Small Hydro Power Project Nepal - Supporting Financial Institutions
This is part of a condensed report on the Small Hydropower Promotion Projct (SHPP). For an overview on the whole report please refer to following page: SHPP Report. |
Supporting Financial institutions
A large aspect of SHPP’s sector development focussed on SHP financing. Improving the stability of political, regulatory and financial environments builds the basis for the provision of SHP investment opportunities and capital inflows. Even though this is a big task to be carried by the renewable energies or SHP sectors alone, there have been many activities in the past years to mitigate factors that are deterring private equity and debt providers from involvement in SHP in Nepal. We will highlight a few experiences from banks, insurers and investors. What they have in common is that they seek financing opportunities that deliver a good balance of security (predictability of the environment, risk, insurance), liquidity (exit options) and yield (returns), based on their own motivations and profiles.
Banks Counselling
Given investment volumes in the range of a few million USD, an important part of technical support to the sector included upgrading the capacity of the financial institutions to understand small hydropower generation and to understand whether a project was going to be feasible or profitable. The sector needed a party to carry out appraisals on received proposals. In former times the Nepal Industrial Development Corporation (NIDC) used to provide a similar service for tourism and agriculture/forestry projects, but this service was terminated in 1990 after a failed attempt to merge NIDC with the Ministry of Industry. Now financial institutions needed to rely on external experts or develop in-house expertise like the Clean Energy Bank (see box). SHPP conducted many events to bring this expertise to financial institutions, using training sessions with Swiss and local technical and financial experts.
“No risk – No Gain”
The idea that no worthwhile profit will be gained without a substantial amount of input is a well known concept when it comes to investment. Still, smart investors are aware of the risks they are taking and should know which opportunities exist to mitigate such risks. The table below groups the main risks that investments in renewable energies are exposed to.
Risk | Description/examples | Mitigation |
Hydrological and Environmental Risks | Landslides, floods; ESIA/permits; |
Proper analysis; |
Socio cultural/community conflict. | ||
Professional Risks | Cost/time overrun during construction |
Turn key or CPE contracts? active monitoring, penalties to contractors in case of delay, insurance Guarantee from contractor, EM supplier and designer. |
Design failure or inability to reach designed output/performance during operation. | ||
Political Risks | Risk of confiscation, expropriation and nationalization; |
Improvement of political framework conditions – stability; Very limited influence by investors. |
Changed regulation on tax holidays; | ||
Political unrest; Strikes | ||
Market Risk | Reliability of buyer |
Good PPA, guaranteed for at least payback period; Different rates in dry / wet season. |
Public and private investors and equity financing
The main advantage of working with these financiers is that they can bring in a lot of ‘non-financial resources’ like modern and efficient project management skills. This often leads to significant efficiency and productivity increases. Additionally, this kind of capital and the corresponding ‘non-financial resources’ have a leveraging effect of attracting debt financing at more interesting terms.
In the case of Nepal, these financiers have certainly had a good influence on single SHP projects and the growing volume of private SHP plants in operation. There is, however, a strong indication that organising this kind of capital through equity investment companies could result in better accessibility to capital for SHP financing.
For further information about Project Financing click here.
Mechanisms and Mechanics of Perfecting Security under Project Finance
The following factors must be considered in the loaning of money on project finance basis for a hydropower project in order to perfect security.
Revenue: watertight arrangement for commercial operation during debt service period:
- PPA:
- Assign it to the lender(s) with the Nepal Electricity Authority’s (NEA) consent.
- Ensure that the revenue stream received from NEA is directed to a bank account specified by the lender. NEA will have to be approached for their concurrence.
- Designate such a bank account as an ‘escrow account’ in which the lender shall have the first lien.
- Allow the developer to withdraw money from such an account without any hindrance only to the extent necessary to operate the project plant and to maintain the plant in top condition pursuant to ‘prudent operating practices’.
- Money to be automatically transferred to the lenders for their debt service (both principal and interest thereon) on specified dates.
- Allow the developer to withdraw money from the account for the distribution of dividend to its shareholders, to the extent permissible based on fund balance in the escrow account after leaving an amount necessary to meet one (or the unit agreed between the borrower and lender) debt service obligation in immediate future.
Expenditure: watertight arrangement during construction period
- Assign all contracts or agreements, inter alia, related to construction, supply, transportation, erection or installation, consultancies (design, engineering, supervision, etc.) to the lenders so that they are able to continue to complete implementation and operation of the project in the case of borrower default by being able to step into the shoes of the borrower or have someone do so on the lender’s behalf. (Should even include employment contracts of key personnel that are indispensable for the implementation of the project!)
- Ensure that the borrower company’s equity-holders inject their equity, at least, on pari passu basis, if not more, during the implementation of the project.
- Ensure that both debt and equity for the project are injected into a dedicated bank account on which the lender has the first lien and outflows from this account are closely monitored by the lender.
- Ensure that proper contractual arrangements are made such that (a) cost and (b) time constraints are not exceeded. (Time overrun tends to be more expensive than cost overrun due to additional interest during construction, loss of revenue and even penalty to NEA for delayed delivery of electricity.).
- Ensure that there are no gaps and cracks between various contracts or agreements, which could increase the total project cost.
- Ensure that the borrower company has or is able to access the necessary contingency fund to complete the project even if the project cost goes up due to unforeseen reasons.
- Payments for construction closely supervised by lenders.
Safety-net: success or failure dependent on robust and sturdy safety-net of insurance
- Risk assessment should be made to prepare a risk profile, which will dictate the insurance program.
- Ensure that all necessary insurance policies are put in place in order to cover all exposures to all possible risks (e.g., CAR, EAR, TAR, ALOP, increase in cost due to devaluation, contractors’ equipment, third party liability, comprehensive workmen’s compensation, professional liability and so on and so forth). The words of the proposed insurance policies are to be finalized in consultation with the lender.
- Ensure that the lender is mentioned in such insurance policies as the co-insured in order to provide for the eventualities emanating from default by the borrower.
- Ensure that the project’s cost estimate has adequately budgeted for the payment of insurance premium.
- Documentation to perfect security
- Execute loan agreement between the lender and the borrower to sign off on the arrangements agreed and put in place as listed above.
- Have such agreement ‘registered’ wherein all tangible and intangible (various contracts, agreements, license, etc.) assets are mortgaged against the loan, enabling the lender to foreclose without having to resort to court of law.
Risk Management (Ratna Sansar Shrestha, FCA)
Financing a hydropower project is very heavily dependent on prudent management of risk. This involves identification of various risks associated with a project and assessment thereof. However, the most important step lies in arranging measures to mitigate such risks, including an effective insurance program. Let us take a look at certain important risks from the perspective mentioned here.
Foreign Exchange Risk
A developer can borrow locally or from foreign institutions and the conditions with regard to security will be the same. However, the borrower’s exposure to certain risk will be different. There are two main types of risks that a borrower needs to be aware of when borrowing from a foreign lender.
Foreign exchange risk is inherent in foreign loan due to the fact that foreign currency tends to be relatively strong compared to Nepalese currency. This risk materializes with devaluation, if revenue is denominated in local currency while having to service the loan denominated in foreign currency. Similarly, this risk may also be manifest in the rising cost of imports. This risk can be mitigated by (a) either having the loan denominated in local currency or (b) rate of revenue denominated in foreign currency. In the case of increase in the cost of imports, an insurance coverage against cost escalation would mitigate this risk.
Repatriation Risk
Another risk associated with foreign loan is ‘repatriation risk’. This becomes of greater concern to a lender if he is not able to repatriate the proceeds of debt servicing. Generally, governments of developing countries, in their quest to attract foreign investment, have enacted legislation guaranteeing repatriation. If such a guarantee is not available, either the lender will not make a loan or will make it subject to exorbitant rates of interest. In Nepal repatriation is guaranteed by Foreign Investment & Technology Transfer Act, 2049 and Electricity Act, 2049 for hydropower projects. A foreign investor is also subject to this risk.
Sovereign Risk (Country Risk)
A foreign entrepreneur investing in Nepal is exposed to risks such as those associated with the government’s creditworthiness, the possibility of expropriation and nationalization, changes in the local political environment and enforceability of contracts. These types of risks are known as sovereign and country risks. Multilateral Investment Guarantee Association (MIGA), a member of The World Bank Group, provides insurance against such risks for a fee. However, the availability of such insurance is limited only to foreign investors.
Interest Rates
It is now time, we also touch upon the concept of interest rate risk. Lenders offer two kinds of interest rates: (a) floating rate and (b) fixed rate. Floating rate entails changes in the interest rate during the term of the loan, thereby introducing an element of uncertainty or risk for the borrower. Banks prefer floating rates as they need to be able to adapt to changes in financial market as well as to cover their own exposure to the vagaries of changing interest rates (including bank rate). For a developer, the fixed rate is the best way to mitigate this risk. However, banks tend to add a margin to the then prevalent rate to cushion their own risk.
Inflation Risk
The real value of a unit of nominal currency tends to depreciate over time with inflation. Even hard currency is subject to this risk. Escalation in the rate of tariff is the only answer, short of trying to hold down the inflation with one’s bare hands!
Legislative Change Risk
Here, we are talking about the risk of changes in the country’s laws that (a) increases rates and taxes or other expenses and liabilities, (b) reduces revenue of the project, or (c) reduces the value of the assets. Such changes impact the viability of a project adversely. Generally an entrepreneur has to take such risks. However, it can also be mitigated by passing the impact through to the utility, provided that the utility is amenable to such pass through.
Market Risk
It is common knowledge amongst engineers that energy requires guaranteed market, due to the constraint with regard to, primarily, storage and transmission. A simple way to mitigate this risk is to sign a long-term PPA with the utility.
Revenue Risk
A developer can have a long-term PPA, but such a PPA may also not ensure plant factor at a specific level if the utility accepts delivery of the energy at its pleasure, mainly in the case of a run-of-the-river type of project lacking poundage. This means there will not be a guaranteed stream of revenue to the project in order for it to meet its financial obligation with regard to (a) operation, maintenance and repairs, and (b) debt servicing. ‘Take or pay’ type of PPA mitigates this risk.
However, with respect to both market risks and revenue risk, it needs to be noted that electric energy is being traded in spot markets in Western Europe.
Payment Risk
This risk emanates from the lack of creditworthiness on the part of the utility, buyer of the energy. In many developing countries, state-owned utilities do not have established credit histories and also suffer from records of poor management, over-employment, high leakage (technical or otherwise), etc.
Developers are known to ask the government to issue counter-guarantees to cover payment risk. This basically entails a government standing surety to the fact that the utility pays its dues to the developer in time, and in the case of the utility’s failure to meet its obligations, the government is required to promptly make payments to mitigate the delinquency of the utility. Nowadays, multilateral funding agencies like the World Bank take a dim view of a government issuing counter guarantee. Having a letter of credit put in place by the utility with the IPP as the beneficiary is another way of mitigating this risk for short term.
Construction Risk
Time and cost overrun risks are a group of construction risks of which time overrun risks result in loss of revenue as well as raising total amount of interest during construction of debt financing and may even attract a penalty for late delivery of energy. Other construction risks are force majeure risk, socioeconomic or environmental risk, geological risk, performance risk, design risk, etc. One can arrange insurance coverage against such risks like CAR, TAR, EAR, professional liability, etc, including ‘advance loss of profit insurance’, which can be complemented by signing a ‘fixed price’ turnkey contract (or EPC contract) and incorporating a clause for imposition of liquidated damages on the contractor for delayed substantial completion or commissioning of the plant.
Hydrological Risk
The ‘take-or-pay’ nature of the PPA guarantees the fact that all energy produced by a plant, depending on the availability of water, irrespective of whether the season is dry or wet, shall be turned into cash. However, if there is no water to generate energy due to the change in the level of precipitation, climatic reason or change in the hydrology of the catchment area, then these projects are on their own. This risk emanates from the fact that seasonal rainfall patterns affect the amount of water available to a hydropower plant and generation may fall below contract levels in any season, thus threatening the revenue stream of such projects. Obviously, a dry year will be an unmitigated disaster for a hydropower plant. The most effective way to mitigate hydrology risk is to gather hydrological data for a reasonable number of years in the past and design the project accordingly after having selected a project with better hydrological potential as well as information.