Make sure you register to our monthly newsletter, it's going out soon! Stay up do date about the latest energy news and our current activities.
Click here to register!

Difference between revisions of "Checklist for the Construction of a Biogas Plant"

From energypedia
***** (***** | *****)
m
***** (***** | *****)
 
(11 intermediate revisions by 4 users not shown)
Line 1: Line 1:
 
<div id="PageContent">
 
<div id="PageContent">
= Checklist for building a biogas plant  =
+
= Overview =
  
'''Finishing the planning''', i.e. [[Siting of the Biogas Unit|site evaluation]], [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/detincdem.html determination of energy demand and biomass supply] / biogas yield, [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/sizing.html plant sizing], selection of plant [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/design/digestypes2.html#APPRDES design], how and where to use the biogas, etc., in accordance with the [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/planguide.html planning guide]
+
The checklist for the construction of a biogas plant is summarized below.
  
'''Stipulate the plant's location and elaborate a site plan''', including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry
+
<br/>
  
'''Draft a technical drawing showing all plant components''', i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage
+
= Checklist for the Construction =
  
'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':
+
*<u>'''Planning of the Biogas Plant'''</u><ul style="margin-left: 40px;">
 +
<li>i.e. [[Siting of the Biogas Unit|site evaluation]],</li>
 +
<li>[[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield,</li>
 +
<li>[[Sizing of the Biogas Plant|plant sizing]],</li>
 +
<li>selection of plant [[Types of Biogas Digesters and Plants#Biogas Plant Types and Design|design]],</li>
 +
<li>how and where to use the biogas, etc., in accordance with the [[Planning Guide for Biogas Plants|planning guide]]</li>
 +
</ul>
 +
</ul>
  
*bricks / stones / blocks for walls and foundation
+
<br/>
*sand, gravel
 
*inlet / outlet pipes
 
*metal parts (sheet metal, angle irons, etc.)
 
*gas pipes and fittings
 
*paint and sealants
 
*gas appliances
 
*tools
 
*mason and helper
 
*unskilled labor
 
*workshop for metal (gas-holder) and pipe installation
 
  
'''Material / personnel assignment planning''', i.e. procedural planning and execution of:
+
*<u>'''Stipulate the plant's location and elaborate a site plan'''</u><ul style="margin-left: 40px;">
 +
<li>including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry</li>
 +
</ul>
 +
</ul>
  
*excavation
+
<br/>
*foundation slab
 
*digester masonry
 
*gasholder
 
*rendering and sealing the masonry
 
*mixing pit - slurry storage pit
 
*drying out the plant
 
*installing the gas pipe
 
*acceptance inspection
 
  
'''Regular building supervision''' '''Commissioning'''  
+
*<u>'''Draft a technical drawing showing all plant components'''</u><ul style="margin-left: 40px;">
 +
<li>i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage</li>
 +
</ul>
 +
</ul>
  
*functional inspection of the biogas plant and its components
+
<br/>
*starting the plant
 
  
'''Filling the plant'''  
+
*<u>'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':</u><ul style="margin-left: 40px;">
 +
<li>bricks / stones / blocks for walls and foundation<br/></li>
 +
<li>sand, gravel<br/></li>
 +
<li>inlet / outlet pipes<br/></li>
 +
<li>metal parts (sheet metal, angle irons, etc.)<br/></li>
 +
<li>gas pipes and fittings<br/></li>
 +
<li>paint and sealants<br/></li>
 +
<li>gas appliances<br/></li>
 +
<li>tools<br/></li>
 +
<li>mason and helper<br/></li>
 +
<li>unskilled labor<br/></li>
 +
<li>workshop for metal (gas-holder) and pipe installation<br/></li>
 +
</ul>
 +
</ul>
  
'''Training the user'''
+
<br/>
  
[[Construction of a Biogas Plant|Back to "construction"]]
+
*<u>'''Material / personnel assignment planning''', i.e. procedural planning and execution of:</u><ul style="margin-left: 40px;">
 +
<li>excavation<br/></li>
 +
<li>foundation slab<br/></li>
 +
<li>digester masonry<br/></li>
 +
<li>gasholder<br/></li>
 +
<li>rendering and sealing the masonry<br/></li>
 +
<li>mixing pit - slurry storage pit<br/></li>
 +
<li>drying out the plant<br/></li>
 +
<li>installing the gas pipe<br/></li>
 +
<li>acceptance inspection<br/></li>
 +
</ul>
 +
</ul>
 +
 
 +
<br/>
 +
 
 +
*<u>'''Regular building supervision''' '''Commissioning'''</u><ul style="margin-left: 40px;">
 +
<li>functional inspection of the biogas plant and its components<br/></li>
 +
<li>starting the plant<br/></li>
 +
</ul>
 +
</ul>
 +
 
 +
<br/>
 +
 
 +
*<u>'''Filling the plant'''</u>
 +
 
 +
'''​'''<br/>
 +
 
 +
*<u>'''Training the user'''</u>
 +
 
 +
<br/>
 +
 
 +
= Further Information =
 +
 
 +
*[[Checklist for the Planning of a Biogas Plant|Checklist for the Planning of a Biogas Plant]]
 +
 
 +
<br/>
 +
 
 +
= References =
 +
 
 +
<references /><br/>
 +
</div>
  
<br>
 
</div>
 
 
[[Category:Biogas]]
 
[[Category:Biogas]]

Latest revision as of 09:25, 7 December 2015

Overview

The checklist for the construction of a biogas plant is summarized below.


Checklist for the Construction


  • Stipulate the plant's location and elaborate a site plan
    • including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry


    • Draft a technical drawing showing all plant components
      • i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage


      • Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant:
        • bricks / stones / blocks for walls and foundation
        • sand, gravel
        • inlet / outlet pipes
        • metal parts (sheet metal, angle irons, etc.)
        • gas pipes and fittings
        • paint and sealants
        • gas appliances
        • tools
        • mason and helper
        • unskilled labor
        • workshop for metal (gas-holder) and pipe installation


        • Material / personnel assignment planning, i.e. procedural planning and execution of:
          • excavation
          • foundation slab
          • digester masonry
          • gasholder
          • rendering and sealing the masonry
          • mixing pit - slurry storage pit
          • drying out the plant
          • installing the gas pipe
          • acceptance inspection


          • Regular building supervision Commissioning
            • functional inspection of the biogas plant and its components
            • starting the plant


            • Filling the plant


            • Training the user


            Further Information


            References