= Overview =
 
= Overview =
  
Please add information here...
+
-> Grid Extension / Densification Approaches:[[Community Rural Electrification Programme (CREP) Nepal|Community Rural Electrification Programme (CREP), Nepal]]
  
 
<br/>
 
<br/>
  
= Grid Extension / Densification Approaches<br/> =
+
= Type of Grid Activities<br/> =
 
 
*[[Community Rural Electrification Programme (CREP) Nepal|Community Rural Electrification Programme (CREP), Nepal]]
 
  
<br/>
+
== Grid Extension ==
  
= Type of Grid Activities<br/> =
+
{| align="left" cellspacing="1" cellpadding="1" border="0" style="width: 100%" class="FCK__ShowTableBorders"
 
 
{| align="left" cellspacing="1" cellpadding="1" border="0" class="FCK__ShowTableBorders" style="width: 100%"
 
 
|-
 
|-
 
| [[File:Picture1.jpg|frame|center|150px|Grid extension: Benin, Ghana, Nicaragua, Nepal|alt=Picture1.jpg]]
 
| [[File:Picture1.jpg|frame|center|150px|Grid extension: Benin, Ghana, Nicaragua, Nepal|alt=Picture1.jpg]]
|-
 
| [[File:Picture2.jpg|frame|center|150px|Grid densification (with and without transformation): Bolivia, Peru, Mozambique, Uganda|alt=Picture2.jpg]]
 
|-
 
| [[File:Picture3.jpg|frame|center|150px|Grid densification (with and without transformation) - 2: Bolivia, Peru, Mozambique, Uganda|alt=Picture3.jpg]]
 
 
|}
 
|}
  
Line 33: Line 25:
 
<br/>
 
<br/>
  
<br/>
+
== Grid Densification ==
  
<br/>
+
{| cellspacing="1" cellpadding="5" border="0" style="width: 100%"
 
+
|-
<br/>
+
| [[File:Picture2.jpg|frame|center|150px|Grid densification (with and without transformation): Bolivia, Peru, Mozambique, Uganda|alt=Picture2.jpg]][[File:Picture3.jpg|frame|center|150px|Grid densification (with and without transformation) - 2: Bolivia, Peru, Mozambique, Uganda|alt=Picture3.jpg]]
 
+
|}
<br/>
 
 
 
<br/>
 
 
 
<br/>
 
 
 
<br/>
 
 
 
<br/>
 
 
 
<br/>
 
 
 
<br/>
 
 
 
<br/>
 
 
 
<br/>
 
  
<br/>
 
 
<br/>
 
  
<br/>
 
  
 
= Costs<br/> =
 
= Costs<br/> =
Line 299: Line 270:
 
*<span style="font-family: arial;  color: black">In rural areas several households are connected to a meter to save the connection fee which can be legal or illegal according to national and local regulation. In some of these case voltage drop can be a severe problem</span>
 
*<span style="font-family: arial;  color: black">In rural areas several households are connected to a meter to save the connection fee which can be legal or illegal according to national and local regulation. In some of these case voltage drop can be a severe problem</span>
  
<br/>
+
-> [https://energypedia.info/wiki/Category:Lessons_Learned Lessons Learned Category on energypedia]<br/>
 +
 
 +
 
  
 
= Further Information =
 
= Further Information =
Line 311: Line 284:
 
<references />
 
<references />
  
 +
[[Category:Grid]]
 +
[[Category:Benin]]
 +
[[Category:Ghana]]
 +
[[Category:Nicaragua]]
 +
[[Category:Bolivia]]
 +
[[Category:Peru]]
 +
[[Category:Mozambique]]
 +
[[Category:Financing_and_Funding]]
 
[[Category:Lessons_Learned]]
 
[[Category:Lessons_Learned]]
[[Category:Financing_and_Funding]]
 
[[Category:Mozambique]]
 
[[Category:Peru]]
 
[[Category:Bolivia]]
 
[[Category:Nicaragua]]
 
[[Category:Ghana]]
 
[[Category:Benin]]
 
[[Category:Grid]]
 

Revision as of 15:55, 12 August 2014

Overview

-> Grid Extension / Densification Approaches:Community Rural Electrification Programme (CREP), Nepal


Type of Grid Activities

Grid Extension

Picture1.jpg
Grid extension: Benin, Ghana, Nicaragua, Nepal






Grid Densification

Picture2.jpg
Grid densification (with and without transformation): Bolivia, Peru, Mozambique, Uganda
Picture3.jpg
Grid densification (with and without transformation) - 2: Bolivia, Peru, Mozambique, Uganda


Costs


Benin

Ghana

Nicaragua

Bolivien

Peru

Mozambique

Costs/

Connection (€)

2000

5540

220-588

62

90

134

Tariff

Social tariff

Social tariff

Social tariff

Social tariff

Social tariff

Social tariff

Security of energy supply

Medium

Medium

High

High

High

high


Financial Support


Benin

Ghana

Nicaragua

Bolivien

Peru

Mozambique

EnDev subsidy

70%

99%

100%

20%

22%

100%

Government

30%

0%

0%

0%

0%

0%

Utility

0%

0%

0%

0-80%

0%

0%

Customer

0%

1%

0%

0-80%

78%

0%


Additional Support

  • Procurement support
  • Developing local standards for grid connection
  • Facilitating group applications for grid connections
  • Training of local electricians for in-house wiring
  • Training of consumers in energy use and efficiency
  • Ex-ante savings for connection fees
  • Introduction of installment payments of the connection fee linked to the electricity bills


Lessons Learned

  • Some utilities are not interested in grid densification
  • Poor households are often excluded in extension projects
  • Some utilities have great difficulties to organize efficient procurement processes causing severe delays
  • Free rider effect difficult to avoid (efficient selection process or accept the effect)
  • Detailed monitoring is considered a burden and not always implemented
  • In several countries power generation capacity cannot keep up withgrid extension
  • In rural areas several households are connected to a meter to save the connection fee which can be legal or illegal according to national and local regulation. In some of these case voltage drop can be a severe problem

-> Lessons Learned Category on energypedia