Difference between revisions of "Expanding mini-grids during Covid-19 – Experiences from Kalobeyei"

From energypedia
***** (***** | *****)
***** (***** | *****)
Line 11: Line 11:
  
 
<br/>
 
<br/>
 +
  
  
Line 21: Line 22:
 
They&nbsp;provide 60kWp&nbsp;with 120kWh storage&nbsp;in the settlement, and 20kWp&nbsp;with&nbsp;60kWh storage&nbsp;in the host town.&nbsp;A&nbsp;100kVA&nbsp;diesel-generator serves&nbsp;as&nbsp;back-up&nbsp;for the mini-grid in the settlement and was&nbsp;sized based on estimated consumption patterns.&nbsp;All demand sites in the settlement are spread around 4km², with the&nbsp;distribution lines extending&nbsp;to&nbsp;Xkm&nbsp;and covering&nbsp;customers&nbsp;in&nbsp;proximity to the&nbsp;mini-grids.&nbsp;Customers can activate via pre-paid tokens&nbsp;their&nbsp;electricity supply and&nbsp;have&nbsp;meters that&nbsp;measure consumption.&nbsp;In the initial operation period,&nbsp;average&nbsp;monthly&nbsp;electricity&nbsp;consumption&nbsp;of&nbsp;households in&nbsp;settlement and host town&nbsp;experienced&nbsp;a nearly&nbsp;six-fold rise&nbsp;and&nbsp;stands&nbsp;currently&nbsp;at&nbsp;about&nbsp;6kWh&nbsp;for both.&nbsp;This shows the contribution of the mini-grids&nbsp;in&nbsp;improving&nbsp;the&nbsp;energy access&nbsp;of&nbsp;previously excluded populations&nbsp;as&nbsp;well as&nbsp;the&nbsp;existence of demand for high-tier electricity supply.<br/>
 
They&nbsp;provide 60kWp&nbsp;with 120kWh storage&nbsp;in the settlement, and 20kWp&nbsp;with&nbsp;60kWh storage&nbsp;in the host town.&nbsp;A&nbsp;100kVA&nbsp;diesel-generator serves&nbsp;as&nbsp;back-up&nbsp;for the mini-grid in the settlement and was&nbsp;sized based on estimated consumption patterns.&nbsp;All demand sites in the settlement are spread around 4km², with the&nbsp;distribution lines extending&nbsp;to&nbsp;Xkm&nbsp;and covering&nbsp;customers&nbsp;in&nbsp;proximity to the&nbsp;mini-grids.&nbsp;Customers can activate via pre-paid tokens&nbsp;their&nbsp;electricity supply and&nbsp;have&nbsp;meters that&nbsp;measure consumption.&nbsp;In the initial operation period,&nbsp;average&nbsp;monthly&nbsp;electricity&nbsp;consumption&nbsp;of&nbsp;households in&nbsp;settlement and host town&nbsp;experienced&nbsp;a nearly&nbsp;six-fold rise&nbsp;and&nbsp;stands&nbsp;currently&nbsp;at&nbsp;about&nbsp;6kWh&nbsp;for both.&nbsp;This shows the contribution of the mini-grids&nbsp;in&nbsp;improving&nbsp;the&nbsp;energy access&nbsp;of&nbsp;previously excluded populations&nbsp;as&nbsp;well as&nbsp;the&nbsp;existence of demand for high-tier electricity supply.<br/>
  
Given this success, ESDS Kenya, acting complementary to EnDev, is commissioned to facilitate the expansion of the mini-grids into the Villages 2 and 3 of the Kalobeyei Settlement. This takes place in close coordination with the Turkana County government and serves its Kalobeyei Integrated Socio-Economic Development Plan (KISEDP). As [https://bit.ly/3lxePsb market-studies] by EnDev suggested that the majority of refugee households cannot afford the current, already subsidized tariff, financing schemes are being explored as support measures to reach a broad consumer base. As a second pillar of its activities, ESDS Kenya assists UNHCR in its transition towards a cleaner energy supply by supporting the solarization of the infrastructure of the facilities it maintains in Kalobeyei and Kakuma.
+
Given this success,&nbsp;ESDS Kenya, acting complementary to&nbsp;EnDev,&nbsp;is&nbsp;commissioned&nbsp;by the BMZ&nbsp;to facilitate the expansion of the&nbsp;mini-grids&nbsp;into the Villages 2 and 3 of the Kalobeyei Settlement.&nbsp;This takes place in coordination with the Turkana&nbsp;County government and serves its Kalobeyei Integrated Socio-Economic Development Plan (KISEDP).&nbsp;As market-studies by&nbsp;EnDev&nbsp;suggested that the&nbsp;majority of&nbsp;refugee&nbsp;households&nbsp;cannot afford the current, already subsidized&nbsp;tariff, financing schemes are being explored as support measures&nbsp;to reach&nbsp;a broader&nbsp;consumer base.&nbsp;As a second pillar of its activities, ESDS Kenya assists UNHCR in its&nbsp;transition towards a cleaner energy supply by supporting the solarization of&nbsp;its&nbsp;infrastructure&nbsp;in Kalobeyei and Kakuma&nbsp;and enacting energy efficiency measures&nbsp;through technical&nbsp;and legal&nbsp;assessments.&nbsp;<br/>
  
However, the outbreak of COVID-19 necessitated an adjustment to these plans: With the objective to provide immediate and high-impact support to Kalobeyei’s inhabitants, ESDS Kenya prioritized the connection of facilities to the mini-grids that reinforce response measures to the pandemic. This included 3 health facilities, 2 in the settlement and one in the host town, 4 learning institutions in the settlement that serve as isolation centers, and a WFP horticultural farm that sustains the food supply.
+
However, the outbreak of COVID-19&nbsp;necessitated an adjustment to&nbsp;these&nbsp;plans:&nbsp;With the objective to provide&nbsp;immediate&nbsp;and&nbsp;high-impact support&nbsp;to&nbsp;Kalobeyei’s inhabitants,&nbsp;ESDS Kenya prioritized&nbsp;the connection of&nbsp;critical&nbsp;facilities&nbsp;to the mini-grids&nbsp;that&nbsp;reinforce&nbsp;response measures&nbsp;to the pandemic.&nbsp;In discussion with UNHCR,&nbsp;it&nbsp;was decided to electrify&nbsp;3 health&nbsp;clinics,&nbsp;2 in the settlement and&nbsp;1&nbsp;in the host town,&nbsp;4 learning institutions in the settlement&nbsp;that serve as isolation&nbsp;centers, and a WFP horticultural farm&nbsp;that&nbsp;supports&nbsp;food&nbsp;security.&nbsp;For all facilities, the&nbsp;ESDS’&nbsp;team conducted rapid need&nbsp;assessments&nbsp;and&nbsp;designed the technical systems&nbsp;before the construction&nbsp;work for the distribution lines was&nbsp;tendered&nbsp;in a fast-tracked process.<br/>
  
These measures improve the preparedness of the Kalobeyei Settlements and Host Community Town to COVID-19 and are being/could be completed despite the restrictions on movement and interaction put in place by authorities. With the first infection reported on 25th May 2020 in Kakuma and Kalobeyei, the connected facilities take a significant role in curbing the spread of the virus and keeping the situation under control.
+
These measures improve the preparedness of the Kalobeyei Settlements and Host Community Town to&nbsp;Covid-19&nbsp;and&nbsp;were&nbsp;completed despite the restrictions on movement and interaction put in place by authorities. With the&nbsp;first infection reported on 25th&nbsp;May 2020&nbsp;in Kakuma and Kalobeyei, the&nbsp;connected facilities&nbsp;take a significant role in curbing the spread of the virus and&nbsp;contribute to response measures of authorities.&nbsp;Notwithstanding the fact that the mini-grid connection of the facilities&nbsp;took place under light of the pandemic, the impact of&nbsp;their&nbsp;electrification&nbsp;goes beyond&nbsp;Covid-19.&nbsp;It&nbsp;improves health&nbsp;and education&nbsp;services,&nbsp;offers&nbsp;learning&nbsp;opportunities&nbsp;and&nbsp;sustains&nbsp;the food supply&nbsp;in&nbsp;Kalobeyei&nbsp;for refugees and host community. Their&nbsp;access to sustainable energy&nbsp;enhances&nbsp;their&nbsp;self-reliance and quality of life&nbsp;which&nbsp;contribute to&nbsp;ESDS’ broader objectives.&nbsp;<br/>
  
Notwithstanding the fact that the mini-grid connection of the facilitates took place under light of the pandemic, the impact of these activities goes beyond it. The electricity-access of the facilities improves health care services and offers learning opportunities for refugee and host community households that enhance the quality of life for the inhabitants of Kalobeyei.
+
However,&nbsp;it must be noted that during&nbsp;the&nbsp;implementation&nbsp;two main challenges&nbsp;were&nbsp;identified: First, despite&nbsp;accelerating the&nbsp;process,&nbsp;it took 5 months from initial request to completion&nbsp;which signifies the difficulties for&nbsp;development cooperation organisation&nbsp;like GIZ&nbsp;to provide short-term emergency response measures.&nbsp;This shows the&nbsp;potential of&nbsp;conceptualizing&nbsp;scalable solutions that can&nbsp;be&nbsp;rapidly deployed&nbsp;and&nbsp;dismantled,&nbsp;e.g.&nbsp;containerized&nbsp;system, in emergency situations, which,&nbsp;however,&nbsp;must be differentiated from development efforts. This&nbsp;demonstrates the&nbsp;clear delimitations between humanitarian and development&nbsp;projects and links&nbsp;to&nbsp;the second&nbsp;encountered&nbsp;challenge, that is&nbsp;the&nbsp;sustainability of&nbsp;rapid response measures.&nbsp;In&nbsp;the case of Kalobeyei,&nbsp;it was not possible to conceptualize&nbsp;a&nbsp;self-sustaining&nbsp;business model for the&nbsp;operation and maintenance of the distribution lines&nbsp;prior to their installation&nbsp;which&nbsp;still relies on ESDS Kenya’s support.&nbsp;This opens the questions how response measures providing immediate relief can be reconciled with&nbsp;sustainability.&nbsp;<br/>
  
In subsequent steps, ESDS Kenya will work towards sustaining the operation and maintenance of the distribution lines with private sector involvement and refocus its attention to upscaling the mini-grids by connecting additional customers in the other villages of the settlement and making the electricity more affordable.<br/>
+
These are the&nbsp;next steps&nbsp;ESDS Kenya&nbsp;will&nbsp;work towards, that is&nbsp;sustaining&nbsp;the&nbsp;distribution lines&nbsp;to ensure their functioning long-term wise. Moreover,&nbsp;once&nbsp;pandemic-related restrictions allow, the team will&nbsp;refocus&nbsp;its attention&nbsp;to&nbsp;its initial plans&nbsp;of&nbsp;connecting&nbsp;additional&nbsp;customers&nbsp;in the other villages of the settlement&nbsp;to the mini-grids.&nbsp;<br/>
  
 +
[[Category:Kenya]]
 +
[[Category:Mini-grid]]
 
[[Category:Humanitarian_Energy]]
 
[[Category:Humanitarian_Energy]]
[[Category:Mini-grid]]
 
[[Category:Kenya]]
 

Revision as of 07:01, 12 October 2020

Template:ESDS back to link

Overview [Draft]

In the Kalobeyei Settlement and host community town, ESDS Kenya supported the Covid-19 response measures of local authorities and UNHCR by electrifying facilities that enhance efforts to contain the pandemic. In total, 3 health facilities, providing medical services to refugees and the host community, 4 schools, earmarked as isolation centers, and 1 horticultural farm run by WFP which sustains the food supply were connected to two mini-grids in the Kalobeyei Settlement and Town. As rapid response measure, they have an immediate impact on mitigating Covid-19, while they also improve the energy services in Kalobeyei beyond the pandemic and align with the broader objective of ESDS.


Mini-Grid in Kalobeyei.Source: Renewvia Energy





Article

The Kakuma Refugee Camp and the Kalobeyei Integrated Settlement, located in Turkana County at the north-western border of Kenya, currently host close to 200,000 refugees from Eastern and Central Africa. Albeit donors and humanitarian organizations installed mini-grids and the nearby Kakuma town is connected to a sub-station of the national grid, only 5 percentage of households in the camps had reliable access to electricity in 2019 according to UNHCR, while many systems, including the sub-station, run on diesel generators.

To remedy this situation and as part of its efforts facilitate the market-entry of the private sector in providing sustainable energy, EnDev supported the installation of two mini-grids in the Kalobeyei Settlement Village 1 and Host Community Town in cooperation with national and local authorities and UNHCR. The mini-grids are run by a private company on a self-sustaining business model and provide electricity for households from the refugee and host community, SMEs and social institutions at a tariff close to the national level. This was achieved by offering a grant to cover a portion of the capital investment and Results-based Financing (RBF) to the operating company. Since September 2019, both mini-grids are operational and serve close to 600 households, businesses and social institutions. 

They provide 60kWp with 120kWh storage in the settlement, and 20kWp with 60kWh storage in the host town. A 100kVA diesel-generator serves as back-up for the mini-grid in the settlement and was sized based on estimated consumption patterns. All demand sites in the settlement are spread around 4km², with the distribution lines extending to Xkm and covering customers in proximity to the mini-grids. Customers can activate via pre-paid tokens their electricity supply and have meters that measure consumption. In the initial operation period, average monthly electricity consumption of households in settlement and host town experienced a nearly six-fold rise and stands currently at about 6kWh for both. This shows the contribution of the mini-grids in improving the energy access of previously excluded populations as well as the existence of demand for high-tier electricity supply.

Given this success, ESDS Kenya, acting complementary to EnDev, is commissioned by the BMZ to facilitate the expansion of the mini-grids into the Villages 2 and 3 of the Kalobeyei Settlement. This takes place in coordination with the Turkana County government and serves its Kalobeyei Integrated Socio-Economic Development Plan (KISEDP). As market-studies by EnDev suggested that the majority of refugee households cannot afford the current, already subsidized tariff, financing schemes are being explored as support measures to reach a broader consumer base. As a second pillar of its activities, ESDS Kenya assists UNHCR in its transition towards a cleaner energy supply by supporting the solarization of its infrastructure in Kalobeyei and Kakuma and enacting energy efficiency measures through technical and legal assessments. 

However, the outbreak of COVID-19 necessitated an adjustment to these plans: With the objective to provide immediate and high-impact support to Kalobeyei’s inhabitants, ESDS Kenya prioritized the connection of critical facilities to the mini-grids that reinforce response measures to the pandemic. In discussion with UNHCR, it was decided to electrify 3 health clinics, 2 in the settlement and 1 in the host town, 4 learning institutions in the settlement that serve as isolation centers, and a WFP horticultural farm that supports food security. For all facilities, the ESDS’ team conducted rapid need assessments and designed the technical systems before the construction work for the distribution lines was tendered in a fast-tracked process.

These measures improve the preparedness of the Kalobeyei Settlements and Host Community Town to Covid-19 and were completed despite the restrictions on movement and interaction put in place by authorities. With the first infection reported on 25th May 2020 in Kakuma and Kalobeyei, the connected facilities take a significant role in curbing the spread of the virus and contribute to response measures of authorities. Notwithstanding the fact that the mini-grid connection of the facilities took place under light of the pandemic, the impact of their electrification goes beyond Covid-19. It improves health and education services, offers learning opportunities and sustains the food supply in Kalobeyei for refugees and host community. Their access to sustainable energy enhances their self-reliance and quality of life which contribute to ESDS’ broader objectives. 

However, it must be noted that during the implementation two main challenges were identified: First, despite accelerating the process, it took 5 months from initial request to completion which signifies the difficulties for development cooperation organisation like GIZ to provide short-term emergency response measures. This shows the potential of conceptualizing scalable solutions that can be rapidly deployed and dismantled, e.g. containerized system, in emergency situations, which, however, must be differentiated from development efforts. This demonstrates the clear delimitations between humanitarian and development projects and links to the second encountered challenge, that is the sustainability of rapid response measures. In the case of Kalobeyei, it was not possible to conceptualize a self-sustaining business model for the operation and maintenance of the distribution lines prior to their installation which still relies on ESDS Kenya’s support. This opens the questions how response measures providing immediate relief can be reconciled with sustainability. 

These are the next steps ESDS Kenya will work towards, that is sustaining the distribution lines to ensure their functioning long-term wise. Moreover, once pandemic-related restrictions allow, the team will refocus its attention to its initial plans of connecting additional customers in the other villages of the settlement to the mini-grids.