Checklist for the Construction of a Biogas Plant

From energypedia
Revision as of 12:14, 16 October 2014 by ***** (***** | *****)

Overview

The checklist for the construction of a biogas plant is summarized below.


Checklist for the Construction


  • Stipulate the plant's location and elaborate a site plan
    • including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry


  • Draft a technical drawing showing all plant components
    • i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage


  • Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant:
    • bricks / stones / blocks for walls and foundation
    • sand, gravel
    • inlet / outlet pipes
    • metal parts (sheet metal, angle irons, etc.)
    • gas pipes and fittings
    • paint and sealants
    • gas appliances
    • tools
    • mason and helper
    • unskilled labor
    • workshop for metal (gas-holder) and pipe installation


  • Material / personnel assignment planning, i.e. procedural planning and execution of:
    • excavation
    • foundation slab
    • digester masonry
    • gasholder
    • rendering and sealing the masonry
    • mixing pit - slurry storage pit
    • drying out the plant
    • installing the gas pipe
    • acceptance inspection


  • Regular building supervision Commissioning
    • functional inspection of the biogas plant and its components
    • starting the plant


  • Filling the plant


  • Training the user


Further Information


References