Difference between revisions of "MHP El Plan"
From energypedia
***** (***** | *****) |
***** (***** | *****) |
||
Line 1: | Line 1: | ||
− | = Overview<br/> = | + | = Overview and General Information<br/> = |
'''<u>Location of the site:</u>''' | '''<u>Location of the site:</u>''' | ||
− | *<u>Country</u>: | + | *<u>Country</u>: Nicaragua |
− | *<u>District</u>: | + | *<u>District</u>: |
− | *<u>River</u>: | + | *<u>River</u>: |
− | *<u>GPS Coordinates</u>: | + | *<u>GPS Coordinates</u>: |
− | |||
− | |||
− | |||
− | + | = Further Information<br/> = | |
− | |||
− | |||
− | |||
− | |||
− | '''Tariff structure:''' Not applicable | + | '''Start of Construction:''' December 2011<br/> |
+ | '''Date of Commissioning:''' June 2012<br/> | ||
+ | '''Ownership / Operation Model:''' Privately owned<br/> | ||
+ | '''Tariff structure:''' Not applicable<br/> | ||
+ | '''Turbine:''' Pelton<br/> | ||
+ | '''Generator:''' Modified direct drive motor, 3 phase, 20 V, 150 W (approximately)<br/> | ||
− | |||
− | + | = Ressources - Codicions<br/> = | |
− | |||
− | |||
− | |||
− | |||
− | + | = Civil Works<br/> = | |
− | |||
− | <br/> | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | + | = Electromechanical Equipment<br/> = | |
− | |||
− | = | ||
− | |||
− | <br/> | + | = Electrical Transmission<br/> = |
− | |||
− | < | + | = Economic Information<br/> = |
Revision as of 21:38, 26 March 2014
Overview and General Information
Location of the site:
- Country: Nicaragua
- District:
- River:
- GPS Coordinates:
Further Information
Start of Construction: December 2011
Date of Commissioning: June 2012
Ownership / Operation Model: Privately owned
Tariff structure: Not applicable
Turbine: Pelton
Generator: Modified direct drive motor, 3 phase, 20 V, 150 W (approximately)