In 2009, Qollpana was selected as an ideal place to implement Bolivia's first wind park. Qollpana is located <span id="result_box" lang="en"><span>in the municipality of Pocona, 122 km from <span id="result_box" lang="en"><span>Cochambamba</span></span> city. </span></span><span id="result_box" style="" lang="en"><span title="Debido al contexto político y las condiciones meteorológicas adecuadas, se eligió a Qollpana, del municipio de Pocona, ubicado a 122 km de la ciudad de Cochabamba."></span><span title="Las mediciones y estudios a lo largo de tres años concluyeron que Qollpana tiene un potencial eólico excelente para instalar un proyecto a gran escala.">Studies over three years concluded that Qollpana has excellent wind potential to set up a large-scale project. This wind farm was implemented by <span id="result_box" style="" lang="en"><span>the National Electricity Company Bolivia (ENDE) Corani and had tecnichal assitance by GIZ.</span></span><span id="result_box" style="" lang="en"><span></span></span></span></span><br/> | In 2009, Qollpana was selected as an ideal place to implement Bolivia's first wind park. Qollpana is located <span id="result_box" lang="en"><span>in the municipality of Pocona, 122 km from <span id="result_box" lang="en"><span>Cochambamba</span></span> city. </span></span><span id="result_box" style="" lang="en"><span title="Debido al contexto político y las condiciones meteorológicas adecuadas, se eligió a Qollpana, del municipio de Pocona, ubicado a 122 km de la ciudad de Cochabamba."></span><span title="Las mediciones y estudios a lo largo de tres años concluyeron que Qollpana tiene un potencial eólico excelente para instalar un proyecto a gran escala.">Studies over three years concluded that Qollpana has excellent wind potential to set up a large-scale project. This wind farm was implemented by <span id="result_box" style="" lang="en"><span>the National Electricity Company Bolivia (ENDE) Corani and had tecnichal assitance by GIZ.</span></span><span id="result_box" style="" lang="en"><span></span></span></span></span><br/> | ||
− | <span style="" lang="en"><span title="Las mediciones y estudios a lo largo de tres años concluyeron que Qollpana tiene un potencial eólico excelente para instalar un proyecto a gran escala."><span style="" lang="en"><span>The planning and construction of Qollpana's wind farm is divided in two phases: Qollpana | + | <span style="" lang="en"><span title="Las mediciones y estudios a lo largo de tres años concluyeron que Qollpana tiene un potencial eólico excelente para instalar un proyecto a gran escala."><span style="" lang="en"><span>The planning and construction of Qollpana's wind farm is divided in two phases: Qollpana 1 and 2.</span></span></span></span> |
'''Qollpana 1:''' | '''Qollpana 1:''' |
Revision as of 23:37, 1 September 2017
In 2009, Qollpana was selected as an ideal place to implement Bolivia's first wind park. Qollpana is located in the municipality of Pocona, 122 km from Cochambamba city. Studies over three years concluded that Qollpana has excellent wind potential to set up a large-scale project. This wind farm was implemented by the National Electricity Company Bolivia (ENDE) Corani and had tecnichal assitance by GIZ.
The planning and construction of Qollpana's wind farm is divided in two phases: Qollpana 1 and 2.
Qollpana 1:
In 2011 ENDE Corani started the wind energy project with two turbines of 1.5 MW each. These turbines are licensed by the German company Vensys Energy AG; and marketed by the Chinese company Goldwind.
Qollpana 2:
In December 2014 the Bolivian government signed a contract to start the second phase of Qollpana's wind farm. A high voltage transmission line and eight turbines of 3 MW each have been installed in Qollpana to date. The Qollpana's power output is 24 MW (phase II). The German company ENERCON GmbH installed the turbines and monitors 24/7.
For more information, click here.