= Grid extension/densification approaches = | = Grid extension/densification approaches = | ||
− | = Type of grid activities | + | = Type of grid activities = |
− | + | {| cellspacing="1" cellpadding="1" width="200" align="left" border="1" | |
+ | |- | ||
+ | | [[Image:Picture1.jpg|thumb|center|200px|Picture1.jpg]] | ||
+ | |- | ||
+ | | [[Image:Picture2.jpg|thumb|center|200px|Picture2.jpg]] | ||
+ | |- | ||
+ | | [[Image:Picture3.jpg|200px]] | ||
+ | |} | ||
− | + | | |
− | + | '''Grid extension:''' | |
− | + | Benin, Ghana, Nicaragua, Nepal | |
− | + | | |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | + | <br> | |
− | + | <br>'''Grid densification(with and without transformation):''' | |
+ | Bolivia, Peru, Mozambique, Uganda | ||
− | + | | |
− | + | | |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
− | <br> | + | <br> |
+ | |||
+ | <br> | ||
= Costs<br> = | = Costs<br> = |
Revision as of 11:53, 26 August 2011
Grid extension/densification approaches
Type of grid activities
Grid extension:
Benin, Ghana, Nicaragua, Nepal
Grid densification(with and without transformation):
Bolivia, Peru, Mozambique, Uganda
Costs
<span /> |
Benin |
Ghana <span /> |
Nicaragua |
Bolivien |
Peru |
Mozambique |
Costs/ Connection (€) |
2000 |
5540 |
220-588 |
62 |
90 |
134 |
Tariff |
Social tariff |
Social tariff |
Social tariff |
Social tariff |
Social tariff |
Social tariff |
Security of energy supply |
Medium |
Medium |
High |
High |
High |
high |
Financial support
<span /> |
Benin |
Ghana <span /> |
Nicaragua |
Bolivien |
Peru |
Mozambique |
EnDev subsidy |
70% |
99% |
100% |
20% |
22% |
100% |
Government |
30% |
0% |
0% |
0% |
0% |
0% |
Utility |
0% |
0% |
0% |
0-80% |
0% |
0% |
Customer |
0% |
1% |
0% |
0-80% |
78% |
0% |
Additional Support
- Procurement support
- Developing local standards for grid connection
- Facilitating group applications for grid connections
- Training of local electricians for in-house wiring
- Training of consumers in energy use and efficiency
- Ex-ante savings for connection fees
- Introduction of installment payments of the connection fee linked to the electricity bills
Lessons learnt
- Some utilities are not interested in grid densification
- Poor households are often excluded in extension projects
- Some utilities have great difficulties to organize efficient procurement processes causing severe delays
- Free rider effect difficult to avoid (efficient selection process or accept the effect)
- Detailed monitoring is considered a burden and not always implemented
- In several countries power generation capacity cannot keep up with grid extension
- In rural areas several households are connected to a meter to save the connection fee which can be legal or illegal according to national and local regulation. In some of these case voltage drop can be a severe problem