Difference between revisions of "Pico Hydro Development to Provide Electric Light to the Rural Poor in Remote and Inaccessible Areas of Sri Lanka"

From energypedia
***** (***** | *****)
(Created page with "== Introduction == The main objective of this project was to provide access to electricity through Pico Hydro systems (PH) to households situated in isolated, rural hilly area...")
 
***** (***** | *****)
m
Line 2: Line 2:
 
The main objective of this project was to provide access to electricity through Pico Hydro systems (PH) to households situated in isolated, rural hilly areas of Sri Lanka. Pico Hydro systems with an output of up to 1 kW each and efficiency between 32-40% were implemented in different locations in the Sabaragamuwa Province. Next to technical training, awareness raising and dissemination were considerable parts of the implementation strategy.  
 
The main objective of this project was to provide access to electricity through Pico Hydro systems (PH) to households situated in isolated, rural hilly areas of Sri Lanka. Pico Hydro systems with an output of up to 1 kW each and efficiency between 32-40% were implemented in different locations in the Sabaragamuwa Province. Next to technical training, awareness raising and dissemination were considerable parts of the implementation strategy.  
 
{| class="wikitable"
 
{| class="wikitable"
|+Basic Information
+
|+Basic Projekt Information
!Location
+
|Location:
!Sri Lanka
+
|Sri Lanka
 
|-
 
|-
 
|Technology:
 
|Technology:
Line 18: Line 18:
 
|WISIONS financial support: €€ 44,000
 
|WISIONS financial support: €€ 44,000
 
|-
 
|-
|CO2 Reduction
+
|CO2 Reduction:
 
|71.6 tCO2/year
 
|71.6 tCO2/year
 
|-
 
|-
Line 24: Line 24:
 
|Practical Action Sri Lanka
 
|Practical Action Sri Lanka
 
|-
 
|-
|Duration
+
|Duration:
 
|October 2010 – April 2012
 
|October 2010 – April 2012
 
|}
 
|}

Revision as of 12:47, 17 August 2026

Introduction

The main objective of this project was to provide access to electricity through Pico Hydro systems (PH) to households situated in isolated, rural hilly areas of Sri Lanka. Pico Hydro systems with an output of up to 1 kW each and efficiency between 32-40% were implemented in different locations in the Sabaragamuwa Province. Next to technical training, awareness raising and dissemination were considerable parts of the implementation strategy.

Basic Projekt Information
Location: Sri Lanka
Technology: Pico hydro power
Energy-related need: Electricity
Costs: Total: €€ 74,538
WISIONS financial support: €€ 44,000
CO2 Reduction: 71.6 tCO2/year
Partners Involved: Practical Action Sri Lanka
Duration: October 2010 – April 2012