Difference between revisions of "Micro Hydro Power in Leku, Ethiopia"

From energypedia
***** (***** | *****)
***** (***** | *****)
m
Line 1: Line 1:
  
= <span id="Overview" class="mw-headline">Overview </span><br/> =
+
= Overview<br/> =
  
 
<u>Location of the '''Micro Hydro Power (MHP)''' site:</u>
 
<u>Location of the '''Micro Hydro Power (MHP)''' site:</u>
Line 25: Line 25:
 
<br/>
 
<br/>
  
 
+
= Details<br/> =
 
 
 
 
= <span class="mw-headline" id="Details">Details </span><br/> =
 
  
 
The MHP plant Leku has a capacity of 20 kW and is planned to be inaugurated in beginning of 2016. A total of approximately 200 households will be connected to the plant, in addition to social institutions for example: a mosque, a school, a commercial center, a health center, a Farmers Training Center (FTC), a co-operative office and a grain mill owned by Chokerisa Kenisa Leku co-operative.<br/>
 
The MHP plant Leku has a capacity of 20 kW and is planned to be inaugurated in beginning of 2016. A total of approximately 200 households will be connected to the plant, in addition to social institutions for example: a mosque, a school, a commercial center, a health center, a Farmers Training Center (FTC), a co-operative office and a grain mill owned by Chokerisa Kenisa Leku co-operative.<br/>
Line 45: Line 42:
 
<br/>
 
<br/>
  
 +
= Pictures<br/> =
  
= Pictures<br/> =
 
 
{|
 
{|
 
|-
 
|-
| [[File:Generator Leku.jpg|border|330px| Generator Leku]]<br/>
+
| [[File:Generator Leku.jpg|thumb|right|330pxpx|Generator used at MHP Leku|alt=Generator Leku]]<br/>
 
|  
 
|  
 
+
[[File:PH and Penstock.jpg|thumb|right|400pxpx|PH and Penstock|alt=PH and Penstock.jpg]]<br/>
[[File:PH and Penstock.jpg|border|400px|PH and Penstock.jpg]]<br/>
 
  
 
|-
 
|-
| [[File:River Leku.jpg|border|330px|River Leku.jpg]]<br/>
+
| [[File:River Leku.jpg|thumb|right|330pxpx|River Leku|alt=River Leku.jpg]]<br/>
| [[File:Turbine Leku.jpg|border|400px|Turbine Leku.jpg]]
+
| [[File:Turbine Leku.jpg|thumb|right|400pxpx|Turbine used in MHP Leku|alt=Turbine Leku.jpg]]
 
|}
 
|}
 +
 +
= Further Information =
 +
 +
*[[Portal:Hydro|Hydro portal on energypedia]]
 +
 +
[[Category:Hydro]]
 +
[[Category:Micro-Hydro/Pico-Hydro]]

Revision as of 07:31, 11 August 2015

Overview

Location of the Micro Hydro Power (MHP) site:

  • Country: Ethiopia Energy Situation
  • District: Jimma
  • River: Boru river
  • GPS Coordinates: Between 7o17’ & 7o44’ North and between 36o17’& 36o


Background

Leku Migira Mill Upgrading Project is located on the Boru River in Jimma zone. The project seeks to re-develop an existing water mill scheme into dual purpose mechanical mill facility as productive use as well as electrical power generation plant. It is located in the Oromia regional state, Jimma zone, Shebe Sombo woreda.

The economic base of the Leku Migira kebele is directly linked to agriculture, mainly production of coffee and maize. A total population of about 3,985 is living in the kebele within 782 households in 25 smaller neighborhoods (gares). This project at its full capacity will benefit about 200 households.


Objective

The general objective of the project is to incorporate into the existing traditional watermill plant, electric generating facility to provide modern clean, affordable and sustainable energy for the kebele. In addition, the project aims to improve the living standard of inhabitants in the kebele.


Details

The MHP plant Leku has a capacity of 20 kW and is planned to be inaugurated in beginning of 2016. A total of approximately 200 households will be connected to the plant, in addition to social institutions for example: a mosque, a school, a commercial center, a health center, a Farmers Training Center (FTC), a co-operative office and a grain mill owned by Chokerisa Kenisa Leku co-operative.


  • Start of construction: December 2013
  • Date of Commissioning: Planned for beginning of 2016
  • Ownership / Operation Modell: The MHP plant is to be owned and operated by the local community
  • Tariff structure: Not yet derived
  • Turbine: T-12 cross flow turbine
  • Generator: Three phase synchronous generator/20kW
  • Electric load controller capacity: 20 kW
  • Transmission line type/length: Aluminum cable/3300m


Pictures

Generator Leku
Generator used at MHP Leku

PH and Penstock.jpg
PH and Penstock

River Leku.jpg
River Leku

Turbine Leku.jpg
Turbine used in MHP Leku

Further Information