= Checklist<br/> =
+
= Overview =
  
'''Finishing the planning'''
+
The checklist for the construction of a biogas plant is summarized below
  
i.e. [[Siting of the Biogas Unit|site evaluation]], [[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield, [[Sizing of the Biogas Plant|plant sizing]], selection of plant [[Types of Biogas Digesters and Plants#Biogas_Plant_Types_and_Design|design]], how and where to use the biogas, etc., in accordance with the [[Planning Guide for Biogas Plants|planning guide]]
+
<br/>
 +
*'''Planning of the Biogas Plant'''
  
 +
i.e. [[Siting of the Biogas Unit|site evaluation]], [[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield, [[Sizing of the Biogas Plant|plant sizing]], selection of plant [[Types of Biogas Digesters and Plants#Biogas Plant Types and Design|design]], how and where to use the biogas, etc., in accordance with the [[Planning Guide for Biogas Plants|planning guide]]
  
 +
<br/>
 +
*'''Stipulate the plant's location and elaborate a site plan'''
  
'''Stipulate the plant's location and elaborate a site plan'''  
+
including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry
 +
 
 +
<br/>
 +
*'''Draft a technical drawing showing all plant components'''
 +
 
 +
i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage
  
including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry
+
<br/>
 +
*'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':
 +
 
 +
bricks / stones / blocks for walls and foundation<br/>
 +
 
 +
sand, gravel<br/>
 +
 
 +
inlet / outlet pipes<br/>
 +
 
 +
metal parts (sheet metal, angle irons, etc.)<br/>
  
 +
gas pipes and fittings<br/>
  
 +
paint and sealants<br/>
  
'''Draft a technical drawing showing all plant components'''
+
gas appliances<br/>
  
i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage
+
tools<br/>
  
 +
mason and helper<br/>
  
 +
unskilled labor<br/>
  
'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':
+
workshop for metal (gas-holder) and pipe installation<br/>
  
*bricks / stones / blocks for walls and foundation
+
<br/>
*sand, gravel
+
*'''Material / personnel assignment planning''', i.e. procedural planning and execution of:
*inlet / outlet pipes
 
*metal parts (sheet metal, angle irons, etc.)
 
*gas pipes and fittings
 
*paint and sealants
 
*gas appliances
 
*tools
 
*mason and helper
 
*unskilled labor
 
*workshop for metal (gas-holder) and pipe installation
 
  
 +
excavation<br/>
  
 +
foundation slab<br/>
  
'''Material / personnel assignment planning''', i.e. procedural planning and execution of:
+
digester masonry<br/>
  
*excavation
+
gasholder<br/>
*foundation slab
 
*digester masonry
 
*gasholder
 
*rendering and sealing the masonry
 
*mixing pit - slurry storage pit
 
*drying out the plant
 
*installing the gas pipe
 
*acceptance inspection
 
  
 +
rendering and sealing the masonry<br/>
  
 +
mixing pit - slurry storage pit<br/>
  
'''Regular building supervision''' '''Commissioning'''
+
drying out the plant<br/>
  
*functional inspection of the biogas plant and its components
+
installing the gas pipe<br/>
*starting the plant
 
  
 +
acceptance inspection<br/>
  
 +
<br/>
 +
*'''Regular building supervision''' '''Commissioning'''
  
'''Filling the plant'''
+
functional inspection of the biogas plant and its components<br/>
  
 +
starting the plant<br/>
  
'''Training the user'''
+
<br/>
 +
*'''Filling the plant'''
  
 +
'''​'''<br/>
 +
*'''Training the user'''
  
[[Construction of a Biogas Plant|-> Back to "Construction"]]
+
<br/>
 
</div>
 
</div>
 +
[[Biogas|-> Back to "Biogas Portal"]]<br/>
 +
 +
<br/>
  
 
[[Category:Biogas]]
 
[[Category:Biogas]]

Revision as of 11:33, 20 March 2014

Overview

The checklist for the construction of a biogas plant is summarized below


  • Planning of the Biogas Plant

i.e. site evaluation, determination of energy demand and biomass supply / biogas yield, plant sizing, selection of plant design, how and where to use the biogas, etc., in accordance with the planning guide


  • Stipulate the plant's location and elaborate a site plan

including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry


  • Draft a technical drawing showing all plant components

i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage


  • Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant:

bricks / stones / blocks for walls and foundation

sand, gravel

inlet / outlet pipes

metal parts (sheet metal, angle irons, etc.)

gas pipes and fittings

paint and sealants

gas appliances

tools

mason and helper

unskilled labor

workshop for metal (gas-holder) and pipe installation


  • Material / personnel assignment planning, i.e. procedural planning and execution of:

excavation

foundation slab

digester masonry

gasholder

rendering and sealing the masonry

mixing pit - slurry storage pit

drying out the plant

installing the gas pipe

acceptance inspection


  • Regular building supervision Commissioning

functional inspection of the biogas plant and its components

starting the plant


  • Filling the plant


  • Training the user


-> Back to "Biogas Portal"