Risks in Energy Access Projects

From energypedia
Revision as of 15:27, 26 February 2019 by ***** (***** | *****)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

Overview

Mini-grids and stand-alone systems play an important role when facilitating energy access in developing countries. However, despite the financing scheme and the type of technology applied, there are potential risks to be considered.

Painuly (2001)[1] in Hazelton et al. (2015)[2] states that unawareness and misinterpretation of risks (and benefits) are a major barrier for technology adoption. 

Therefore a de-risking approach along the entire life cycle of a project is necessary in order to ensure its success and sustainability.

This article includes:

  • An example of activities that can be carried out during a projects’ preparation as guidance on how to be aware of risks.
  • An extensive list of risks organized in six sub-categories based on literature review and field experience in monitoring. For most of the risks there are suggestions on how to minimize, mitigate or controll them during the life cycle of a project.
  • The four main steps of risk management are presented in a graph that encapsulates the essentials of this iterative process. In addition, there is an explanation on how to prioritize risks according to the dimensions of their probability to occur and their impact potential.
  • At the end the reader can consider revising some experiences applying de-risking approaches for rural electrification projects (mini-grids and hydro), as well as further reading about risks management for renewable energy systems.


De-risking Approach During Project Preparation

Not well-prepared projects reduce their chances of receiving funding and miss important opportunities. For example, governments usually do not invest in project preparation except if there is a chance of attracting funding. A report about scaling-up finance for sustainable energy investments of SE4All identifies as key factors that challenge project preparation:

  1. Lack of adequate project preparation funding for all phases of preparation.
  2. Lack of capacity to prepare good quality projects.
  3. Absence of institutional vehicle for project preparation.

In this sense, for a successful project preparation it is important to list all possible risks associated to the project. During any project preparation it is required a sound project structure to reduce uncertainties and allocate risks. However, often the focus is on some phases of the project cycle, rather than on all, often neglecting the earlier stages. This could later lead to an inadequate risk oversight and consequently to an unsuccessful and unsustainable project. Applying a de-risking approach consists of a series of activities to reduce the occurrence of risks or their influence at any point in a project's life. This is also known as 'Risk-management', and its fundamentals are the process of identifying risks, analysing them, determining the degree of tolerance and consequently accepting or designating mitigation or control actions.

An appropriate project preparation should include a range of activities and outputs across the entire project cycle, an example of a governmental project preparation is presented in the SE4All report:

Table 1: Project preparation [3]

 Project cycle phases

     Processes

  Detailed activities

   Examples of required outputs

Early stage

Concept development

Project identification and concept development

Sector planning, project identification and screening

Sector policy papers

Project concept notes

Prefeasibility reports

Establishing the enabling environment

Identifying legal/ regulatory/ institutional and other impediments and rectifying them

Laws

Regulations

Allocation of responsibilities

Mid to late stage

Feasibility, structuring and transacting

Due diligence

Detailed financial, legal, engineering, environmental and social appraisals

Reports that validate and develop concept further

Project structuring

Detailed financial and legal structuring

Financial models

Legal documentation

Marketing

Promotion of the project and assessment of private sector interest

Detailed project description/ information memorandum

Road shows/ conferences

Transacting

Procuring and negotiating project documentation

Bid documentation

Signed, negotiated project documentation

Source: Infrastructure Consortium for Africa, Assessment of Project Preparation Facilities for Africa (2012) in SE4All, Scaling Up Finance for Sustainable Energy Investments (2015)



Probable Risks and Suggestions for Mitigation & Control

There is a wide range of risks that could threaten the development, implementation and operation of energy projects. Some of the risks may ‘only being seen’ by investors, while developers and owner-operators are aware of other risks. Nevertheless it is important to address them holistically, ideally from the early phase on. The following table summarizes some of the risks identified in the literature review based on existing projects and lessons learned. It also includes suggestions on how risks can be minimized, mitigated or controlled during the life cycle of a project and by different actors.
Many of the listed risks might be context specific therefore do not refer to any specific technological solution per se; the listing provides a synopsis of common risks across, mainly, renewable technology, without analysing the interdependencies and relationships among risks. Moreover, some risks may correspond to more than one category, though the information has been arranged in this order (within six categories) to facilitate a better overview.
In addition, this article is open for further contributions.

Table 2: Probable risks and suggestions for mitigation and control

Technical risks

Risk Risk description Risk mitigation/ control mechanism

Load uncertainty[2][4]

Poor estimation of load size, growth and schedule, could derive in under- or oversized systems. This can lead to increased investment/running cost, lower efficiency, and unreliable supply.

Overestimated efficiency.

  • Recommended to perform in-field power ratings.
  • Use of design tools to estimate load.
  • Consider modular designs.
  • If possible, the design should include future expansion.
  • Limit the initial generation capacity and increase it gradually as demand grows.
  • Manage consumption according to the available capacity: load control or daily energy allowance.
  • Include energy efficiency measures.

Power quality[2]

Integrating PV and batteries, in retrofits on existing systems, may affect the stability of the grid due to incompatibilities and an ineffective control system.

  • Appropriate control strategy.
  • Appropriate design simulation prior implementation.
  • Consider distributed generation as it is less variable than centralized systems.

Equipment failure/ Downtime[2]

Premature failure of hardware can not only cause service interruption but damage the entire system.

In addition, despite existing warranties, these can be hard to fulfil due to the remoteness where they system is located.

  • Appropriate routine maintenance.
  • Equipment should meet quality standards and be appropriate for the environmental conditions.

Hardware compatibility issues[2]

Proprietary protocols could provoke incompatibility between components.

  • Use open based protocols.
  • Choose single provider.

Limitation for continuous supply/storage[2]

Batteries have a limited life-span and are vulnerable to be misused, this impacts on the energy balance and supply affecting the operation of generators (specific for hybrid systems).

  • Proper training.
  • Manage operators and user’s expectations.
  • Consider product selection.
  • Planning/budgeting for spare parts, replacement.

Familiarity with the technology[2]

Difficulty to operate and maintain, complexity of maintenance, limited knowledge on maintenance issues.

  • Continuous capacity building on technical aspects starting before implementation.
  • Trained technicians should receive payment for their job as incentive.

Future connectivity[2]

Interim solutions, such as mini-grids, would ideally be connected to the main grid if it becomes available, otherwise it becomes obsolete.

  • Design should consider the same standard as the central network.

Supply and installation issues[2][4]

Incorrect installation and operation of hardware, combined with the remoteness where the technology is installed.

  • Incorporate capacity development in the plan: proper training for local installers and operators.
  • Hire reliable contractors for installation and certain elements of the operation.
  • Rely on construction consultants to oversee project implementation and ensure that contractors comply with the expectations of the developers.

Building and testing[5]

Property damage or third-party liability arising from mishaps during building or testing.

 

Institutional/ Organizational risks 

Risk
Risk description Risk mitigation/ control mechanism

Stakeholder management[2]

Multiple parties involved whose activities, incentives, will not align between parties, causing negative outcomes.

  • Parties need to aware of their obligations and maintain a collaborative approach.
  • Agreements to protect every actor equally.

Operational[4]

Administration errors or fraud.

  • Simple standardisation like appropriate accounting and regular auditing.
  • Establishment of internal rules and the standardisation of processes.
  • Regular training for continous improvement, operational efficiency and service delivery.

Geographical isolation[2]

Difficulties to acquire spare parts and/or repair due to long distances, transportation challenges and lack of skilled personnel in the area.

  • Ensure local capacity building.
  • Routine and preventive maintenance should be properly scheduled.
  • Timely identification of the closest spare parts provider/s.

Geo-political risks

Risk Risk description Risk mitigation/ control mechanism

Change in public policy[4]

Increase in taxes levied on technology or import and export duties.

Subsidies affecting operation and/or profitability.

  • Political risks with high probability of occurrence may be hard to mitigate.

Political instability

Unrest, social conflicts, war.

 

Delays in approvals

Arbitrary actions of public authorities can affect the development of any energy access project.

  • Continuous involvement and consultation of local authorities during the development and implementation.

Arrival of the national grid

Investment’s payback and further cash flows could be in danger or threatened.

  • Continuous involvement and consultation of local authorities during the development and implementation.

Financial and economic risks

Risk Risk description Risk mitigation/ control mechanism

Commitment, competence and credit worthiness of investors[6]

Large level of investment/ long tenor of return, may require additional equity later after project has begun.

  • Credit assessment.
  • Verify the competence and/or knowledge regarding energy projects.

Inadequate business models[2]

Effective business models are key for deployment and may need to be continuously revised to scale up.

  • Information about similar experiences.
  • Seek for support to ensure capacity building and/or access to finance.
  • Choose models that are practical and appropriate for the local context.

Diesel and cost supply[2]

Although the use is reduced (hybrid systems), prices and availability impact the operation of the system.

  • Maximise other sources of generation.
  • Develop time-of-use-tariffs to discourage use when diesel would be required.

Exchange rates/ Inflation[6]

Foreign exchange rate changes due to devaluation, convertibility or transfer restrictions.

  • Borrow in local currency.
  • Cross-currency swaps (if possible).
  • Use hedging instruments (though this may be complex and expensive).
  • Involve local investors.

Credit[6]

Risk of default of counterparties or default on specific payments.

  • Good credit risk management.

Liquidity and refinancing[7]

Liquidity risks arising from revenue shortfalls or mismatches between the timing of cash receipts and payments. At the same time borrowers might be unable to refinance an outstanding loan due to inadequate loan terms or the maturity of the loan is mismatched with the lifetime of the project.

  • Internal liquidity facilities to advance or support payments to bridge short-term cash flow problems (i.e.: debt service reserve accounts, excess spread accounts, over-collateralisation, contingent equity).
  • External liquidity facilities provide a short-term letter of credit or credit line without additional cash requirements (i.e. Regional Liquidity Support Facility (RLSF) established in partnership between KfW, Africa Trade Insurance Agency and IRENA in sub-Saharan Africa).
  • Liquidity guarantee to lenghten loans.
  • Put options to refinance ensuring long-term lending for borrowers.

Social risks

Risk Risk description Risk mitigation/ control mechanism

Public resistance[4]

Resistance of interest groups because of visual aesthetics, water supply, smell (biogas), etc.

  • Include the whole community throughout the development and operation of the project.
  • Partnerships with local organizations can help to facilitate the relationship between developers and customers.
  • Implementation of capacity building measures and dedicated promotion of productive use of energy could support establishing local support.
  • Project should be well embedded in the socio-cultural context where is going to be built/ installed.
  • Ensure public opinion, transparency and involvement of local capacities.

Community/ social integration[2]

Over-consumption from one or few users can cause a black-out. Theft or users connecting loads beyond their quota.

  • Community engagement from the outset and follow up.
  • Avoid top-down approach.
  • Respect local organisational structures.
  • Manage and follow up user expectations: users should be aware of the potential limitations.
  • Enforce load control measures.
  • Tariff system to prevent overconsumption.
  • Proper education to discourage illegal connections: educate about the consequences or impact on the operation and performance of the system.

Appropriate pricing and payments[2][4]

Rural customers usually have low incomes which is challenging when setting a price that is both sufficiently high to give returns and low enough to make it affordable.

  • Tariffs should be flexible and revisable.
  • Educate about consequences of non-payment such as supply cut-off or penalties.
  • Uncomplicated bill setting and non-bureaucratic procedures for connection and consumption payment.
  • Smart metering systems equipped with tamper protection or in combination with incentives for electricity use.
  • Take into account possible inability to pay: income fluctuations and payment culture.
  • Verify the satisfaction of users (to avoid unwillingness to pay).

Operators and end users’ safety[2]

Risks of harm due to higher voltages and extensive wiring.

  • Provide appropriate training to operators and users.
  • Design and installation according to international standards.

Theft and vandalism[4]

Components or other valuable materials, for which there is a secondary market, are in danger of being stolen.

  • Secure perimeter.
  • Develop sense of ownership within the local community.

Environmental risks

Risk Risk description Risk mitigation/ control mechanism

Environmental

Harm to the environment caused by operating the technology may affect planning & permitting.

  • Environmental Impact Assessment (EIA).

Weather-related /availability[4]

Risk of fall in volume of electricity produced owing to lack of wind, sunshine, water flow/low rainfall, biomass availability.

 

  • If possible, obtain long term data to select site.
  • Establish close relationship to local biomass supply by creating dependency: supplying the supplier (fertilizer, bargain electricity price).

Force majeure[4]

Environmental disaster like severe storms, typhoons, sandstorms, volcanic eruption, earth quakes, mud slides, etc.

 

Source: Own elaboration based on literature review

Once projects are aware of the different risks they could face, it is important to consider that addressing all risks might be too expensive in terms of time and resources. For this reason it is important to prioritize risks, this can be done effectively using risk-management tools, which can later lead to decide appropriate measures. 



Risk Management

The optimum for a project is to reach a level of risk consciousness that can lead to elaborate effective and efficient mitigation strategies. Therefore risk management needs to be understood as a dynamic process, which should strive to include the ideas and insights from the different the different stakeholders involved in a project (investors, operators, users, etc.), especially during the risk identification.

Figure 1: Risk management main steps

RTENOTITLE



Source: Own elaboration based on FEMA (2017)[8] and Manetsgruber et al. (2015)[4]

The first step of risk management will result in an overview of all risks associated to different aspects in a project (i.e. the categories considered in Table 2). Every risk should be assessed according to the magnitude of its impact potential and the probability of it to happen. A common and widely used risk management tool to visualise the impact of individual risks is a risk map as shown in Figure 2. 

Figure 2: Risk map with different colors indicating levels of importance

RTENOTITLE


Source: Manetsgruber et al. (2015)[4]


The colour differentiation in a risk map indicates the level of importance of each risk. As mentioned, risk management is an iterative process and a risk map can be used to better understand the current risk situation at a particular moment in time, it also represents the outcome or risk mitigation interventions. Being aware of the risks does not necessarily mean to address each of them. Prioritization can be done effectively using the map (chart) in which risks are assessed in two dimensions:

  • Probability - to probability of a risk to occur.
  • Impact (Loss potential) - the size of the impact varies in terms of different factors (i.e. costs).

Considering both dimensions, there are four possible levels where risks can be placed[9]:

  1. Low impact/ Low probability - risks at the bottom left corner are low level, these can be often ignored.
  2. Low impact/ High probability - risks in the bottom right corner are of moderate importance, the project should reduce the likelihood of these to occur.
  3. High impact/ low probability - risks in the top left corner are of high importance, but they are unlikely to happen. Contingency plans should be in place.
  4. High impact/ high probability - risks located at the top right corner are critical and should be a top priority for the project.

Based on these four leveles and according to the Risk Management Approach Guide (Manetsgruber et al., 2015)[4] there are four general risk management levels that can be developed after analysing the data contained in a risk map (Figure 3). This serves to identify primary strategies to address each risk, and could be adjusted or replaced if necessary over the life cycle of a project. The different strategies can derive from the risk map itself in relation to the impact magnitude and probability, according to levels of:

  • Risk tolerance: these type of risks occur rarely and have a low negative impact, the project should be aware of them but there is no need of further action, though these need to be observed and re-assessed if necessary.
  • Risk transfer: these risks have a high impact potential and low probability of occurrence, therefore these should be transferred to or covered by a willing third party as they can cause significant harm to the project.
  • Risk reduction: risks have a high probability of occurrence and low impact, resource buffers or emergency measures con be applied to reduce the possibility of it to occur. Likewise, measures like for example specific operation practices, training and technology upgrades, among others, can deflect or prevent the threats of these risks.
  • Risk avoidance: these risks require actions to mitigate them to decrease the probability of occurrence.

Figure 3: Risk map with four generic strategic risk zones

RTENOTITLE

Source: Manetsgruber et al. (2015)[4]

Rural energy access displays a high degree of complexity and it is required to think about developing a specific risk management approach, tailor-made for the type and scale of the projects[4].




Best Practices

Risk management for mini grids Risk Management Approach Guide)- Case-based analysis on the economics of mini-grids based on different projects with different: power generation techniques, Business models approaches and integration to given circumstances (page 41- 48) and recommendations (page 50).

Uganda: Solar Kirchner uses an anchor business customer

  • The payment risk, including the lack of willingness or ability to pay, is reduced by ensuring stable loads and cash flows by an anchor business, a telecommunication tower. Nearby villages profit from electrification.[4]

Laos: Sunlabob applies risk management by asset splitting

  • Negotiation with the national utility to ensure steady incomes for the mini-grid operators after national grid arrives will reduced the payment risk. As does supporting local micro-entrepreneurship.
  • Diversifying the power-generating sources (hydro, PV, and a diesel) reduces the technology and performance risk, as well as the resource availability risk.
  • Splitting the assets into three categories reduces the total loss of investment risk: public owned infrastructural assets (grid), private owned movable assets, and productive use assets are owned by local entrepreneurs.[4]

Senegal: INENSUS adopts strategies to reduce unpredictable demand

  • To reduce the risk of unpredictable demand prepaid energy users purchase 'energy blocks' that are consumed during a certain period of time otherwise they expire.
  • As a form to regulate consumption, the system allows users to trade unused 'energy blocks' whitin the village. The use of intelligent smart meters enables users to monitor their own consumption.
  • Additional income for users is possible as they trade unused 'energy blocks' according a price they set themselves.
  • Customers are ranked in categories (high and low priority) to ensure that in times of energy shortage high priority customers will remain connected to the grid, reducing the risk of unpredictable demand.

Cape Verde: Trama Tecno Ambiental (TTA) applied a tariff design and created micro-business for energy surplus

  • With the use of smart meters users determine and adjust their future demand reducing payment risk.
  • To reduce the unpredictable demand risk, a micro-business (commercialisation of ice) has been established to make use of solar energy surplus, generating also additional income for the facility.

Senegal: Kaito ensures long term revenue

  • Before starting operations, micro-business creation was fostered including the electrfication of existing businesses concentrated in a market area to ensure stable payments after implementation to reduce the risk of non-payment.
  • To reduce the risk of social acceptance all relevant stakeholders are involved at the beginning of the project.

Large scale projects


Further Reading

References

  1. Painuly, Jyoti Prasad, ‘Barriers to renewable energy penetration; a framework for analysis’, Renewable Energy 24, 2001. http://www1.upme.gov.co/SGIC/sites/default/files/Barriers%20to%20renewable%20energy%20penetration.pdf
  2. 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.13 2.14 2.15 Hazelton, James; Bruce, Anna; MacGill Iain, ‘A review of the potential benefits and risks of photovoltaic hybrid mini-grid systems’, Renewable Energy 67, 2013. https://www.researchgate.net/publication/259298363_A_review_of_the_potential_benefits_and_risks_of_photovoltaic_hybrid_mini-grid_systems Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Hazelton (2013)" defined multiple times with different content
  3. SE4All Advisory Board's Finance Committee, 'Scaling Up FInance for Sustainable Energy Investments, 2015. http://www.se4all.org/sites/default/files/SE4All-Advisory-Board-Finance-Committee-Report.pdf
  4. 4.00 4.01 4.02 4.03 4.04 4.05 4.06 4.07 4.08 4.09 4.10 4.11 4.12 4.13 4.14 4.15 Manetsgruber, David; Wagemann, Bernanrd; Kondev, Bozhil; Dziergwa, Katrin. Risk Management for Mini-Grids: A new approach to guide mini-grid development. 2015. https://www.ruralelec.org/sites/default/files/risk_management_for_mini-grids_2015_final_web_0.pdf Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Manetsgruber (2015)" defined multiple times with different content
  5. The Economist, ‘Managing the risk in renewable energy’, 2011 https://www.altran.de/fileadmin/medias/DE.altran.de/documents/Fachartikel/Managing-The-Risk-In-Renewable-Energy.pdf
  6. 6.0 6.1 6.2 Green Rhino Energy, ‘Project Risk Matrix’, 2013, http://www.greenrhinoenergy.com/finance/renewable/risks.php Cite error: Invalid <ref> tag; name "Green (2013)" defined multiple times with different content Cite error: Invalid <ref> tag; name "Green (2013)" defined multiple times with different content
  7. IRENA, ‘Unlocking renewable energy investment: the role of risk mitigation and structured finance’, 2016, https://www.irena.org/DocumentDownloads/Publications/IRENA_Risk_Mitigation_and_Structured_Finance_2016.pdf
  8. FEMA, Risk Mapping, Assessment and Planning (Risk Map), Department of Homeland Security US, 2017,https://www.fema.gov/risk-mapping-assessment-and-planning-risk-map
  9. Mind Tools, 'Risk Impact/ Probability Chart', 2017. https://www.mindtools.com/pages/article/newPPM_78.htm