Small Hydropower Promotion Project (SHPP) - support from water to wire

From energypedia
Revision as of 09:32, 18 August 2011 by ***** (***** | *****)

Small Hydropower Promotion Project (SHPP) - support from "water to wire"

The Small Hydropower Promotion Project (SHPP) was implemented in the year 2000. After ten years of promoting small hydropower in Nepal, the project was phased out at the end of 2010. Throughout the three phases of SHPP’s implementation the project’s objective was:

  • Phase 1: The demand for small hydropower stations of the rural population to improve the economic and social living conditions is satisfied through investments in this sector.
  • Phase 2: A market for the development and rehabilitation of small hydropower stations is established and supports the economic activities of stakeholders.
  • Phase 3: The continuous dissemination of small hydropower sites secures the energy supply in rural areas of Nepal.


SHPP has thus continuously worked on the improvement of the small hydropower sector in Nepal, firstly focusing on subsectors of grid-interconnected small hydropower sites (below one MW as well as sites with a capacity of up to 10 MW). During the second and the third phases, SHPP also became engaged with small off-grid hydropower schemes by supporting the existing Alternative Energy Promotion Centre (AEPC LINK), and conducting feasibility studies

 

Background of the project

Nepal has an enormous hydropower potential with a theoretical generation capacity of 83,000 MW of which approximately 42,000 MW is economically feasible. From a technical perspective, the hydrological and topographical conditions of the country including a high quantity of perennial rivers in combination with steep gradients provide almost ideal conditions for the development of hydropower projects. Even so, only a small fraction of this potential is currently being utilized. In 2009, the total generation capacity of hydropower plants in the country was only 635.6 MW. From these, 631.1 MW are connected to the national grid, and 4.5 MW is generated by off-grid mini and micro hydropower plants supplying electricity at local levels.


GRAFIK

 

Since 2008 more than 1200 pico hydropower schemes (below 5 kW) have been built in Nepal. Approximately 720 schemes in the range of 5 kW to 1 MW were commissioned to produce off-grid electricity for rural communities. Around 100 companies are certified to working in operation and construction of mini and micro hydropower schemes.
According to the latest annual report of the NEA from 2009, hydropower accounts for 88.33% of the energy volume served through the grid. 29.57% (170 MW) of this derives from Independent Power Producers (IPPs). Only 0.29% of the energy derives from thermal plants, and 11.39% of the electricity was imported from India. The electricity demand exceeds the supply by far and it is rising by more than 10% per year.


GRAFIK


Source: Nepal Electricity Authority (2009): A year in review. Internet: http://www.nea.org.np/, retrieved Sept 2010.
One major obstacle for electricity supply in Nepal derives from the fact that the whole system has almost no base load. All hydropower plants are run-of-river type schemes with no seasonal storage capacity meaning that in the dry season there is an increased energy deficit. In combination with inefficient transmissions and distribution causing up to 26% system losses, this resulted in up to 18 hours of load shedding per day (compared to 2 hours load shedding during the monsoon season) in 2008/2009.
Moreover, electricity supply is limited to 48% of the population most of which is in urban areas. The rural electrification rate is only around 8%. The low level of electrification as well as insufficient supply in the electrified areas hampers both economic development and access to information and education. Although the Nepalese government officially recognizes the importance of developing the electricity sector, and has passed a Hydropower Development Policy, the political instability of the country makes it difficult to develop and enact long-term strategies in general. To date, there is no National Energy Strategy for the country. A draft forwarded to the parliament cannot be approved as the parliament is incapacitated in its current situation. A draft of the Ordinance for the Development and Management of the Electricity Sector, to which SHPP contributed, has been pending in parliament since 2005. Up to now, the energy policy objectives which mainly emphasize the development of the hydropower sector are set up as a part of the general 5-Year Plans by the National Planning Commission. The current 3-Year Interim Plan (2007/08 – 2009/10) defining insufficient electricity supply as one of the most urgent problems of the country aims to produce significant increases of private sector participation in the hydropower sector as well as an extension of the NEA-generated capacity. The ambitious goal is to abandon the practice of load-shedding in 2013/14 by completing ongoing hydropower projects adding 105 MW generation capacity (85 MW by public sector, 20 MW by private sector) and the initiation of new hydropower projects with 2,115 MW capacity. However, knowing that hydropower projects in Nepal are usually delayed for a couple of years, these goals are very unlikely to be achieved. During the previous planning period, only 13% of the projected generation capacity increase was achieved.
To date, among the on-grid hydropower plants, 19 with a generation capacity of 158 MW are operated by IPPs. Six IPP projects are under construction and for 25 projects the Power Purchase Agreement (PPA) has already been signed. In total, there are around 170 projects developed and operated by IPPs in different stages, ranging from 1 to 50 MW with a total capacity of 1600 MW. Although it has to be assumed that only a part of them will be realized, these numbers indicate that the hydropower sector with the support of SHPP has indeed become an attractive area for investment during the last decade. According to the Nepal Association of Independent Power Producers (IPPAN), capital available for hydropower in the country’s banks is sufficient to finance hydropower plants with a combined capacity of 50 MW at the same time. Since a deficit of confidence and capital is one of its direct effects, political instability can be seen as a major bottleneck for further development of this sector.

Ten years of Small Hydro Promotion Programme in Nepal 

Ideas for privately and commercially operated hydropower schemes in Nepal were first introduced by donor organizations in the early 1990s. At that time, Nepal was suffering from acute electricity shortages causing direct economic losses and leading to the migration of several industries to neighboring countries and resulting in a significant loss of jobs. The government of Nepal (GoN), being under great pressure to solve these problems, recognized the importance of the private sector for developing the hydropower potential of the country and adopted the legal framework accordingly. However, even though its regulations were among the most favorable to private investment in South Asia, the interest of the private sector to invest in hydropower remained limited for the next decade. At this time, there was only one international organization engaged in the hydropower sector in Nepal - the Swiss NGO Helvetas, who has been working in Nepal since the early 1980s. In 1992, the Norwegian Organisation NORAD supported the construction of a hydropower plant with a 60 MW capacity in Khimti. To finance the project, the company Himal Power Limited was founded, a joint venture with 60% Norwegian and 40% Nepalese shareholders. When it came into service in 2000, Khimti became the first commercially run hydropower scheme in Nepal. The second one was the 36 MW scheme at Bothekoshi, supported by USAID.
Simultaneously, in 1992, the German development cooperation became engaged in the hydropower sector with a small project aimed towards the electrification of district centers in Nepal. During the 4-year project period GTZ developed a master plan for the electrification of approximately 40 district centers through small hydropower schemes and conducted site identification and feasibility studies. After project closure the need to further promote small hydropower in Nepal was identified. In response, GTZ screened 7 potential hydropower schemes and conducted a workshop with various stakeholders to indentify barriers hindering further development of the small hydropower sector. Barriers for further development were therefore identified as the following:

  • Lack of supportive policy for Independent Power Producers (IPPs)
  • Lack of capacity of project developers and financial institutions to appraise feasibility studies prepared by engineering consultants
  • Lack of experience in achieving Power Purchase Agreements (PPA) between IPPs and the Nepal Electricity Authority (NEA) 
  • General lack of capacity in financial institutions
  • Lack of independent construction supervisors.


The government of Nepal created an opportunity for private investment and ownership of generation facilities with the energy policy (Electricity Act, 2049), introduced in 1992. However, this regulation/policy did not immediately result in a large influx of investment in the small/mini hydro sector as was expected. Several specific gaps preventing large scale growth in the sector were identified as:

  1. Low feed in rates: too low to attract large scale investment at the prevailing cost levels and options for debt financing. A project with estimated 18% IRR gives little premium for investors when the debt rate is around 15%.
  2. Lenient regulation in licensing. This caused many sites to be caught up by speculators without anything happening for years.
  3. Underdeveloped financial and insurance sector, mainly due to lack of political stability and proper institutional structures. Private capital in Nepal is traditionally structured as family business, instead of incorporated investment companies. These family businesses have limited knowledge of modern project management tools and culture. And even though private investment was continuous during times of conflict, debt financing was problematic. Also, despite long term efforts, Nepal does not offer any sovereign guarantee for SHP or other utility investments. This combined with the limited financing volume available and the long payback period for hydro investment caused limited interest in financing small hydropower plants.
  4. Limited experience in the private sector. This ranged from civil construction companies to component manufacturers and project developers.