= Checklist for building a biogas plant  =
 
= Checklist for building a biogas plant  =
  
'''Finishing the planning''', i.e. [[Siting of the Biogas Unit|site evaluation]], [[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield, [[Sizing_of_the_Biogas_Plant|plant sizing]], selection of plant [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/design/digestypes2.html#APPRDES design], how and where to use the biogas, etc., in accordance with the [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/planguide.html planning guide]  
+
'''Finishing the planning''', i.e. [[Siting of the Biogas Unit|site evaluation]], [[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield, [[Sizing of the Biogas Plant|plant sizing]], selection of plant [[Types_of_Biogas_Digesters_and_Plants#Biogas_Plant_Types_and_Design|design]], how and where to use the biogas, etc., in accordance with the [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/planguide.html planning guide]  
  
 
'''Stipulate the plant's location and elaborate a site plan''', including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry  
 
'''Stipulate the plant's location and elaborate a site plan''', including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry  

Revision as of 14:25, 23 March 2009

Checklist for building a biogas plant

Finishing the planning, i.e. site evaluation, determination of energy demand and biomass supply / biogas yield, plant sizing, selection of plant design, how and where to use the biogas, etc., in accordance with the planning guide

Stipulate the plant's location and elaborate a site plan, including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry

Draft a technical drawing showing all plant components, i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage

Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant:

  • bricks / stones / blocks for walls and foundation
  • sand, gravel
  • inlet / outlet pipes
  • metal parts (sheet metal, angle irons, etc.)
  • gas pipes and fittings
  • paint and sealants
  • gas appliances
  • tools
  • mason and helper
  • unskilled labor
  • workshop for metal (gas-holder) and pipe installation

Material / personnel assignment planning, i.e. procedural planning and execution of:

  • excavation
  • foundation slab
  • digester masonry
  • gasholder
  • rendering and sealing the masonry
  • mixing pit - slurry storage pit
  • drying out the plant
  • installing the gas pipe
  • acceptance inspection

Regular building supervision Commissioning

  • functional inspection of the biogas plant and its components
  • starting the plant

Filling the plant

Training the user

Back to "construction"