing showing all plant components
      • i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage


      • Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant:
        • bricks / stones / blocks for walls and foundation
        • sand, gravel
        • inlet / outlet pipes
        • metal parts (sheet metal, angle irons, etc.)
        • gas pipes and fittings
        • paint and sealants
        • gas appliances
        • tools
        • mason and helper
        • unskilled labor
        • workshop for metal (gas-holder) and pipe installation


        • Material / personnel assignment planning, i.e. procedural planning and execution of:
          • excavation
          • foundation slab
          • digester masonry
          • gasholder
          • rendering and sealing the masonry
          • mixing pit - slurry storage pit
          • drying out the plant
          • installing the gas pipe
          • acceptance inspection


          • Regular building supervision Commissioning
            • functional inspection of the biogas plant and its components
            • starting the plant


            • Filling the plant


            • Training the user


            Further Information


            References