Micro Hydro Power (MHP) - Ethiopia, Ererte
From energypedia
Revision as of 14:32, 20 December 2010 by ***** (***** | *****)
Location of the site:
- Country: Ethiopia
- District: Bona Zuria
- Kebele: Beshiro Gute
- GPS coordinate: 6º33’26.8’’N 38º40’8.4’’ E
- Start of Construction: August 2009
- Date of Commissioning:
- Ownership:
Robot Electric Users Cooperative/community based cooperative society - Tariff Structure:
Flat rate/monthly based per appliance
Technical Specification:
- Canal: Lined stone masonry having a length of 53m
- Penstock: Mild stell having a diameter of 400mm and a length of 42m/locally manufactured
- Turbine:
T-15 cross flow turbine /Manufactured locally - Generator:
- Grid:
Wooden pole, ABC cable(2.76Km)