= Checklist for building a biogas plant  =
+
= Checklist<br/> =
  
'''Finishing the planning''', i.e. [[Siting of the Biogas Unit|site evaluation]], [[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield, [[Sizing of the Biogas Plant|plant sizing]], selection of plant [[Types of Biogas Digesters and Plants#Biogas_Plant_Types_and_Design|design]], how and where to use the biogas, etc., in accordance with the [[Planning Guide for Biogas Plants|planning guide]]
+
'''Finishing the planning'''
  
'''Stipulate the plant's location and elaborate a site plan''', including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry
+
i.e. [[Siting of the Biogas Unit|site evaluation]], [[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield, [[Sizing of the Biogas Plant|plant sizing]], selection of plant [[Types of Biogas Digesters and Plants#Biogas_Plant_Types_and_Design|design]], how and where to use the biogas, etc., in accordance with the [[Planning Guide for Biogas Plants|planning guide]]
  
'''Draft a technical drawing showing all plant components''', i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage
 
  
'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':
 
  
*bricks / stones / blocks for walls and foundation  
+
'''Stipulate the plant's location and elaborate a site plan'''
*sand, gravel  
+
 
*inlet / outlet pipes  
+
including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry
*metal parts (sheet metal, angle irons, etc.)  
+
 
*gas pipes and fittings  
+
 
*paint and sealants  
+
 
*gas appliances  
+
'''Draft a technical drawing showing all plant components'''
*tools  
+
 
*mason and helper  
+
i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage
*unskilled labor  
+
 
 +
 
 +
 
 +
'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':
 +
 
 +
*bricks / stones / blocks for walls and foundation
 +
*sand, gravel
 +
*inlet / outlet pipes
 +
*metal parts (sheet metal, angle irons, etc.)
 +
*gas pipes and fittings
 +
*paint and sealants
 +
*gas appliances
 +
*tools
 +
*mason and helper
 +
*unskilled labor
 
*workshop for metal (gas-holder) and pipe installation
 
*workshop for metal (gas-holder) and pipe installation
  
'''Material / personnel assignment planning''', i.e. procedural planning and execution of:
 
  
*excavation  
+
 
*foundation slab  
+
'''Material / personnel assignment planning''', i.e. procedural planning and execution of:
*digester masonry  
+
 
*gasholder  
+
*excavation
*rendering and sealing the masonry  
+
*foundation slab
*mixing pit - slurry storage pit  
+
*digester masonry
*drying out the plant  
+
*gasholder
*installing the gas pipe  
+
*rendering and sealing the masonry
 +
*mixing pit - slurry storage pit
 +
*drying out the plant
 +
*installing the gas pipe
 
*acceptance inspection
 
*acceptance inspection
  
'''Regular building supervision''' '''Commissioning'''
 
  
*functional inspection of the biogas plant and its components  
+
 
 +
'''Regular building supervision''' '''Commissioning'''
 +
 
 +
*functional inspection of the biogas plant and its components
 
*starting the plant
 
*starting the plant
  
'''Filling the plant'''  
+
 
 +
 
 +
'''Filling the plant'''
 +
 
  
 
'''Training the user'''
 
'''Training the user'''
  
[[Construction of a Biogas Plant|Back to "construction"]]  
+
 
</div>  
+
[[Construction of a Biogas Plant|-> Back to "Construction"]]
 +
</div>
 +
 
 
[[Category:Biogas]]
 
[[Category:Biogas]]

Revision as of 15:43, 30 August 2012

Checklist

Finishing the planning

i.e. site evaluation, determination of energy demand and biomass supply / biogas yield, plant sizing, selection of plant design, how and where to use the biogas, etc., in accordance with the planning guide


Stipulate the plant's location and elaborate a site plan

including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry


Draft a technical drawing showing all plant components

i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage


Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant:

  • bricks / stones / blocks for walls and foundation
  • sand, gravel
  • inlet / outlet pipes
  • metal parts (sheet metal, angle irons, etc.)
  • gas pipes and fittings
  • paint and sealants
  • gas appliances
  • tools
  • mason and helper
  • unskilled labor
  • workshop for metal (gas-holder) and pipe installation


Material / personnel assignment planning, i.e. procedural planning and execution of:

  • excavation
  • foundation slab
  • digester masonry
  • gasholder
  • rendering and sealing the masonry
  • mixing pit - slurry storage pit
  • drying out the plant
  • installing the gas pipe
  • acceptance inspection


Regular building supervision Commissioning

  • functional inspection of the biogas plant and its components
  • starting the plant


Filling the plant


Training the user


-> Back to "Construction"