{{Project Resource Center
 
{{Project Resource Center
 
|REPRC title=Uganda - West Nile Rural Electrification Project
 
|REPRC title=Uganda - West Nile Rural Electrification Project
Line 16: Line 15:
 
|REPRC file other=
 
|REPRC file other=
 
|REPRC type general=Case Study
 
|REPRC type general=Case Study
 +
|REPRC type case=Other
 
|REPRC type other=
 
|REPRC type other=
|REPRC technology general RE=General RE
 
 
|REPRC technology hydro=Hydro
 
|REPRC technology hydro=Hydro
 
|REPRC technology hydro sub=Small/Mini
 
|REPRC technology hydro sub=Small/Mini
 +
|REPRC technology general RE=General RE
 
|REPRC connection=Off-grid
 
|REPRC connection=Off-grid
|REPRC abstract=This case study constitutes an example of a rural electrification project, with the following features:<br/>
+
|REPRC abstract=This case study constitutes an example of a rural electrification project, with the following features: '''Barriers:''' Lack of long term debt financing; '''Instrument:''' Two-step financing backed by liquidity guarantee; '''Application:''' Bullet repayment of initial 8-year loan with new 7-year loan with amortization payments on the two loans profiled to match a 15-year loan. Liquidity guarantee of funds for new 7-year loan.
*'''Barriers:''' Lack of long term debt financing<br/>
 
*'''Instrument:''' Two-step financing backed by liquidity guarantee<br/>
 
*'''Application:''' Bullet repayment of initial 8-year loan with new 7-year loan with amortization payments on the two loans profiled to match a 15-year loan. Liquidity guarantee of funds for new 7-year loan.<br/>
 
 
}}
 
}}
  

Latest revision as of 19:04, 16 April 2014



Uganda - West Nile Rural Electrification Project

Title of Document Uganda - West Nile Rural Electrification Project
Abstract This case study constitutes an example of a rural electrification project, with the following features: Barriers: Lack of long term debt financing; Instrument: Two-step financing backed by liquidity guarantee; Application: Bullet repayment of initial 8-year loan with new 7-year loan with amortization payments on the two loans profiled to match a 15-year loan. Liquidity guarantee of funds for new 7-year loan.
File Download

English: Uganda West Nile rural electrification project.pdf

Original Source World Bank
Year 2011
Region/Country Africa - Uganda
Language(s) English
Document Type Case Study - Other
Technology Hydro Small/Mini
General RE
Connection Type Off-grid


Hydro