Overview

Name of the site: Ocote Tuma
Country: Nicaragua (GPS Coordinates: ?)
Turbine Type: Pelton
Power Output: 30 kW
Project Status: in operation
Comments: -




Operation Data

Gross Head:
Net/Design Head:
Flow (design flow):
Comments on flow variation during the year:




Technical Information

Comments:


Civil Works and Penstock

Dam construction material: Concrete
Dam Dimensions: -
Storage Volume Reservoir: -
Sedimentation Basin material: not available
Sedimentation Basin Dimensions:
Penstock Length: -
Penstock Diameter at Beginning: 6"
Penstock Diameter at End: 6"
Penstock Changes of Diameter: 0
Penstock Material: PVC
Security Valve: yes

Electromechanical Equipment

Turbine

Turbine Type: Pelton, 1 injector
Turbine Diameter:
Turbine Material: Bronce
Turbine Manufacturer: Nica Bosch (Contact: company does not exist any more)
Potencial (nominal):
Rated Head:
Rated Flow:
Rated Speed:
Runaway Speed:
Shaft diameter and material:
Direction of Rotation: clockwise
Orientation of Shaft: horizontal

Generator:

Generator Manufacturer and Model: Stamford
Phases: 3
Potencial (nominal):
Nominal voltage: 120 / 240 V
Nominal Speed: 1800 rpm
Frequency: 60 Hz
Isolation Class: H

Mechanical Transmission / Coupling

Type of Belt: Abasic Plana
Belt Manufacturer: Centro de Rodamientos
Distance between Pulleys:
Diameter of Generator Pulley:
Diameter of Generator Pulley:

Control System

Control System Manufacturer and Model: No control system, manual flow control
Type of Control:
Capacity:


Electrical Transmission

Mini Grid: yes
Connection to national Grid: no
Grid Voltage: 240 / 120 V
Diameter of Conductor: Triplex No.4
Transformer Rating:


Economic Information

Developer: (Contact: )
Start of Construction:
Date of Commissioning:
Ownership / Operation Model:
Operator:
Tariff structure:
Connected Housholds: 55
Connection Cost Cost to be covered by houshold:
Overall Project Costs:





Project Photos

OcoteTuma.JPG


OcoteTuma
OcoteTuma
OcoteTuma