= Overview =
 
= Overview =
Line 8: Line 6:
 
The following table summarizes some of the risks identified based on existing projects and lessons learned from the literature review. Though this article is open for further contributions.
 
The following table summarizes some of the risks identified based on existing projects and lessons learned from the literature review. Though this article is open for further contributions.
  
Some of the risks listed may be context specific, some are view from the ‘owner’ point of view, while others from the investor perspective. Moreover, the listed risks may correspond to more than one of the categories, though the information has been arranged in this order to facilitate an overview.
+
Some of the risks listed may be context specific, some are looked at from the ‘owner’ point of view, while others from the investor perspective. Moreover, the listed risks may correspond to more than one of the categories, though the information has been arranged this order within six categories to facilitate an overview.
  
 
 
 
 
  
{| border="1" cellspacing="0" cellpadding="0" width="1340"
+
{| style="width: 1340px" cellspacing="0" cellpadding="0" border="1"
 
|-
 
|-
| style="width:119px;height:36px;" |  
+
| style="width:119px; height:36px" |  
 
'''Category'''
 
'''Category'''
  
| style="width:121px;height:36px;" |  
+
| style="width:121px; height:36px" |  
 
'''Risk'''
 
'''Risk'''
  
| style="width:306px;height:36px;" |  
+
| style="width:306px; height:36px" |  
 
'''Risk description'''
 
'''Risk description'''
  
| style="width:268px;height:36px;" |  
+
| style="width:268px; height:36px" |  
 
'''Risk mitigation/ control mechanism'''
 
'''Risk mitigation/ control mechanism'''
  
| style="width:78px;height:36px;" |  
+
| style="width:78px; height:36px" |  
 
'''Reference'''
 
'''Reference'''
  
 
|-
 
|-
| rowspan="9" style="width:119px;height:77px;" |  
+
| rowspan="9" style="width:119px; height:77px" |  
 
Technical
 
Technical
  
| style="width:121px;height:77px;" |  
+
| style="width:121px; height:77px" |  
 
Load uncertainty
 
Load uncertainty
  
| style="width:306px;height:77px;" |  
+
| style="width:306px; height:77px" |  
 
Poor estimation of load size, growth and schedule, could derive in under- or oversized systems. This can lead to increased investment/running cost, lower efficiency, and unreliable supply.
 
Poor estimation of load size, growth and schedule, could derive in under- or oversized systems. This can lead to increased investment/running cost, lower efficiency, and unreliable supply.
  
 
Overestimated efficiency
 
Overestimated efficiency
  
| style="width:268px;height:77px;" |  
+
| style="width:268px; height:77px" |  
 
*Recommended to perform in-field power ratings.
 
*Recommended to perform in-field power ratings.
 
*Use of design tools to estimate load.
 
*Use of design tools to estimate load.
Line 50: Line 48:
 
*Include energy efficiency measures.
 
*Include energy efficiency measures.
  
| style="width:78px;height:77px;" |  
+
| style="width:78px; height:77px" |  
 
2, 5
 
2, 5
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Power quality
 
Power quality
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Integrating PV and batteries, in retrofits on existing systems, may affect the stability of the grid due to incompatibilities and an ineffective control system.
 
Integrating PV and batteries, in retrofits on existing systems, may affect the stability of the grid due to incompatibilities and an ineffective control system.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Appropriate control strategy.
 
*Appropriate control strategy.
 
*Appropriate design simulation prior implementation.
 
*Appropriate design simulation prior implementation.
 
*Consider distributed generation as it is less variable than centralized systems.
 
*Consider distributed generation as it is less variable than centralized systems.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
2
 
2
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Equipment failure/ Downtime
 
Equipment failure/ Downtime
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Premature failure of hardware can not only cause service interruption but damage the entire system.
 
Premature failure of hardware can not only cause service interruption but damage the entire system.
  
 
In addition, despite existing warranties, these can be hard to fulfil due to the remoteness where they system is located.
 
In addition, despite existing warranties, these can be hard to fulfil due to the remoteness where they system is located.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Appropriate routine maintenance.
 
*Appropriate routine maintenance.
 
*Equipment should meet quality standards and be appropriate for the environmental conditions.
 
*Equipment should meet quality standards and be appropriate for the environmental conditions.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
2
 
2
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Hardware compatibility issues
 
Hardware compatibility issues
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Proprietary protocols could provoke incompatibility between components.
 
Proprietary protocols could provoke incompatibility between components.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Use open based protocols.
 
*Use open based protocols.
 
*Choose single provider.
 
*Choose single provider.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
2
 
2
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Limitation for continuous supply/storage
 
Limitation for continuous supply/storage
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Batteries have a limited life-span and are vulnerable to be misused, this impacts on the energy balance and supply affecting the operation of generators (specific for hybrid systems).
 
Batteries have a limited life-span and are vulnerable to be misused, this impacts on the energy balance and supply affecting the operation of generators (specific for hybrid systems).
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Proper training.
 
*Proper training.
 
*Manage operators and user’s expectations.
 
*Manage operators and user’s expectations.
Line 111: Line 109:
 
*Planning/budgeting for spare parts, replacement.
 
*Planning/budgeting for spare parts, replacement.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
2
 
2
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Familiarity with the technology
 
Familiarity with the technology
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Difficulty to operate and maintain, complexity of maintenance, limited knowledge on maintenance issues.
 
Difficulty to operate and maintain, complexity of maintenance, limited knowledge on maintenance issues.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Continuous capacity building on technical aspects starting before implementation.
 
*Continuous capacity building on technical aspects starting before implementation.
 
*Trained technicians should receive payment for their job as incentive.
 
*Trained technicians should receive payment for their job as incentive.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
2
 
2
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Future connectivity
 
Future connectivity
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Interim solutions, such as mini-grids, would ideally be connected to the main grid if it becomes available, otherwise it becomes obsolete.
 
Interim solutions, such as mini-grids, would ideally be connected to the main grid if it becomes available, otherwise it becomes obsolete.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Design should consider the same standard as the central network
 
*Design should consider the same standard as the central network
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
2
 
2
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Supply and installation issues
 
Supply and installation issues
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Incorrect installation and operation of hardware, combined with the remoteness where the technology is installed.
 
Incorrect installation and operation of hardware, combined with the remoteness where the technology is installed.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Incorporate capacity development in the plan: proper training for local installers and operators.
 
*Incorporate capacity development in the plan: proper training for local installers and operators.
 
*Hire reliable contractors for installation and certain elements of the operation.
 
*Hire reliable contractors for installation and certain elements of the operation.
 
*Rely on construction consultants to oversee project implementation and ensure that contractors comply with the expectations of the developers.
 
*Rely on construction consultants to oversee project implementation and ensure that contractors comply with the expectations of the developers.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
2, 5
 
2, 5
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Building and testing
 
Building and testing
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Property damage or third-party liability arising from mishaps during building or testing.
 
Property damage or third-party liability arising from mishaps during building or testing.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
 
 
 
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
4
 
4
  
 
|-
 
|-
| rowspan="3" style="width:119px;height:9px;" |  
+
| rowspan="3" style="width:119px; height:9px" |  
 
Institutional/ Organizational
 
Institutional/ Organizational
  
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Stakeholder management
 
Stakeholder management
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Multiple parties involved whose activities, incentives, will not align between parties, causing negative outcomes.
 
Multiple parties involved whose activities, incentives, will not align between parties, causing negative outcomes.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Parties need to aware of their obligations and maintain a collaborative approach.
 
*Parties need to aware of their obligations and maintain a collaborative approach.
 
*Agreements to protect every actor equally.
 
*Agreements to protect every actor equally.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
2
 
2
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Operational
 
Operational
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Administration errors or fraud.
 
Administration errors or fraud.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Simple standardisation like appropriate accounting and regular auditing.
 
*Simple standardisation like appropriate accounting and regular auditing.
 
*Establishment of internal rules and the standardisation of processes.
 
*Establishment of internal rules and the standardisation of processes.
 
*Regular training for contentious improvement, operational efficiency and service delivery.
 
*Regular training for contentious improvement, operational efficiency and service delivery.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
5
 
5
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Geographical isolation
 
Geographical isolation
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Difficulties to acquire spare parts and/or repair due to long distances, transportation challenges and lack of skilled personnel in the area.
 
Difficulties to acquire spare parts and/or repair due to long distances, transportation challenges and lack of skilled personnel in the area.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Ensure local capacity building.
 
*Ensure local capacity building.
 
*Routine and preventive maintenance should be properly scheduled.
 
*Routine and preventive maintenance should be properly scheduled.
 
*Timely identification of the closest spare parts provider/s.
 
*Timely identification of the closest spare parts provider/s.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
2
 
2
  
 
|-
 
|-
| rowspan="4" style="width:119px;height:9px;" |  
+
| rowspan="4" style="width:119px; height:9px" |  
 
Geo-political
 
Geo-political
  
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Change in public policy
 
Change in public policy
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Increase in taxes levied on technology or import and export duties.
 
Increase in taxes levied on technology or import and export duties.
  
 
Subsidies affecting operation and/or profitability.
 
Subsidies affecting operation and/or profitability.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Political risks with high probability of occurrence may be hard to mitigate.
 
*Political risks with high probability of occurrence may be hard to mitigate.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
5
 
5
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Political instability
 
Political instability
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Unrest, social conflicts, war.
 
Unrest, social conflicts, war.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
 
 
 
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
 
 
 
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Delays in approvals
 
Delays in approvals
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Arbitrary actions of public authorities can affect the development of any energy access project.
 
Arbitrary actions of public authorities can affect the development of any energy access project.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Continuous involvement and consultation of local authorities during the development and implementation.
 
*Continuous involvement and consultation of local authorities during the development and implementation.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
 
 
 
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Arrival of the national grid
 
Arrival of the national grid
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Investment’s payback and further cash flows could be in danger or threatened.
 
Investment’s payback and further cash flows could be in danger or threatened.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Continuous involvement and consultation of local authorities during the development and implementation.
 
*Continuous involvement and consultation of local authorities during the development and implementation.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
 
 
 
  
 
|-
 
|-
| rowspan="6" style="width:119px;height:9px;" |  
+
| rowspan="6" style="width:119px; height:9px" |  
 
Finance and Economics
 
Finance and Economics
  
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Commitment, competence and credit worthiness of investors
 
Commitment, competence and credit worthiness of investors
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Large level of investment/ long tenor of return, may require additional equity later after project has begun.
 
Large level of investment/ long tenor of return, may require additional equity later after project has begun.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Credit assessment.
 
*Credit assessment.
 
*Verify the competence and/or knowledge regarding energy projects.
 
*Verify the competence and/or knowledge regarding energy projects.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
3
 
3
  
 
|-
 
|-
| style="width:121px;height:9px;" |  
+
| style="width:121px; height:9px" |  
 
Inadequate business models
 
Inadequate business models
  
| style="width:306px;height:9px;" |  
+
| style="width:306px; height:9px" |  
 
Effective business models are key for deployment and may need to be continuously revised to scale up.
 
Effective business models are key for deployment and may need to be continuously revised to scale up.
  
| style="width:268px;height:9px;" |  
+
| style="width:268px; height:9px" |  
 
*Information about similar experiences.
 
*Information about similar experiences.
 
*Seek for support to ensure capacity building and/or access to finance.
 
*Seek for support to ensure capacity building and/or access to finance.
 
*Chose models that are practical and appropriate for the local context.
 
*Chose models that are practical and appropriate for the local context.
  
| style="width:78px;height:9px;" |  
+
| style="width:78px; height:9px" |  
 
2
 
2
  
 
|-
 
|-
| style="width:121px;height:68px;" |  
+
| style="width:121px; height:68px" |  
 
Diesel and cost supply
 
Diesel and cost supply
  
| style="width:306px;height:68px;" |  
+
| style="width:306px; height:68px" |  
 
Although the use is reduced (hybrid systems), prices and availability impact the operation of the system.
 
Although the use is reduced (hybrid systems), prices and availability impact the operation of the system.
  
| style="width:268px;height:68px;" |  
+
| style="width:268px; height:68px" |  
 
*Maximise other sources of generation.
 
*Maximise other sources of generation.
 
*Develop time-of-use-tariffs to discourage use when diesel would be required.
 
*Develop time-of-use-tariffs to discourage use when diesel would be required.
  
| style="width:78px;height:68px;" |  
+
| style="width:78px; height:68px" |  
 
2
 
2
  
 
|-
 
|-
| style="width:121px;height:88px;" |  
+
| style="width:121px; height:88px" |  
 
Exchange rates/ Inflation
 
Exchange rates/ Inflation
  
| style="width:306px;height:88px;" |  
+
| style="width:306px; height:88px" |  
 
Foreign exchange rate changes due to devaluation, convertibility or transfer restrictions.
 
Foreign exchange rate changes due to devaluation, convertibility or transfer restrictions.
  
| style="width:268px;height:88px;" |  
+
| style="width:268px; height:88px" |  
 
*Borrow in local currency.
 
*Borrow in local currency.
 
*Cross-currency swaps (if possible).
 
*Cross-currency swaps (if possible).
Line 332: Line 330:
 
*Involve local investors.
 
*Involve local investors.
  
| style="width:78px;height:88px;" |  
+
| style="width:78px; height:88px" |  
 
3
 
3
  
 
|-
 
|-
| style="width:121px;height:35px;" |  
+
| style="width:121px; height:35px" |  
 
Credit
 
Credit
  
| style="width:306px;height:35px;" |  
+
| style="width:306px; height:35px" |  
 
Risk of default of counterparties or default on specific payments.
 
Risk of default of counterparties or default on specific payments.
  
| style="width:268px;height:35px;" |  
+
| style="width:268px; height:35px" |  
 
*Good credit risk management.
 
*Good credit risk management.
  
| style="width:78px;height:35px;" |  
+
| style="width:78px; height:35px" |  
 
3
 
3
  
 
|-
 
|-
| style="width:121px;height:17px;" |  
+
| style="width:121px; height:17px" |  
 
Liquidity
 
Liquidity
  
| style="width:306px;height:17px;" |  
+
| style="width:306px; height:17px" |  
 
 
 
 
  
| style="width:268px;height:17px;" |  
+
| style="width:268px; height:17px" |  
 
 
 
 
  
| style="width:78px;height:17px;" |  
+
| style="width:78px; height:17px" |  
 
 
 
 
  
 
|-
 
|-
| rowspan="5" style="width:119px;height:287px;" |  
+
| rowspan="5" style="width:119px; height:287px" |  
 
Social
 
Social
  
| style="width:121px;height:287px;" |  
+
| style="width:121px; height:287px" |  
 
Public resistance
 
Public resistance
  
| style="width:306px;height:287px;" |  
+
| style="width:306px; height:287px" |  
 
Resistance of interest groups because statics, water supply, smell (biogas), etc.
 
Resistance of interest groups because statics, water supply, smell (biogas), etc.
  
| style="width:268px;height:287px;" |  
+
| style="width:268px; height:287px" |  
 
*Include the whole community throughout the development and operation of the project.
 
*Include the whole community throughout the development and operation of the project.
 
*Partnerships with local organizations can help to facilitate the relationship between developers and customers.
 
*Partnerships with local organizations can help to facilitate the relationship between developers and customers.
Line 378: Line 376:
 
*Ensure public opinion, transparency and involvement of local capacities
 
*Ensure public opinion, transparency and involvement of local capacities
  
| style="width:78px;height:287px;" |  
+
| style="width:78px; height:287px" |  
 
5
 
5
  
 
|-
 
|-
| style="width:121px;height:106px;" |  
+
| style="width:121px; height:106px" |  
 
Community/social integration
 
Community/social integration
  
| style="width:306px;height:106px;" |  
+
| style="width:306px; height:106px" |  
 
Over-consumption from one or few users can cause a black-out. Theft or users connecting loads beyond their quota.
 
Over-consumption from one or few users can cause a black-out. Theft or users connecting loads beyond their quota.
  
| style="width:268px;height:106px;" |  
+
| style="width:268px; height:106px" |  
 
*Community engagement from the outset and follow up.
 
*Community engagement from the outset and follow up.
 
*Avoid top-down approach.
 
*Avoid top-down approach.
Line 397: Line 395:
 
*Proper education to discourage illegal connections: educate about the consequences or impact on the operation and performance of the system.
 
*Proper education to discourage illegal connections: educate about the consequences or impact on the operation and performance of the system.
  
| style="width:78px;height:106px;" |  
+
| style="width:78px; height:106px" |  
 
2
 
2
  
 
|-
 
|-
| style="width:121px;height:287px;" |  
+
| style="width:121px; height:287px" |  
 
Appropriate pricing and payments
 
Appropriate pricing and payments
  
| style="width:306px;height:287px;" |  
+
| style="width:306px; height:287px" |  
 
Rural customers usually have low incomes which is challenging when setting a price that is both sufficiently high to give returns and low enough to make it affordable.
 
Rural customers usually have low incomes which is challenging when setting a price that is both sufficiently high to give returns and low enough to make it affordable.
  
| style="width:268px;height:287px;" |  
+
| style="width:268px; height:287px" |  
 
*Tariffs should be flexible and revisable
 
*Tariffs should be flexible and revisable
 
*Educate about consequences of non-payment such as supply cut-off or penalties.
 
*Educate about consequences of non-payment such as supply cut-off or penalties.
Line 415: Line 413:
 
*Verify the satisfaction of users (to avoid unwillingness to pay).
 
*Verify the satisfaction of users (to avoid unwillingness to pay).
  
| style="width:78px;height:287px;" |  
+
| style="width:78px; height:287px" |  
 
2, 5
 
2, 5
  
 
|-
 
|-
| style="width:121px;height:77px;" |  
+
| style="width:121px; height:77px" |  
 
Operators and end users’ safety
 
Operators and end users’ safety
  
| style="width:306px;height:77px;" |  
+
| style="width:306px; height:77px" |  
 
Risks of harm due to higher voltages and extensive wiring.
 
Risks of harm due to higher voltages and extensive wiring.
  
| style="width:268px;height:77px;" |  
+
| style="width:268px; height:77px" |  
 
*Provide appropriate training to operators and users.
 
*Provide appropriate training to operators and users.
 
*Design and installation according to international standards.
 
*Design and installation according to international standards.
  
| style="width:78px;height:77px;" |  
+
| style="width:78px; height:77px" |  
 
2
 
2
  
 
|-
 
|-
| style="width:121px;height:59px;" |  
+
| style="width:121px; height:59px" |  
 
Theft and vandalism
 
Theft and vandalism
  
| style="width:306px;height:59px;" |  
+
| style="width:306px; height:59px" |  
 
Components or other valuable materials for which there is a secondary market, are in danger of being stolen
 
Components or other valuable materials for which there is a secondary market, are in danger of being stolen
  
| style="width:268px;height:59px;" |  
+
| style="width:268px; height:59px" |  
 
*Secure perimeter.
 
*Secure perimeter.
 
*Develop sense of ownership within the local community.
 
*Develop sense of ownership within the local community.
  
| style="width:78px;height:59px;" |  
+
| style="width:78px; height:59px" |  
 
5
 
5
  
 
|-
 
|-
| rowspan="3" style="width:119px;height:52px;" |  
+
| rowspan="3" style="width:119px; height:52px" |  
 
Environment
 
Environment
  
| style="width:121px;height:52px;" |  
+
| style="width:121px; height:52px" |  
 
Environmental
 
Environmental
  
| style="width:306px;height:52px;" |  
+
| style="width:306px; height:52px" |  
 
Harm to the environment caused by operating the technology may affect planning & permitting.
 
Harm to the environment caused by operating the technology may affect planning & permitting.
  
| style="width:268px;height:52px;" |  
+
| style="width:268px; height:52px" |  
 
*Environmental Impact Assessment (EIA).
 
*Environmental Impact Assessment (EIA).
  
| style="width:78px;height:52px;" |  
+
| style="width:78px; height:52px" |  
 
 
 
 
  
 
|-
 
|-
| style="width:121px;height:87px;" |  
+
| style="width:121px; height:87px" |  
 
Weather-related /availability
 
Weather-related /availability
  
| style="width:306px;height:87px;" |  
+
| style="width:306px; height:87px" |  
 
Risk of fall in volume of electricity produced owing to lack of wind, sunshine, water flow/low rainfall, biomass availability.
 
Risk of fall in volume of electricity produced owing to lack of wind, sunshine, water flow/low rainfall, biomass availability.
  
 
 
 
 
  
| style="width:268px;height:87px;" |  
+
| style="width:268px; height:87px" |  
 
*If possible obtain long term data to select site.
 
*If possible obtain long term data to select site.
 
*Establish close relationship to local biomass supply by creating dependency: supplying the supplier (fertilizer, bargain electricity price)
 
*Establish close relationship to local biomass supply by creating dependency: supplying the supplier (fertilizer, bargain electricity price)
  
| style="width:78px;height:87px;" |  
+
| style="width:78px; height:87px" |  
 
5
 
5
  
 
|-
 
|-
| style="width:121px;height:57px;" |  
+
| style="width:121px; height:57px" |  
 
Force majeure
 
Force majeure
  
| style="width:306px;height:57px;" |  
+
| style="width:306px; height:57px" |  
 
Environmental disaster like severe storms, typhoons, sandstorms, volcanic eruption, earth quakes, mud slides, etc.
 
Environmental disaster like severe storms, typhoons, sandstorms, volcanic eruption, earth quakes, mud slides, etc.
  
| style="width:268px;height:57px;" |  
+
| style="width:268px; height:57px" |  
 
 
 
 
  
| style="width:78px;height:57px;" |  
+
| style="width:78px; height:57px" |  
 
5
 
5
  
 
|}
 
|}
 
<div></div>
 
<div></div>
 
+
<br/>
  
 
= References =
 
= References =
Line 514: Line 512:
 
</div>&lt;/div&gt;
 
</div>&lt;/div&gt;
  
 +
[[Category:Energy_Access]]
 +
[[Category:Lighting]]
 
[[Category:Risks]]
 
[[Category:Risks]]
[[Category:Lighting]]
 
[[Category:Energy_Access]]
 

Revision as of 07:20, 7 February 2017

Overview

Mini-grids and stand-alone systems play an important role when facilitating energy access in developing countries with improved technology. However there are potential risks to be considered in spite of the financing scheme applied and the type of technology. Painuly (2001)[1] in Hazelton et al. (2015)[2] states that unawareness and misinterpretation of risks (and benefits) are a major barrier for technology adoption.

The following table summarizes some of the risks identified based on existing projects and lessons learned from the literature review. Though this article is open for further contributions.

Some of the risks listed may be context specific, some are looked at from the ‘owner’ point of view, while others from the investor perspective. Moreover, the listed risks may correspond to more than one of the categories, though the information has been arranged this order within six categories to facilitate an overview.

 

Category

Risk

Risk description

Risk mitigation/ control mechanism

Reference

Technical

Load uncertainty

Poor estimation of load size, growth and schedule, could derive in under- or oversized systems. This can lead to increased investment/running cost, lower efficiency, and unreliable supply.

Overestimated efficiency

  • Recommended to perform in-field power ratings.
  • Use of design tools to estimate load.
  • Consider modular designs.
  • If possible, the design should include future expansion.
  • Limit the initial generation capacity and increase it gradually as demand grows.
  • Manage consumption according to the available capacity: load control or daily energy allowance.
  • Include energy efficiency measures.

2, 5

Power quality

Integrating PV and batteries, in retrofits on existing systems, may affect the stability of the grid due to incompatibilities and an ineffective control system.

  • Appropriate control strategy.
  • Appropriate design simulation prior implementation.
  • Consider distributed generation as it is less variable than centralized systems.

2

Equipment failure/ Downtime

Premature failure of hardware can not only cause service interruption but damage the entire system.

In addition, despite existing warranties, these can be hard to fulfil due to the remoteness where they system is located.

  • Appropriate routine maintenance.
  • Equipment should meet quality standards and be appropriate for the environmental conditions.

2

Hardware compatibility issues

Proprietary protocols could provoke incompatibility between components.

  • Use open based protocols.
  • Choose single provider.

2

Limitation for continuous supply/storage

Batteries have a limited life-span and are vulnerable to be misused, this impacts on the energy balance and supply affecting the operation of generators (specific for hybrid systems).

  • Proper training.
  • Manage operators and user’s expectations.
  • Consider product selection.
  • Planning/budgeting for spare parts, replacement.

2

Familiarity with the technology

Difficulty to operate and maintain, complexity of maintenance, limited knowledge on maintenance issues.

  • Continuous capacity building on technical aspects starting before implementation.
  • Trained technicians should receive payment for their job as incentive.

2

Future connectivity

Interim solutions, such as mini-grids, would ideally be connected to the main grid if it becomes available, otherwise it becomes obsolete.

  • Design should consider the same standard as the central network

2

Supply and installation issues

Incorrect installation and operation of hardware, combined with the remoteness where the technology is installed.

  • Incorporate capacity development in the plan: proper training for local installers and operators.
  • Hire reliable contractors for installation and certain elements of the operation.
  • Rely on construction consultants to oversee project implementation and ensure that contractors comply with the expectations of the developers.

2, 5

Building and testing

Property damage or third-party liability arising from mishaps during building or testing.

 

4

Institutional/ Organizational

Stakeholder management

Multiple parties involved whose activities, incentives, will not align between parties, causing negative outcomes.

  • Parties need to aware of their obligations and maintain a collaborative approach.
  • Agreements to protect every actor equally.

2

Operational

Administration errors or fraud.

  • Simple standardisation like appropriate accounting and regular auditing.
  • Establishment of internal rules and the standardisation of processes.
  • Regular training for contentious improvement, operational efficiency and service delivery.

5

Geographical isolation

Difficulties to acquire spare parts and/or repair due to long distances, transportation challenges and lack of skilled personnel in the area.

  • Ensure local capacity building.
  • Routine and preventive maintenance should be properly scheduled.
  • Timely identification of the closest spare parts provider/s.

2

Geo-political

Change in public policy

Increase in taxes levied on technology or import and export duties.

Subsidies affecting operation and/or profitability.

  • Political risks with high probability of occurrence may be hard to mitigate.

5

Political instability

Unrest, social conflicts, war.

 

 

Delays in approvals

Arbitrary actions of public authorities can affect the development of any energy access project.

  • Continuous involvement and consultation of local authorities during the development and implementation.

 

Arrival of the national grid

Investment’s payback and further cash flows could be in danger or threatened.

  • Continuous involvement and consultation of local authorities during the development and implementation.

 

Finance and Economics

Commitment, competence and credit worthiness of investors

Large level of investment/ long tenor of return, may require additional equity later after project has begun.

  • Credit assessment.
  • Verify the competence and/or knowledge regarding energy projects.

3

Inadequate business models

Effective business models are key for deployment and may need to be continuously revised to scale up.

  • Information about similar experiences.
  • Seek for support to ensure capacity building and/or access to finance.
  • Chose models that are practical and appropriate for the local context.

2

Diesel and cost supply

Although the use is reduced (hybrid systems), prices and availability impact the operation of the system.

  • Maximise other sources of generation.
  • Develop time-of-use-tariffs to discourage use when diesel would be required.

2

Exchange rates/ Inflation

Foreign exchange rate changes due to devaluation, convertibility or transfer restrictions.

  • Borrow in local currency.
  • Cross-currency swaps (if possible).
  • Use hedging instruments (though this may be complex and expensive).
  • Involve local investors.

3

Credit

Risk of default of counterparties or default on specific payments.

  • Good credit risk management.

3

Liquidity

 

 

 

Social

Public resistance

Resistance of interest groups because statics, water supply, smell (biogas), etc.

  • Include the whole community throughout the development and operation of the project.
  • Partnerships with local organizations can help to facilitate the relationship between developers and customers.
  • Implementation of capacity building measures and dedicated promotion of productive use of energy could support establishing local support.
  • Project should be well embedded in the socio-cultural context where is going to be built/ installed.
  • Ensure public opinion, transparency and involvement of local capacities

5

Community/social integration

Over-consumption from one or few users can cause a black-out. Theft or users connecting loads beyond their quota.

  • Community engagement from the outset and follow up.
  • Avoid top-down approach.
  • Respect local organisational structures.
  • Manage and follow up user expectations: users should be aware of the potential limitations.
  • Enforce load control measures.
  • Tariff system to prevent overconsumption.
  • Proper education to discourage illegal connections: educate about the consequences or impact on the operation and performance of the system.

2

Appropriate pricing and payments

Rural customers usually have low incomes which is challenging when setting a price that is both sufficiently high to give returns and low enough to make it affordable.

  • Tariffs should be flexible and revisable
  • Educate about consequences of non-payment such as supply cut-off or penalties.
  • Uncomplicated bill setting and non-bureaucratic procedures for connection and consumption payment.
  • Smart metering systems equipped with tamper protection or in combination with incentives for electricity use.
  • Take into account possible inability to pay: income fluctuations and payment culture.
  • Verify the satisfaction of users (to avoid unwillingness to pay).

2, 5

Operators and end users’ safety

Risks of harm due to higher voltages and extensive wiring.

  • Provide appropriate training to operators and users.
  • Design and installation according to international standards.

2

Theft and vandalism

Components or other valuable materials for which there is a secondary market, are in danger of being stolen

  • Secure perimeter.
  • Develop sense of ownership within the local community.

5

Environment

Environmental

Harm to the environment caused by operating the technology may affect planning & permitting.

  • Environmental Impact Assessment (EIA).

 

Weather-related /availability

Risk of fall in volume of electricity produced owing to lack of wind, sunshine, water flow/low rainfall, biomass availability.

 

  • If possible obtain long term data to select site.
  • Establish close relationship to local biomass supply by creating dependency: supplying the supplier (fertilizer, bargain electricity price)

5

Force majeure

Environmental disaster like severe storms, typhoons, sandstorms, volcanic eruption, earth quakes, mud slides, etc.

 

5


References


[1] Painuly, Jyoti Prasad, ‘Barriers to renewable energy penetration; a framework for analysis’, Renewable Energy 24, 2001

[2] Hazelton, James; Bruce, Anna; MacGill Iain, ‘A review of the potential benefits and risks of photovoltaic hybrid mini-grid systems’, Renewable Energy 67, 2013. https://www.researchgate.net/publication/259298363_A_review_of_the_potential_benefits_and_risks_of_photovoltaic_hybrid_mini-grid_systems 

[3] Green Rhino Energy, ‘Project Risk Matrix’, 2013, http://www.greenrhinoenergy.com/finance/renewable/risks.php

[4] The Economist, Managing the risk in renewable energy, 2011 https://www.altran.de/fileadmin/medias/DE.altran.de/documents/Fachartikel/Managing-The-Risk-In-Renewable-Energy.pdf

[5] Manetsgruber, David; Wagemann, Bernanrd; Kondev, Bozhil; Dziergwa, Katrin. Risk Management for Mini-Grids: A new approach to guide mini-grid development. 2015. https://www.ruralelec.org/sites/default/files/risk_management_for_mini-grids_2015_final_web_0.pdf


 