Difference between revisions of "Micro Hydro Power (MHP) - Ethiopia, Ererte"
From energypedia
***** (***** | *****) m |
***** (***** | *****) |
||
Line 4: | Line 4: | ||
*<u>District</u>: Hula | *<u>District</u>: Hula | ||
*<u>Kebele</u>: Beshiro Gute | *<u>Kebele</u>: Beshiro Gute | ||
+ | *<u>River</u>:<br> | ||
*[[GPS coordinates - MHP sites EnDev|<u>GPS coordinate</u>]]<u>:</u> 6º33’26.8’’N 38º40’8.4’’ E | *[[GPS coordinates - MHP sites EnDev|<u>GPS coordinate</u>]]<u>:</u> 6º33’26.8’’N 38º40’8.4’’ E | ||
+ | |||
+ | <br> | ||
+ | |||
+ | The MHP plant Ererte has a capacity of 33 kW and was inaugurated in May 2011. A total of approximately 200 households will be connected to the plant. The maximum number of potentially connectable households is 700. | ||
<br> '''Start of Construction: '''August 2009 | <br> '''Start of Construction: '''August 2009 | ||
Line 39: | Line 44: | ||
| | ||
− | [[Category:Hydro]] | + | [[Category:Hydro]][[Category:Ethiopia]] |
Revision as of 15:14, 26 July 2011
Location of the site:
- Country: Ethiopia
- District: Hula
- Kebele: Beshiro Gute
- River:
- GPS coordinate: 6º33’26.8’’N 38º40’8.4’’ E
The MHP plant Ererte has a capacity of 33 kW and was inaugurated in May 2011. A total of approximately 200 households will be connected to the plant. The maximum number of potentially connectable households is 700.
Start of Construction: August 2009
Date of Commissioning:
Ownership: Robot Electric Users Cooperative/community based cooperative society
Tariff Structure: Flat rate/monthly based per appliance
Technical Specification:
- Canal: Lined stone masonry having a length of 53m
- Penstock: Mild stell having a diameter of 400mm and a length of 42m/locally manufactured
- Turbine:
T-15 cross flow turbine /Manufactured locally - Generator:
- Grid:
Wooden pole, ABC cable(2.76Km)