= Step-by-Step Planning Checklist for Biogas Plants  =
+
= Overview<br/> =
  
The following table gives an overview of all the steps required to build a biogas unit. The order follows a usual time-line. There are steps which can be combined. However, to skip any of them might lead to future problems.  
+
The following table gives an overview of all the steps required to build a biogas unit.  
  
{| width="100%" cellpadding="5" border="1"
+
The order follows a usual time-line. There are steps which can be combined. However, to skip any of them might lead to future problems.
 +
 
 +
 
 +
 
 +
= Step-by-Step Planning Checklist for Biogas Plants<br/> =
 +
 
 +
{| border="1" cellpadding="5" width="100%"
 
|-
 
|-
! width="50%" | Customer  
+
! style="width: 50%;  background-color: rgb(204, 204, 204)" | Customer<br/>
! width="50%" | Contractor
+
! style="width: 50%;  background-color: rgb(204, 204, 204)" | Contractor
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| organizes advertisement, awareness creation
 
| organizes advertisement, awareness creation
 
|-
 
|-
| hears about biogas, develops interest, get's in contact with the contractor  
+
| hears about biogas, develops interest, get's in contact with the contractor<br/>
 
| &nbsp;
 
| &nbsp;
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| gives first overview over costs
 
| gives first overview over costs
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| writes letter to the customer
 
| writes letter to the customer
 
|-
 
|-
| writes a request  
+
| writes a request
 
| &nbsp;
 
| &nbsp;
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| starts file
 
| starts file
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| makes a side visit, including: discussion and calculations
 
| makes a side visit, including: discussion and calculations
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| makes a quantity survey,
 
| makes a quantity survey,
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| does object planning
 
| does object planning
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
| writes invoice <br> explains warranty performances
+
| writes invoice<br/>explains warranty performances
 
|-
 
|-
| makes first payment (50%)  
+
| makes first payment (50%)
 
| organizes a customer and constructor sign contract
 
| organizes a customer and constructor sign contract
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| hands over a list of building material to be delivered by the customer
 
| hands over a list of building material to be delivered by the customer
 
|-
 
|-
| prepares the material he agreed to deliver  
+
| prepares the material he agreed to deliver
 
| &nbsp;
 
| &nbsp;
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| organizes material delivery, reference line, main construction work, finishing, landscaping, slurry component, piping.
 
| organizes material delivery, reference line, main construction work, finishing, landscaping, slurry component, piping.
 
|-
 
|-
| starts to fill the plant <br> second payment (50%)  
+
| starts to fill the plant<br/>second payment (50%)
 
| &nbsp;
 
| &nbsp;
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| finishes piping installation of gas consumption accessories
 
| finishes piping installation of gas consumption accessories
 
|-
 
|-
| discusses handing over  
+
| discusses handing over
 
| &nbsp;
 
| &nbsp;
 
|-
 
|-
| makes an agreement on co-operation regarding fertiliser utilisation  
+
| makes an agreement on co-operation regarding fertiliser utilisation
 
| &nbsp;
 
| &nbsp;
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| makes a follow up on fertiliser utilisation
 
| makes a follow up on fertiliser utilisation
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| does customer monitoring
 
| does customer monitoring
 
|-
 
|-
| &nbsp;  
+
| &nbsp;
 
| conducts technical and agricultural service visits
 
| conducts technical and agricultural service visits
 
|}
 
|}
  
.
+
 
 +
 
 +
= Further Informaiton<br/> =
 +
 
 +
*
 +
 
 +
= References<br/> =
 +
 
 +
<references />
  
 
[[Category:Biogas]]
 
[[Category:Biogas]]

Revision as of 11:11, 22 November 2012

Overview

The following table gives an overview of all the steps required to build a biogas unit.

The order follows a usual time-line. There are steps which can be combined. However, to skip any of them might lead to future problems.


Step-by-Step Planning Checklist for Biogas Plants

Customer
Contractor
  organizes advertisement, awareness creation
hears about biogas, develops interest, get's in contact with the contractor
 
  gives first overview over costs
  writes letter to the customer
writes a request  
  starts file
  makes a side visit, including: discussion and calculations
  makes a quantity survey,
  does object planning
  writes invoice
explains warranty performances
makes first payment (50%) organizes a customer and constructor sign contract
  hands over a list of building material to be delivered by the customer
prepares the material he agreed to deliver  
  organizes material delivery, reference line, main construction work, finishing, landscaping, slurry component, piping.
starts to fill the plant
second payment (50%)
 
  finishes piping installation of gas consumption accessories
discusses handing over  
makes an agreement on co-operation regarding fertiliser utilisation  
  makes a follow up on fertiliser utilisation
  does customer monitoring
  conducts technical and agricultural service visits