− | = | + | = Overview<br/> = |
− | The following table gives an overview of all the steps required to build a biogas unit | + | The following table gives an overview of all the steps required to build a biogas unit. |
− | {| cellpadding="5" border="1" | + | The order follows a usual time-line. There are steps which can be combined. However, to skip any of them might lead to future problems. |
+ | |||
+ | <br/> | ||
+ | |||
+ | = Step-by-Step Planning Checklist for Biogas Plants<br/> = | ||
+ | |||
+ | {| cellpadding="5" border="1" style="width: 100%" | ||
|- | |- | ||
− | ! | + | ! style="width: 50%; background-color: rgb(204, 204, 204)" | Customer<br/> |
− | ! | + | ! style="width: 50%; background-color: rgb(204, 204, 204)" | Contractor |
|- | |- | ||
− | | | + | | |
− | | organizes advertisement, awareness creation | + | | organizes advertisement, awareness creation |
|- | |- | ||
− | | hears about biogas, develops interest, get's in contact with the contractor | + | | hears about biogas, develops interest, get's in contact with the contractor<br/> |
− | | | + | | |
|- | |- | ||
− | | | + | | |
− | | gives first overview over costs | + | | gives first overview over costs |
|- | |- | ||
− | | | + | | |
− | | writes letter to the customer | + | | writes letter to the customer |
|- | |- | ||
| writes a request | | writes a request | ||
− | | | + | | |
|- | |- | ||
− | | | + | | |
| starts file | | starts file | ||
|- | |- | ||
− | | | + | | |
− | | makes a side visit, including: discussion and calculations | + | | makes a side visit, including: discussion and calculations |
|- | |- | ||
− | | | + | | |
− | | makes a quantity survey, | + | | makes a quantity survey, |
|- | |- | ||
− | | | + | | |
| does object planning | | does object planning | ||
|- | |- | ||
− | | | + | | |
− | | writes invoice <br> explains warranty performances | + | | writes invoice<br/>explains warranty performances |
|- | |- | ||
| makes first payment (50%) | | makes first payment (50%) | ||
− | | organizes a customer and constructor sign contract | + | | organizes a customer and constructor sign contract |
|- | |- | ||
− | | | + | | |
− | | hands over a list of building material to be delivered by the customer | + | | hands over a list of building material to be delivered by the customer |
|- | |- | ||
− | | prepares the material he agreed to deliver | + | | prepares the material he agreed to deliver |
− | | | + | | |
|- | |- | ||
− | | | + | | |
| organizes material delivery, reference line, main construction work, finishing, landscaping, slurry component, piping. | | organizes material delivery, reference line, main construction work, finishing, landscaping, slurry component, piping. | ||
|- | |- | ||
− | | starts to fill the plant <br> second payment (50%) | + | | starts to fill the plant<br/>second payment (50%) |
− | | | + | | |
|- | |- | ||
− | | | + | | |
− | | finishes piping installation of gas consumption accessories | + | | finishes piping installation of gas consumption accessories |
|- | |- | ||
| discusses handing over | | discusses handing over | ||
− | | | + | | |
|- | |- | ||
− | | makes an agreement on co-operation regarding fertiliser utilisation | + | | makes an agreement on co-operation regarding fertiliser utilisation |
− | | | + | | |
|- | |- | ||
− | | | + | | |
− | | makes a follow up on fertiliser utilisation | + | | makes a follow up on fertiliser utilisation |
|- | |- | ||
− | | | + | | |
− | | does customer monitoring | + | | does customer monitoring |
|- | |- | ||
− | | | + | | |
− | | conducts technical and agricultural service visits | + | | conducts technical and agricultural service visits |
|} | |} | ||
+ | <br/> | ||
+ | |||
+ | = Further Informaiton<br/> = | ||
+ | |||
+ | *[[Portal:Biogas|Biogas Portal on energypedia]] | ||
+ | *[[Checklist_for_the_Construction_of_a_Biogas_Plant|Checklist for the Construction of a Biogas Plant]] | ||
+ | |||
+ | <br/> | ||
+ | |||
+ | = References<br/> = | ||
+ | |||
+ | <references /> | ||
− | [[Category: Biogas]] | + | [[Category:Biogas]] |
Latest revision as of 12:17, 16 October 2014
Overview
The following table gives an overview of all the steps required to build a biogas unit.
The order follows a usual time-line. There are steps which can be combined. However, to skip any of them might lead to future problems.
Step-by-Step Planning Checklist for Biogas Plants
Customer |
Contractor |
---|---|
organizes advertisement, awareness creation | |
hears about biogas, develops interest, get's in contact with the contractor |
|
gives first overview over costs | |
writes letter to the customer | |
writes a request | |
starts file | |
makes a side visit, including: discussion and calculations | |
makes a quantity survey, | |
does object planning | |
writes invoice explains warranty performances | |
makes first payment (50%) | organizes a customer and constructor sign contract |
hands over a list of building material to be delivered by the customer | |
prepares the material he agreed to deliver | |
organizes material delivery, reference line, main construction work, finishing, landscaping, slurry component, piping. | |
starts to fill the plant second payment (50%) |
|
finishes piping installation of gas consumption accessories | |
discusses handing over | |
makes an agreement on co-operation regarding fertiliser utilisation | |
makes a follow up on fertiliser utilisation | |
does customer monitoring | |
conducts technical and agricultural service visits |
Further Informaiton