Difference between revisions of "Checklist for the Planning of a Biogas Plant"
From energypedia
***** (***** | *****) m |
***** (***** | *****) m |
||
Line 1: | Line 1: | ||
+ | |||
= Overview<br/> = | = Overview<br/> = | ||
− | The following table gives an overview of all the steps required to build a biogas unit. | + | The following table gives an overview of all the steps required to build a biogas unit. |
The order follows a usual time-line. There are steps which can be combined. However, to skip any of them might lead to future problems. | The order follows a usual time-line. There are steps which can be combined. However, to skip any of them might lead to future problems. | ||
− | + | <br/> | |
= Step-by-Step Planning Checklist for Biogas Plants<br/> = | = Step-by-Step Planning Checklist for Biogas Plants<br/> = | ||
− | {| border="1" cellpadding="5" | + | {| border="1" cellpadding="5" style="width: 100%" |
|- | |- | ||
! style="width: 50%; background-color: rgb(204, 204, 204)" | Customer<br/> | ! style="width: 50%; background-color: rgb(204, 204, 204)" | Customer<br/> | ||
! style="width: 50%; background-color: rgb(204, 204, 204)" | Contractor | ! style="width: 50%; background-color: rgb(204, 204, 204)" | Contractor | ||
|- | |- | ||
− | | | + | | |
| organizes advertisement, awareness creation | | organizes advertisement, awareness creation | ||
|- | |- | ||
| hears about biogas, develops interest, get's in contact with the contractor<br/> | | hears about biogas, develops interest, get's in contact with the contractor<br/> | ||
− | | | + | | |
|- | |- | ||
− | | | + | | |
| gives first overview over costs | | gives first overview over costs | ||
|- | |- | ||
− | | | + | | |
| writes letter to the customer | | writes letter to the customer | ||
|- | |- | ||
| writes a request | | writes a request | ||
− | | | + | | |
|- | |- | ||
− | | | + | | |
| starts file | | starts file | ||
|- | |- | ||
− | | | + | | |
| makes a side visit, including: discussion and calculations | | makes a side visit, including: discussion and calculations | ||
|- | |- | ||
− | | | + | | |
| makes a quantity survey, | | makes a quantity survey, | ||
|- | |- | ||
− | | | + | | |
| does object planning | | does object planning | ||
|- | |- | ||
− | | | + | | |
| writes invoice<br/>explains warranty performances | | writes invoice<br/>explains warranty performances | ||
|- | |- | ||
Line 47: | Line 48: | ||
| organizes a customer and constructor sign contract | | organizes a customer and constructor sign contract | ||
|- | |- | ||
− | | | + | | |
| hands over a list of building material to be delivered by the customer | | hands over a list of building material to be delivered by the customer | ||
|- | |- | ||
| prepares the material he agreed to deliver | | prepares the material he agreed to deliver | ||
− | | | + | | |
|- | |- | ||
− | | | + | | |
| organizes material delivery, reference line, main construction work, finishing, landscaping, slurry component, piping. | | organizes material delivery, reference line, main construction work, finishing, landscaping, slurry component, piping. | ||
|- | |- | ||
| starts to fill the plant<br/>second payment (50%) | | starts to fill the plant<br/>second payment (50%) | ||
− | | | + | | |
|- | |- | ||
− | | | + | | |
| finishes piping installation of gas consumption accessories | | finishes piping installation of gas consumption accessories | ||
|- | |- | ||
| discusses handing over | | discusses handing over | ||
− | | | + | | |
|- | |- | ||
| makes an agreement on co-operation regarding fertiliser utilisation | | makes an agreement on co-operation regarding fertiliser utilisation | ||
− | | | + | | |
|- | |- | ||
− | | | + | | |
| makes a follow up on fertiliser utilisation | | makes a follow up on fertiliser utilisation | ||
|- | |- | ||
− | | | + | | |
| does customer monitoring | | does customer monitoring | ||
|- | |- | ||
− | | | + | | |
| conducts technical and agricultural service visits | | conducts technical and agricultural service visits | ||
|} | |} | ||
− | + | <br/> | |
= Further Informaiton<br/> = | = Further Informaiton<br/> = | ||
+ | *[[Portal:Biogas|Biogas Portal on energypedia]] | ||
* | * | ||
+ | |||
+ | |||
= References<br/> = | = References<br/> = |
Revision as of 08:53, 18 June 2014
Overview
The following table gives an overview of all the steps required to build a biogas unit.
The order follows a usual time-line. There are steps which can be combined. However, to skip any of them might lead to future problems.
Step-by-Step Planning Checklist for Biogas Plants
Customer |
Contractor |
---|---|
organizes advertisement, awareness creation | |
hears about biogas, develops interest, get's in contact with the contractor |
|
gives first overview over costs | |
writes letter to the customer | |
writes a request | |
starts file | |
makes a side visit, including: discussion and calculations | |
makes a quantity survey, | |
does object planning | |
writes invoice explains warranty performances | |
makes first payment (50%) | organizes a customer and constructor sign contract |
hands over a list of building material to be delivered by the customer | |
prepares the material he agreed to deliver | |
organizes material delivery, reference line, main construction work, finishing, landscaping, slurry component, piping. | |
starts to fill the plant second payment (50%) |
|
finishes piping installation of gas consumption accessories | |
discusses handing over | |
makes an agreement on co-operation regarding fertiliser utilisation | |
makes a follow up on fertiliser utilisation | |
does customer monitoring | |
conducts technical and agricultural service visits |