Difference between revisions of "Micro Hydro Power (MHP) - Ethiopia, Ererte"
From energypedia
***** (***** | *****) (Created page with "<br> '''Location of the site''':<br> <br> Country: Ethiopia<br> District: Bona Zuria<br> Kebele: Beshiro Gute<br> GPS coordinate: 6º33’26.8...") |
***** (***** | *****) m |
||
Line 1: | Line 1: | ||
− | <br> | + | '''Location of the site''':<br><br>Country: Ethiopia<br>District: Bona Zuria<br>Kebele: Beshiro Gute<br>GPS coordinate: 6º33’26.8’’N 38º40’8.4’’ E |
− | | + | |
− | + | Start of Construction: August 2009 | |
− | + | Date of Commissioning: | |
− | + | <br> | |
− | + | Ownership: | |
− | + | Robot Electric Users Cooperative/community based cooperative society | |
− | + | <br> | |
− | + | Tariff Structure: | |
− | + | Flat rate/monthly based per appliance | |
+ | <br> | ||
+ | '''Technical Specification:''' | ||
− | + | <br> | |
− | + | Canal: Lined stone masonry having a length of 53m | |
+ | Penstock: Mild stell having a diameter of 400mm and a length of 42m/locally manufactured | ||
+ | | ||
− | + | Turbine: | |
− | + | T-15 cross flow turbine /Manufactured locally | |
+ | Generator: | ||
+ | <br> | ||
− | + | Grid: | |
+ | Wooden pole, ABC cable(2.76Km) | ||
+ | <br> | ||
− | | + | |
− | + | {| class="FCK__ShowTableBorders" cellspacing="1" cellpadding="1" width="100%" border="0" | |
+ | |- | ||
+ | | [[Image:Ererti Fall.JPG|thumb|left|381x286px|Ererti Fall.JPG]] | ||
+ | | [[Image:Ererti MHP site.JPG|thumb|right|381x286px|Ererti MHP site.JPG]] | ||
+ | |- | ||
+ | | [[Image:Ererti MHP weir ,Intake and canal.JPG|thumb|center|381x286px|Ererti MHP weir ,Intake and canal.JPG]] | ||
+ | | [[Image:Locally Manufactured T-15 Turbine.JPG|thumb|right|381x286px|Locally Manufactured T-15 Turbine.JPG]] | ||
+ | |} | ||
| | ||
− | + | [[Category:Hydro]] | |
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− |
Revision as of 14:25, 20 December 2010
Location of the site:
Country: Ethiopia
District: Bona Zuria
Kebele: Beshiro Gute
GPS coordinate: 6º33’26.8’’N 38º40’8.4’’ E
Start of Construction: August 2009
Date of Commissioning:
Ownership:
Robot Electric Users Cooperative/community based cooperative society
Tariff Structure:
Flat rate/monthly based per appliance
Technical Specification:
Canal: Lined stone masonry having a length of 53m
Penstock: Mild stell having a diameter of 400mm and a length of 42m/locally manufactured
Turbine:
T-15 cross flow turbine /Manufactured locally
Generator:
Grid:
Wooden pole, ABC cable(2.76Km)