Difference between revisions of "Hydro - Environmental Impact Assessment (EIA)"

From energypedia
***** (***** | *****)
***** (***** | *****)
Line 1: Line 1:
 
  
 
= Introduction<br/> =
 
= Introduction<br/> =
Line 7: Line 6:
 
As a policy instrument the EIA ensures that the environmental implications of a project are anticipated and minimised. They are applied for all types of projects like infrastructure development, and also for hydropower projects. They might be applied on&nbsp;river basin scale in the case of cumulative Environmental Impact Assessments (CESIA). At European level the EIA Directive 2011/92/EU defines the frame for the application of EIAs.<br/>
 
As a policy instrument the EIA ensures that the environmental implications of a project are anticipated and minimised. They are applied for all types of projects like infrastructure development, and also for hydropower projects. They might be applied on&nbsp;river basin scale in the case of cumulative Environmental Impact Assessments (CESIA). At European level the EIA Directive 2011/92/EU defines the frame for the application of EIAs.<br/>
  
 +
<br/>
 +
 +
= Environmental Impact Assessment (EIA)<br/> =
 +
 +
“An Environmental Impact Assessment (EIA) is a systematic process used to identify, evaluate and mitigate the environmental effects of a '''proposed project''' prior to major decisions and commitments being made” (UNEP). It thus also figures as a means to ensure that projects are implemented with full awareness of environmental factors. An EIA normally results in an Environmental Management Plan (EMP) that elaborates mitigation and monitoring measures. In most industrialized countries EIAs are legally required when a proposed (hydropower) project exceeds a certain size.<br/>
 +
 +
<br/>
 +
 +
== EIA Procedure<br/> ==
 +
 +
Although EIA is a largely standardized approach, concrete implementation depends on the legal context and thus can differ in various countries. Figure 1 shows the European Union’s approach.<br/>
 +
 +
&nbsp;
 +
 +
[[File:|465x263px]]
 +
 +
'''Figure 1'''''': EU Procedure'''[https://energypedia.info/index.php?title=Hydro_-_Environmental_Impact_Assessment_(EIA)&action=edit&mode=wysiwyg#_ftn1 '''<u><font color="#0066cc">[1]</font></u>''']
 +
 +
&nbsp;
 +
 +
During screening it is determined whether or not a full EIA is to be carried out. The European EIA Directive (2011/92/EU, Art.5[https://energypedia.info/index.php?title=Hydro_-_Environmental_Impact_Assessment_(EIA)&action=edit&mode=wysiwyg#_ftn2 <u><font color="#0066cc">[2]</font></u>]), for example, always demands an EIA when storage or water held back by the dam project exceeds 10 million cubic meters (Annex I, 15). Another common approach is to classify dams into categories A, B or C, depending on type, location, sensitivity, and scale, as well as on the nature and magnitude of potential impacts, and then demand different depth of study (e.g. World Bank OP 4.01).
 +
 +
&nbsp;
 +
 +
During scoping stage content and level of detail of analysis is defined. The EU directive, for example, states as minimum information to provide:
 +
 +
&nbsp;
  
= Environmental Impacts of Small Hydro Power Projects<br/> =
+
#
 +
''a description of the project comprising information on the site, design, size and other relevant features of the project;''
 +
 
 +
#
 +
''a description of the likely significant effects of the project on the environment;''
 +
 
 +
#
 +
''a description of the features of the project and/or measures envisaged in order to avoid, prevent or reduce and, if possible, offset likely significant adverse effects on the environment;''
 +
 
 +
#
 +
''a description of the reasonable alternatives studied by the developer, which are relevant to the project and its specific characteristics, and an indication of the main reasons for the option chosen, taking into account the effects of the project on the environment;''
 +
 
 +
#
 +
''a non-technical summary of the information referred to in points (a) to (d)''
 +
 
 +
#
 +
''any additional information specified in Annex IV relevant to the specific characteristics of a particular project or type of project and to the environmental features likely to be affected.''
 +
 
 +
&nbsp;
 +
 
 +
EIAs are project-specific, predicting the potential outcomes of a certain project. The search for alternatives is therefore usually limited to&nbsp; technical design issues. Although the EU Directive demands the description of project alternatives, this is limited to those “''studied by the developer”'' (Article 5, 3d). Instruments that seek to include assessment of alternatives at the earliest appropriate stage of decision-making are the Strategic Environmental Assessment (SEA; see below) and Hydropower Sustainability Assessment Protocol (HSAP), where the Early-Stage Tool is of particular relevance for this aspect (->WIKI-LINK: HSAP). EIAs provide extensive public participation mechanisms during the whole process.
 +
 
 +
&nbsp;
  
Small, run-of-the-river projects are free from many of the environmental problems associated with their large-scale relatives because they use the natural flow of the river, and thus produce relatively little change in the stream channel and flow. The dams built for some run-of-the-river projects are very small and impound little water - and many projects do not require a dam at all. Thus, effects such as oxygen depletion, increased temperature, decreased flow, and rejection of upstream migration aids like fish ladders are not problems for many run-of-the-river projects<ref>Small Hydropower Systems (Dept. of Energy USA, 2001): http://www.nrel.gov/docs/fy01osti/29065.pdf</ref>.
+
Some finance institutes ask as part of their standard approval procedure EIAs to cover additional aspects that can go beyond legal requirements. The involvement of international finance institutes can therefore lead to the application of higher standards compared to non-involvement. Usually the project proponent has to pay for the study. In the case of the EU, EIAs[https://energypedia.info/index.php?title=Hydro_-_Environmental_Impact_Assessment_(EIA)&action=edit&mode=wysiwyg#_ftn3 <u><font color="#0066cc">[3]</font></u>] account for less than 1% of total project costs and take 1-2 years for completion[https://energypedia.info/index.php?title=Hydro_-_Environmental_Impact_Assessment_(EIA)&action=edit&mode=wysiwyg#_ftn4 <u><font color="#0066cc">[4]</font></u>].
  
 
<br/>
 
<br/>
 +
 +
= Cumulative Environmental Impact Assessment (CEIA)<br/> =
 +
 +
In combination with the impacts of other hydro projects within the same river basin, impacts can change or intensify. Therefore the scope of the impact assessment should not be limited to one project, but analyze the impacts with a view to other existing and planned projects. As an advanced version of an EIA, the Cumulative Environmental Impact Assessment (CEIA) seeks to incorporate these effects into the assessment ''of a proposed project''. It therefore enlarges the scale of analysis to regional river basin level.<br/>
 +
 +
Up to date the CEIA as instrument is restricted on large hydropower and is not applycated to small hydro.<br/>
  
 
<br/>
 
<br/>
  
 +
= Environmental Impacts of Small Hydro Power Projects<br/> =
  
 +
Small, run-of-the-river projects are free from many of the environmental problems associated with their large-scale relatives because they use the natural flow of the river, and thus produce relatively little change in the stream channel and flow. The dams built for some run-of-the-river projects are very small and impound little water - and many projects do not require a dam at all. Thus, effects such as oxygen depletion, increased temperature, decreased flow, and rejection of upstream migration aids like fish ladders are not problems for many run-of-the-river projects<ref>Small Hydropower Systems (Dept. of Energy USA, 2001): http://www.nrel.gov/docs/fy01osti/29065.pdf</ref>.<br/>
  
 +
<br/>
 +
 +
<br/>
  
 
= Case Studies =
 
= Case Studies =
Line 25: Line 84:
 
This paper outlines the advantages of SHP, barriers in the development of SHP, EIA process in India, regulatory framework, EIA of SHP projects, case studies of EIA of six SHP projects in the state of Uttarakhand, their impacts on ecological resources & human environment and EMP. It is concluded that there has been low to medium impacts of the projects on the surrounding environment.<br/>
 
This paper outlines the advantages of SHP, barriers in the development of SHP, EIA process in India, regulatory framework, EIA of SHP projects, case studies of EIA of six SHP projects in the state of Uttarakhand, their impacts on ecological resources & human environment and EMP. It is concluded that there has been low to medium impacts of the projects on the surrounding environment.<br/>
  
 +
<br/>
  
 
= Further Information<br/> =
 
= Further Information<br/> =
Line 38: Line 98:
 
<br/>
 
<br/>
  
= References =
+
= References<br/> =
  
<references />
+
<references /><br/>
 +
<div><br/>
 +
----
 +
<div id="ftn1">
 +
[https://energypedia.info/index.php?title=Hydro_-_Environmental_Impact_Assessment_(EIA)&action=edit&mode=wysiwyg#_ftnref1 <u><font color="#0066cc">[1]</font></u>] http://ec.europa.eu/environment/legal/law/pdf/eia/2%20EIA%20%20SEA%20Intro%20final.pdf
 +
</div><div id="ftn2">
 +
[https://energypedia.info/index.php?title=Hydro_-_Environmental_Impact_Assessment_(EIA)&action=edit&mode=wysiwyg#_ftnref2 <u><font color="#0066cc">[2]</font></u>] http://ec.europa.eu/environment/eia/eia-legalcontext.htm
 +
</div><div id="ftn3">
 +
[https://energypedia.info/index.php?title=Hydro_-_Environmental_Impact_Assessment_(EIA)&action=edit&mode=wysiwyg#_ftnref3 <u><font color="#0066cc">[3]</font></u>] figure not hydropower-specific.
 +
</div><div id="ftn4">
 +
[https://energypedia.info/index.php?title=Hydro_-_Environmental_Impact_Assessment_(EIA)&action=edit&mode=wysiwyg#_ftnref4 <u><font color="#0066cc">[4]</font></u>][http://ec.europa.eu/environment/eia/pdf/Costs%20and%20benefits%20of%20the%20EIA%20Directive.pdf <u><font color="#0066cc">http://ec.europa.eu/environment/eia/pdf/Costs%20and%20benefits%20of%20the%20EIA%20Directive.pdf</font></u>]<br/>
 +
</div></div>
  
 +
[[Category:Impacts]]
 +
[[Category:Impacts_Environmental]]
 +
[[Category:Small-Hydro/Mini-Hydro]]
 
[[Category:Hydro]]
 
[[Category:Hydro]]
[[Category:Small-Hydro/Mini-Hydro]]
 
[[Category:Impacts_Environmental]]
 
[[Category:Impacts]]
 

Revision as of 13:40, 22 April 2015

Introduction

An environmental impact assessment (EIA) is an assessment of the possible impact - positive or negative - that a proposed project may have on the environment, considering natural, social and economic aspects. The purpose of the assessment is to ensure that decision makers consider the ensuing environmental impacts to decide whether to proceed with the project.

As a policy instrument the EIA ensures that the environmental implications of a project are anticipated and minimised. They are applied for all types of projects like infrastructure development, and also for hydropower projects. They might be applied on river basin scale in the case of cumulative Environmental Impact Assessments (CESIA). At European level the EIA Directive 2011/92/EU defines the frame for the application of EIAs.


Environmental Impact Assessment (EIA)

“An Environmental Impact Assessment (EIA) is a systematic process used to identify, evaluate and mitigate the environmental effects of a proposed project prior to major decisions and commitments being made” (UNEP). It thus also figures as a means to ensure that projects are implemented with full awareness of environmental factors. An EIA normally results in an Environmental Management Plan (EMP) that elaborates mitigation and monitoring measures. In most industrialized countries EIAs are legally required when a proposed (hydropower) project exceeds a certain size.


EIA Procedure

Although EIA is a largely standardized approach, concrete implementation depends on the legal context and thus can differ in various countries. Figure 1 shows the European Union’s approach.

 

[[File:|465x263px]]

'Figure 1': EU Procedure[1]

 

During screening it is determined whether or not a full EIA is to be carried out. The European EIA Directive (2011/92/EU, Art.5[2]), for example, always demands an EIA when storage or water held back by the dam project exceeds 10 million cubic meters (Annex I, 15). Another common approach is to classify dams into categories A, B or C, depending on type, location, sensitivity, and scale, as well as on the nature and magnitude of potential impacts, and then demand different depth of study (e.g. World Bank OP 4.01).

 

During scoping stage content and level of detail of analysis is defined. The EU directive, for example, states as minimum information to provide:

 

a description of the project comprising information on the site, design, size and other relevant features of the project;

a description of the likely significant effects of the project on the environment;

a description of the features of the project and/or measures envisaged in order to avoid, prevent or reduce and, if possible, offset likely significant adverse effects on the environment;

a description of the reasonable alternatives studied by the developer, which are relevant to the project and its specific characteristics, and an indication of the main reasons for the option chosen, taking into account the effects of the project on the environment;

a non-technical summary of the information referred to in points (a) to (d)

any additional information specified in Annex IV relevant to the specific characteristics of a particular project or type of project and to the environmental features likely to be affected.

 

EIAs are project-specific, predicting the potential outcomes of a certain project. The search for alternatives is therefore usually limited to  technical design issues. Although the EU Directive demands the description of project alternatives, this is limited to those “studied by the developer” (Article 5, 3d). Instruments that seek to include assessment of alternatives at the earliest appropriate stage of decision-making are the Strategic Environmental Assessment (SEA; see below) and Hydropower Sustainability Assessment Protocol (HSAP), where the Early-Stage Tool is of particular relevance for this aspect (->WIKI-LINK: HSAP). EIAs provide extensive public participation mechanisms during the whole process.

 

Some finance institutes ask as part of their standard approval procedure EIAs to cover additional aspects that can go beyond legal requirements. The involvement of international finance institutes can therefore lead to the application of higher standards compared to non-involvement. Usually the project proponent has to pay for the study. In the case of the EU, EIAs[3] account for less than 1% of total project costs and take 1-2 years for completion[4].


Cumulative Environmental Impact Assessment (CEIA)

In combination with the impacts of other hydro projects within the same river basin, impacts can change or intensify. Therefore the scope of the impact assessment should not be limited to one project, but analyze the impacts with a view to other existing and planned projects. As an advanced version of an EIA, the Cumulative Environmental Impact Assessment (CEIA) seeks to incorporate these effects into the assessment of a proposed project. It therefore enlarges the scale of analysis to regional river basin level.

Up to date the CEIA as instrument is restricted on large hydropower and is not applycated to small hydro.


Environmental Impacts of Small Hydro Power Projects

Small, run-of-the-river projects are free from many of the environmental problems associated with their large-scale relatives because they use the natural flow of the river, and thus produce relatively little change in the stream channel and flow. The dams built for some run-of-the-river projects are very small and impound little water - and many projects do not require a dam at all. Thus, effects such as oxygen depletion, increased temperature, decreased flow, and rejection of upstream migration aids like fish ladders are not problems for many run-of-the-river projects[1].



Case Studies

This paper outlines the advantages of SHP, barriers in the development of SHP, EIA process in India, regulatory framework, EIA of SHP projects, case studies of EIA of six SHP projects in the state of Uttarakhand, their impacts on ecological resources & human environment and EMP. It is concluded that there has been low to medium impacts of the projects on the surrounding environment.


Further Information


References

  1. Small Hydropower Systems (Dept. of Energy USA, 2001): http://www.nrel.gov/docs/fy01osti/29065.pdf