Turbines in Private Sector Participation (PSP) Hydro Rwanda
From energypedia
Revision as of 16:09, 7 August 2014 by ***** (***** | *****)
Overview
Concretely, PSP Hydro envisages supporting five private Rwandan Project Developers financially and with ongoing training. The intervention is realized under the umbrella of the Dutch-German Energy Partnership Energising Development (EnDev).
Hydro Sites in Rwanda
Three hydro sites are currently under development in the EnDev project PSP Hydro in Rwanda.
Here is some date about the turbines and generators that will be installed in the projects:
Project site |
project developer |
capazity | Turbine Manufacturer |
[kW] | |||
Murunda | REPRO | 96 | generator: Ossberger (new)
turbine: Ossberger (old) |
Masimeru and Maruruma | ENNy | 250 |
generator + turbine Kochendörfer (new) |
Musarara | SOGEMR | 438 |
generator + turbine Ossberger (new) |
Further Information