Difference between revisions of "Energy for Rural Health Centers"
***** (***** | *****) m |
***** (***** | *****) m |
||
Line 16: | Line 16: | ||
== Defining Energy Needs == | == Defining Energy Needs == | ||
<div><span style="font-size: 10pt; color: #393939">When considering the type of electrification needed to sustain daily operations, a facility must first understand its basic needs. The needs assessment will include an inventory of the types of equipment used in the facility and the power required to operate each device. Understanding the average “daily load”, or the amount of power required to operate equipment under normal working conditions, will influence the choice of power supply. Once the daily energy requirement is established, a range of electrification options can be considered. Understanding the need will also provide managers with a realistic budget for procuring, installing, and maintaining the new system.</span></div> | <div><span style="font-size: 10pt; color: #393939">When considering the type of electrification needed to sustain daily operations, a facility must first understand its basic needs. The needs assessment will include an inventory of the types of equipment used in the facility and the power required to operate each device. Understanding the average “daily load”, or the amount of power required to operate equipment under normal working conditions, will influence the choice of power supply. Once the daily energy requirement is established, a range of electrification options can be considered. Understanding the need will also provide managers with a realistic budget for procuring, installing, and maintaining the new system.</span></div> | ||
+ | === Calculating Energy Needs of a Health Facility === | ||
+ | |||
+ | The USAID [http://tools.poweringhealth.org/ <font color="#0167a5">Health Clinic Power System Design Tool</font>] (4 - Electric Load Inputs) and/or the [http://www.poweringhealth.org/tools/audit.shtml <font color="#0167a5">Energy Audit Spreadsheet</font>] (Worksheet 7 - Future Electric Applications) as well as the examples of energy demands of typical rural health centers in developing countries can help identifying the overall energy demands of health facilities. The amount of expected energy consumption in kWh/day, in addition to expert consultation, will assisst in the selection of appropriate electrification technology. | ||
+ | <div><span>Once a facility has comprehensively analyzed the energy requirements of its day-to-day operations, it must be determined whether those demands are likely to change. Facility managers must think strategically about the possibility that energy demands may increase due to the addition of patients, extended operating hours, or new services. Once this process has been completed and an adequate accounting of needs has been made, the manager can determine the various energy options to meet those demands. These options must be considered in light of all facility-specific variables.</span></div> | ||
== Power Generation Options == | == Power Generation Options == |
Revision as of 09:04, 23 June 2010
Introduction
Electricity Supply
Stepwise Approach to Electrifying a Health Center
- Identify the Health Center's Current Energy Demands
Identify current energy needs and applications, e.g. for lighting, refrigeration, communication, etc. - Account for Near-Term Change
Determine whether energy demands will change in the near-term. - Establish Target Energy Consumption in kWh/day
Use tools such as the USAID Health Clinic Power System Design Tool (4 - Electric Load Inputs) or the Energy Audit Spreadsheet (Worksheet 7 - Future Electric Applications) to calculate the future electric energy consumption in kWh/day. - Determine Technologies Needed to Meet Target
Evaluate energy technologies. - Procure, Design System, and Install Technology
Select the most appropriate energy technology. - Maintain and Financing Your Energy Technology
Institute financing mechanism(s) accounting for operation and maintenance needs and costs.
Remember to contact an expert for assessment, system design, procurement, installation, and maintenance of energy technologies!
Defining Energy Needs
Calculating Energy Needs of a Health Facility
The USAID Health Clinic Power System Design Tool (4 - Electric Load Inputs) and/or the Energy Audit Spreadsheet (Worksheet 7 - Future Electric Applications) as well as the examples of energy demands of typical rural health centers in developing countries can help identifying the overall energy demands of health facilities. The amount of expected energy consumption in kWh/day, in addition to expert consultation, will assisst in the selection of appropriate electrification technology.
Power Generation Options
System Sustainability
Improved Cooking
Further Reading
Powering Health: Electrification Options for Developing Country Health Facilities - USAID website covering all major issues on electricity supply for rural health centers. Several country case studies available. Offers tools for energy audits and load calculation. Highly recommandable!
USAID: Powering Health: Electrification Options for Rural Health Centers - Step-by-step guide on energy needs, power generation options, and sustainability issues for rural health centers. Case studies from Botswana and Uganda.
National Renewable Energy Laboratory (USA) (1998): Renewable Energy for Rural Health Clinics - Publication on energy issues of rural health clinics: energy applications, electrical system components, system selection and economics, institutional considerations. Also provides case studies and lessons learned.
GTZ (1996): Energy Supply for Health Care Facilities in Developing Countries - GTZ publication on energy sources, energy requirements and energy management for rural health centers.
Practical Action: Solar PV Refrigeration of Vaccines - Technical Background of solar refrigeration
References
- ↑ USAID: Powering Health. Internet: http://pdf.usaid.gov/pdf_docs/PNADJ557.pdf