= Overview =
 
= Overview =
  
The checklist for the construction of a biogas plant is summarized below
+
The checklist for the construction of a biogas plant is summarized below.
  
 
<br/>
 
<br/>
*'''Planning of the Biogas Plant'''
 
 
i.e. [[Siting of the Biogas Unit|site evaluation]], [[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield, [[Sizing of the Biogas Plant|plant sizing]], selection of plant [[Types of Biogas Digesters and Plants#Biogas Plant Types and Design|design]], how and where to use the biogas, etc., in accordance with the [[Planning Guide for Biogas Plants|planning guide]]
 
  
 +
= Checklist for the Construction =
 +
<ul>
 +
<li><u>'''Planning of the Biogas Plant'''</u><ul style="margin-left: 40px;">
 +
<li>i.e. [[Siting of the Biogas Unit|site evaluation]], </li>
 +
<li>[[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield, </li>
 +
<li>[[Sizing of the Biogas Plant|plant sizing]], </li>
 +
<li>selection of plant [[Types of Biogas Digesters and Plants#Biogas Plant Types and Design|design]], </li>
 +
<li>how and where to use the biogas, etc., in accordance with the [[Planning Guide for Biogas Plants|planning guide]]</li>
 +
</ul>
 +
</li>
 +
</ul>
 +
<br/>
 +
<ul>
 +
<li><u>'''Stipulate the plant's location and elaborate a site plan'''</u><ul style="margin-left: 40px;">
 +
<li>including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry</li>
 +
</ul>
 +
</li>
 +
</ul>
 +
<br/>
 +
<ul>
 +
<li><u>'''Draft a technical drawing showing all plant components'''</u><ul style="margin-left: 40px;">
 +
<li>i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage</li>
 +
</ul>
 +
</li>
 +
</ul>
 
<br/>
 
<br/>
*'''Stipulate the plant's location and elaborate a site plan'''
+
<ul>
 
+
<li><u>'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':</u><ul style="margin-left: 40px;">
including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry
+
<li>bricks / stones / blocks for walls and foundation<br/></li>
 
+
<li>sand, gravel<br/></li>
 +
<li>inlet / outlet pipes<br/></li>
 +
<li>metal parts (sheet metal, angle irons, etc.)<br/></li>
 +
<li>gas pipes and fittings<br/></li>
 +
<li>paint and sealants<br/></li>
 +
<li>gas appliances<br/></li>
 +
<li>tools<br/></li>
 +
<li>mason and helper<br/></li>
 +
<li>unskilled labor<br/></li>
 +
<li>workshop for metal (gas-holder) and pipe installation<br/></li>
 +
</ul>
 +
</li>
 +
</ul>
 
<br/>
 
<br/>
*'''Draft a technical drawing showing all plant components'''
+
<ul>
 
+
<li><u>'''Material / personnel assignment planning''', i.e. procedural planning and execution of:</u><ul style="margin-left: 40px;">
i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage
+
<li>excavation<br/></li>
 
+
<li>foundation slab<br/></li>
 +
<li>digester masonry<br/></li>
 +
<li>gasholder<br/></li>
 +
<li>rendering and sealing the masonry<br/></li>
 +
<li>mixing pit - slurry storage pit<br/></li>
 +
<li>drying out the plant<br/></li>
 +
<li>installing the gas pipe<br/></li>
 +
<li>acceptance inspection<br/></li>
 +
</ul>
 +
</li>
 +
</ul>
 
<br/>
 
<br/>
*'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':
+
<ul>
 
+
<li><u>'''Regular building supervision''' '''Commissioning'''</u><ul style="margin-left: 40px;">
bricks / stones / blocks for walls and foundation<br/>
+
<li>functional inspection of the biogas plant and its components<br/></li>
 
+
<li>starting the plant<br/></li>
sand, gravel<br/>
+
</ul>
 
+
</li>
inlet / outlet pipes<br/>
+
</ul>
 
 
metal parts (sheet metal, angle irons, etc.)<br/>
 
 
 
gas pipes and fittings<br/>
 
 
 
paint and sealants<br/>
 
 
 
gas appliances<br/>
 
 
 
tools<br/>
 
 
 
mason and helper<br/>
 
 
 
unskilled labor<br/>
 
 
 
workshop for metal (gas-holder) and pipe installation<br/>
 
 
 
 
<br/>
 
<br/>
*'''Material / personnel assignment planning''', i.e. procedural planning and execution of:
+
*<u>'''Filling the plant'''</u>
  
excavation<br/>
+
'''​'''<br/>
 
+
*<u>'''Training the user'''</u>
foundation slab<br/>
 
 
 
digester masonry<br/>
 
 
 
gasholder<br/>
 
 
 
rendering and sealing the masonry<br/>
 
 
 
mixing pit - slurry storage pit<br/>
 
 
 
drying out the plant<br/>
 
 
 
installing the gas pipe<br/>
 
 
 
acceptance inspection<br/>
 
  
 
<br/>
 
<br/>
*'''Regular building supervision''' '''Commissioning'''
 
  
functional inspection of the biogas plant and its components<br/>
+
= Further Information =
 
+
</div>
starting the plant<br/>
+
*[[Portal:Biogas|Biogas Portal on energypedia]]<br/>
 +
*[[Checklist_for_the_Planning_of_a_Biogas_Plant|Checklist for the Planning of a Biogas Plant]]
  
<br/>
 
*'''Filling the plant'''
 
  
'''​'''<br/>
 
*'''Training the user'''
 
  
<br/>
+
= References =
</div>
 
[[Portal:Biogas|-> Back to "Biogas Portal"]]<br/>
 
  
<br/>
+
<references /><br/>
  
 
[[Category:Biogas]]
 
[[Category:Biogas]]

Revision as of 12:14, 16 October 2014

Overview

The checklist for the construction of a biogas plant is summarized below.


Checklist for the Construction


  • Stipulate the plant's location and elaborate a site plan
    • including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry


  • Draft a technical drawing showing all plant components
    • i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage


  • Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant:
    • bricks / stones / blocks for walls and foundation
    • sand, gravel
    • inlet / outlet pipes
    • metal parts (sheet metal, angle irons, etc.)
    • gas pipes and fittings
    • paint and sealants
    • gas appliances
    • tools
    • mason and helper
    • unskilled labor
    • workshop for metal (gas-holder) and pipe installation


  • Material / personnel assignment planning, i.e. procedural planning and execution of:
    • excavation
    • foundation slab
    • digester masonry
    • gasholder
    • rendering and sealing the masonry
    • mixing pit - slurry storage pit
    • drying out the plant
    • installing the gas pipe
    • acceptance inspection


  • Regular building supervision Commissioning
    • functional inspection of the biogas plant and its components
    • starting the plant


  • Filling the plant


  • Training the user