Difference between revisions of "Thermo-technical retrofitting of public buildings"
From energypedia
***** (***** | *****) |
***** (***** | *****) |
||
(5 intermediate revisions by 2 users not shown) | |||
Line 1: | Line 1: | ||
{{Biogas Project Database | {{Biogas Project Database | ||
− | |BSP Project Name=Thermo-technical retrofitting of public buildings | + | |BSP Project Name=Kindergarten No. 5 Jargalant soum - Thermo-technical retrofitting of public buildings |
|BSP Project Desc=Within the project 'Energy efficiency in the grid-connected energy supply' implemented by GIZ on behalf of the German federal Ministry for Economic Cooperation and Development (BMZ) and Swiss Development Cooperation (SDC) sixteen (16) have been retrofitted. This one of these buildings. | |BSP Project Desc=Within the project 'Energy efficiency in the grid-connected energy supply' implemented by GIZ on behalf of the German federal Ministry for Economic Cooperation and Development (BMZ) and Swiss Development Cooperation (SDC) sixteen (16) have been retrofitted. This one of these buildings. | ||
− | |BSP Project Budget=264 | + | |BSP Project Number=14.2128.8-002.00 |
+ | |BSP Project Budget=264,563,214 MNT | ||
|BSP Project Status=Completed | |BSP Project Status=Completed | ||
|BSP Project Start=2014/07/22 | |BSP Project Start=2014/07/22 | ||
|BSP Project Type=other | |BSP Project Type=other | ||
|BSP Project End=2014/09/26 | |BSP Project End=2014/09/26 | ||
+ | |BSP Project Picture=Untitled.png | ||
|BSP Province Name=Khovd | |BSP Province Name=Khovd | ||
|BSP Province=48.001732, 91.635858 | |BSP Province=48.001732, 91.635858 | ||
Line 14: | Line 16: | ||
}} | }} | ||
− | + | ==== Building data and geometry<br/> ==== | |
− | Construction year: 1975<br/> | + | *Construction year: 1975<br/> |
+ | *Cross volume: 3,276.8 m³<br/> | ||
+ | *Thermal envelope: 1,730.3 m²<br/> | ||
+ | *Net volume: 2,835 m³<br/> | ||
+ | *Net floor area: 799.3 m²<br/> | ||
− | + | ==== Implemented measures:<br/> ==== | |
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
*Roof insulation with 20cm EPS- hard foam and waterproofing<br/> | *Roof insulation with 20cm EPS- hard foam and waterproofing<br/> | ||
*Wall insulation with 15cm EPS- hard foam<br/> | *Wall insulation with 15cm EPS- hard foam<br/> | ||
*New windows with 5-chamber plastic frame and double glazing<br/> | *New windows with 5-chamber plastic frame and double glazing<br/> | ||
− | *New exterior doors <br/> | + | *New exterior doors<br/> |
*Rehabilitation of the heating system<br/> | *Rehabilitation of the heating system<br/> | ||
+ | *Contracting company: Tulgat bagana LLC<br/> | ||
+ | |||
+ | ==== Energy consumption<br/> ==== | ||
− | + | *Before: 522 kWh/(m2 a) {calculated}<br/> | |
+ | *After: 140 kWh /(m2 a) {metred}<br/> | ||
+ | *Energy saving per year: 305,332 kWh<br/> | ||
+ | *Coal equivalent saving: 75,020 kg / 75 t<br/> | ||
+ | *CO<sub>2</sub> emission savings per year: 206 t CO<sub>2 </sub>{Estimated}<br/> |
Latest revision as of 05:15, 23 November 2017
Key Project Data
Name
Kindergarten No. 5 Jargalant soum - Thermo-technical retrofitting of public buildings
Description
Within the project 'Energy efficiency in the grid-connected energy supply' implemented by GIZ on behalf of the German federal Ministry for Economic Cooperation and Development (BMZ) and Swiss Development Cooperation (SDC) sixteen (16) have been retrofitted. This one of these buildings.
Project No.
14.2128.8-002.00
Total Budget
264,563,214 MNT
Status
Completed
Timeframe
2014/07/22 - 2014/09/26
Type
other
Project Picture
Location in Mongolia
Province
Khovd {{#display_point: coordinates=48.001732, 91.635858|zoom=4|height=150|width=250|service=openlayers}}
Further Information
Website
Factsheet
Organization
GIZ
Tagging
Publications
Currently, there are no publications related to this project.
Events
Currently, there are no events organized by this project.
Additional Comments
Building data and geometry
- Construction year: 1975
- Cross volume: 3,276.8 m³
- Thermal envelope: 1,730.3 m²
- Net volume: 2,835 m³
- Net floor area: 799.3 m²
Implemented measures:
- Roof insulation with 20cm EPS- hard foam and waterproofing
- Wall insulation with 15cm EPS- hard foam
- New windows with 5-chamber plastic frame and double glazing
- New exterior doors
- Rehabilitation of the heating system
- Contracting company: Tulgat bagana LLC
Energy consumption
- Before: 522 kWh/(m2 a) {calculated}
- After: 140 kWh /(m2 a) {metred}
- Energy saving per year: 305,332 kWh
- Coal equivalent saving: 75,020 kg / 75 t
- CO2 emission savings per year: 206 t CO2 {Estimated}