EIBs lending for renewable energies grew almost fivefold between 2007 and 2010. In 2008 lendings account for 2.2 billion €, in 2009 lendings were 4.2 billion € and in 2010 lending reached 6.2 billion €. However, the proportion of lendings for small and large hydropower projects is unclear. | EIBs lending for renewable energies grew almost fivefold between 2007 and 2010. In 2008 lendings account for 2.2 billion €, in 2009 lendings were 4.2 billion € and in 2010 lending reached 6.2 billion €. However, the proportion of lendings for small and large hydropower projects is unclear. | ||
− | + | Some hydropower projects which are/have been financed are listed below: | |
− | | + | *2005 Gilgel Gibe II, a medium-scale Hydro Power plant with a capacity of 428 MW and 385 km of overhead transmission lines and substations was financed with 50 million €. The project is cascaded with the Gilgel Gibe I project, commissioned and co-funded by the EIB, too |
+ | *in November 2005 The EIB has signed a loan agreement of EUR 45 million with the Laos Government to help finance the "Nam Theun 2" (NT2) hydroelectric power project in Laos | ||
+ | *2006 the EIB financed the construction of the Felou HPP a 60MW Run of River project in Mali which forms part of the Organisation de Mise en valeur du Fleuve Sénégal (OMVS’s) power supply strategy for Mali, Mauritania and Senegal with 33 million € | ||
+ | *2009 the EIB provided a loan up to 44 million € for the design, construction and operation of 10 small scale hydropowr plants with a total capacity of 62MW, located in the Yichang prefecture (Hubei province), China | ||
+ | *2009, the EIB has granted Iberdrola SA a 300 million € loan to finance the expansion of three of the company’s hydropower plants in Galicia and Valencia | ||
+ | *2011 the EIB provided a loan of 70 million € for the construction of the 80MW Budharhals hydroplant on the Kaldakvisl River in southern Iceland | ||
+ | *2011a 300 million € loan for the upgrade of the Alqueva and Venda Nova pump storage projects in Portugal | ||
+ | *2011 EIB is lending €20 million to the Republic of Georgia to finance the completion of rehabilitation of the 1,250 MW Enguri plant and Vardnili hydro cascade | ||
+ | *the EIB confirms commitment to the 147 MW Ruzizi III HPP on the Ruzizi River, a natural border between Rwanda and the Dem. Republic of Congo | ||
+ | *the EIB also confirms commitment to the construction and operation of 305 MW hydropower plant with associated dam and reservoir, located on the Reventazon river in Costa Rica. The project is funfed with up to 200 million €. | ||
+ | *a project currently under appraisal and partly fianced with 30 million € by the EIB is the Lom Pangar 30MW HPP on the Sanaga river and a 110 km transmission line in Cameroon | ||
− | Source: | + | Source: |
− | http://www.renewableenergyworld.com/rea/news/article/2011/11/banks-provide-critical-support-for-hydro-project-development?page=2 | + | http://www.renewableenergyworld.com/rea/news/article/2011/11/banks-provide-critical-support-for-hydro-project-development?page=2 |
− | REN 21 Gl | + | REN 21 Gl<span id="fck_dom_range_temp_1332925161811_695" />obal Status report 2009 and 2010 |
== Inter-American Development Bank (IADB) == | == Inter-American Development Bank (IADB) == |
Revision as of 09:50, 28 March 2012
World Bank Group
The World Banks investments in hydropower projects reflects international trends and demands. In the 1990 hydropower projects were strongly criticised throughout the world since social domains and investments in environmental protection were neglected and human rights have been infringed. Therefore lendings in hydropower during the 1990s significantly decreased accompanied by a shift to projects with fewer environmental and social impacts.By the early 2000s, however, several policies repositioned the World
Bank Group in terms of infrastructure and risk, and established a renewed framework for hydropower.
Thus lending increased over the last five years. In the years from 2002 to 2004 avergae new lending per year amounted to less than $250 million; between 2005 and 2007 avergae new lending increased to $500 million per year. In 2008, new lending exceeded
$1 billion, with an increase in larger, standalone projects (see Figure)
Since 2003 67 hydropower projects have been approved amounting to 3.7 billion USD in WBG contributions (US$3.2 billion for hydropower components) to support almost 9700 MW in project investments.
The majority of the projects have been approved in Africa (Senegal, Democratic Republic of Congo, Sierra Leone, and Uganda) and Asia (People’s Democratic Republic of Laos, India), as well as several rehabilitation projects in Eastern Europe (Ukraine, Macedonia, and Georgia).
Over the time the WBG has adapted product lines and financial instruments. Over the period 1992–2002, the International Bank for Reconstruction and Development (IBRD) and the International Development Association (IDA) accounted for 99% of the lending portfolio, and International Financial Corporation (IFC) the remaining 1%. During 2003–08, IBRD/IDA’s lending decreased significantly,to 58%—mainly because of an absolute decrease in IBRD lending. At the same time, IFC increased support (to 20%), as did carbon finance (to 5%), and guarantees (to 17%), reflecting increased private sector involvement.
The WBG’s assistance extends beyond lending—to technical support, knowledge sharing, policy dialogue, economic and sector
work, and support during project preparation and implementation. In these roles, the WBG draws on a range of products and services which were developed after the fall of lending in the 1990s. These products in form of operational directives and safeguards, coupled with the ongoing development of tools such as Strategic Environmental Assessment and payments for environmental services offer the Bank opportunities to add imputs to hydropower efforts.
Source: Water Working Notes No 21, June 2009. Direction in Hydropower: Scaling Up for Development. Water Sector Board of the Sustainable Development Network of the World Bank Group
Reconstruction Loan Corporation (German Kreditanstalt für Wiederaufbau KfW)
Detailed infomation about the total amount of KfW lendings in hydropower projects in the last years could not be found in the literature. However, the Gloabal Status Report of Renewables 2011 (REN21) stated that the KfW is one of the three leading development banks, in terms of financing of renewables projects in 2010 (with 1.5 billion USD).
Infomation about small and large hydropower projects which are financed by the KfW can be found at the country portal at the KfW website: http://www.kfw-entwicklungsbank.de/ebank/DE_Home/Laender_und_Programme/index.jsp
Countries where small and large hydropower projects have been / are supported are e.g.:
- Albania (small hydropower plants)
- Agypt (rehabilitation of the generators of the Assuan High Dam)
- India (small hydropower plants)
- Macedonia (rehabilitation and modernisation of six hydropower plants)
- Mongolia (rehabilitation of Bogdyn HPP in 2007)
- Montenegro with 16 million € (rehabilitation of existing hydropower plants)
- Morocco with 87 million € (Tanafnit and El Borj Run of River HPP and modernisation of 20 old HPP)
- Pakistan with 97 million € over 6 years (construction of the HPP Keyal Khwar 122 MW)
- Serbia with 30 million € (rehabilitation of Bajina Basta HPP)
- Turkey (support of the construction of five hydropower plants)
- Uganda with 15 million USD for Bujagali HPP 250 MW (after support of small hydropower plants)
Source: Renewables 2011 Global Status Report, REN21 (Paris), 115 pp. (Lead author Janet Sawin)
Regional Development Banks
European Investment Bank (EIB)
EIBs lending for renewable energies grew almost fivefold between 2007 and 2010. In 2008 lendings account for 2.2 billion €, in 2009 lendings were 4.2 billion € and in 2010 lending reached 6.2 billion €. However, the proportion of lendings for small and large hydropower projects is unclear.
Some hydropower projects which are/have been financed are listed below:
- 2005 Gilgel Gibe II, a medium-scale Hydro Power plant with a capacity of 428 MW and 385 km of overhead transmission lines and substations was financed with 50 million €. The project is cascaded with the Gilgel Gibe I project, commissioned and co-funded by the EIB, too
- in November 2005 The EIB has signed a loan agreement of EUR 45 million with the Laos Government to help finance the "Nam Theun 2" (NT2) hydroelectric power project in Laos
- 2006 the EIB financed the construction of the Felou HPP a 60MW Run of River project in Mali which forms part of the Organisation de Mise en valeur du Fleuve Sénégal (OMVS’s) power supply strategy for Mali, Mauritania and Senegal with 33 million €
- 2009 the EIB provided a loan up to 44 million € for the design, construction and operation of 10 small scale hydropowr plants with a total capacity of 62MW, located in the Yichang prefecture (Hubei province), China
- 2009, the EIB has granted Iberdrola SA a 300 million € loan to finance the expansion of three of the company’s hydropower plants in Galicia and Valencia
- 2011 the EIB provided a loan of 70 million € for the construction of the 80MW Budharhals hydroplant on the Kaldakvisl River in southern Iceland
- 2011a 300 million € loan for the upgrade of the Alqueva and Venda Nova pump storage projects in Portugal
- 2011 EIB is lending €20 million to the Republic of Georgia to finance the completion of rehabilitation of the 1,250 MW Enguri plant and Vardnili hydro cascade
- the EIB confirms commitment to the 147 MW Ruzizi III HPP on the Ruzizi River, a natural border between Rwanda and the Dem. Republic of Congo
- the EIB also confirms commitment to the construction and operation of 305 MW hydropower plant with associated dam and reservoir, located on the Reventazon river in Costa Rica. The project is funfed with up to 200 million €.
- a project currently under appraisal and partly fianced with 30 million € by the EIB is the Lom Pangar 30MW HPP on the Sanaga river and a 110 km transmission line in Cameroon
Source:
REN 21 Gl<span id="fck_dom_range_temp_1332925161811_695" />obal Status report 2009 and 2010