m (New page: <div id="PageContent"> = Checklist for building a biogas plant = #'''Finishing the planning''', i.e. [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/pla...)
 
***** (***** | *****)
m
Line 2: Line 2:
 
= Checklist for building a biogas plant  =
 
= Checklist for building a biogas plant  =
  
#'''Finishing the planning''', i.e. [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/siting.html site evaluation], [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/detincdem.html determination of energy demand and biomass supply] / biogas yield, [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/sizing.html plant sizing], selection of plant [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/design/digestypes2.html#APPRDES design], how and where to use the biogas, etc., in accordance with the [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/planguide.html planning guide]<br>
+
#'''Finishing the planning''', i.e. [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/siting.html site evaluation], [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/detincdem.html determination of energy demand and biomass supply] / biogas yield, [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/sizing.html plant sizing], selection of plant [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/design/digestypes2.html#APPRDES design], how and where to use the biogas, etc., in accordance with the [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/planguide.html planning guide]<br>  
#'''Stipulate the plant's location and elaborate a site plan''', including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry  
+
'''Stipulate the plant's location and elaborate a site plan''', including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry  
#'''Draft a technical drawing showing all plant components''', i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage<br>  
+
'''Draft a technical drawing showing all plant components''', i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage<br>  
#'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':  
+
'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':  
#*bricks / stones / blocks for walls and foundation  
+
*bricks / stones / blocks for walls and foundation  
#*sand, gravel  
+
*sand, gravel  
#*inlet / outlet pipes  
+
*inlet / outlet pipes  
#*metal parts (sheet metal, angle irons, etc.)  
+
*metal parts (sheet metal, angle irons, etc.)  
#*gas pipes and fittings  
+
*gas pipes and fittings  
#*paint and sealants  
+
*paint and sealants  
#*gas appliances  
+
*gas appliances  
#*tools  
+
*tools  
#*mason and helper  
+
*mason and helper  
#*unskilled labor  
+
*unskilled labor  
#*workshop for metal (gas-holder) and pipe installation  
+
*workshop for metal (gas-holder) and pipe installation  
#'''Material / personnel assignment planning''', i.e. procedural planning and execution of:  
+
'''Material / personnel assignment planning''', i.e. procedural planning and execution of:  
#*excavation  
+
*excavation  
#*foundation slab  
+
*foundation slab  
#*digester masonry  
+
*digester masonry  
#*gasholder  
+
*gasholder  
#*rendering and sealing the masonry  
+
*rendering and sealing the masonry  
#*mixing pit - slurry storage pit  
+
*mixing pit - slurry storage pit  
#*drying out the plant  
+
*drying out the plant  
#*installing the gas pipe  
+
*installing the gas pipe  
#*acceptance inspection  
+
*acceptance inspection  
#'''Regular building supervision'''  
+
'''Regular building supervision'''  
#'''Commissioning'''  
+
'''Commissioning'''  
#*functional inspection of the biogas plant and its components  
+
*functional inspection of the biogas plant and its components  
#*starting the plant  
+
*starting the plant  
#'''Filling the plant'''  
+
'''Filling the plant'''  
#'''Training the user'''
+
'''Training the user'''
</div>
 

Revision as of 15:45, 4 March 2009

Checklist for building a biogas plant

  1. Finishing the planning, i.e. site evaluation, determination of energy demand and biomass supply / biogas yield, plant sizing, selection of plant design, how and where to use the biogas, etc., in accordance with the planning guide

Stipulate the plant's location and elaborate a site plan, including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry Draft a technical drawing showing all plant components, i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage
Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant:

  • bricks / stones / blocks for walls and foundation
  • sand, gravel
  • inlet / outlet pipes
  • metal parts (sheet metal, angle irons, etc.)
  • gas pipes and fittings
  • paint and sealants
  • gas appliances
  • tools
  • mason and helper
  • unskilled labor
  • workshop for metal (gas-holder) and pipe installation

Material / personnel assignment planning, i.e. procedural planning and execution of:

  • excavation
  • foundation slab
  • digester masonry
  • gasholder
  • rendering and sealing the masonry
  • mixing pit - slurry storage pit
  • drying out the plant
  • installing the gas pipe
  • acceptance inspection

Regular building supervision Commissioning

  • functional inspection of the biogas plant and its components
  • starting the plant

Filling the plant Training the user