= Checklist for building a biogas plant  =
 
= Checklist for building a biogas plant  =
  
#'''Finishing the planning''', i.e. [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/siting.html site evaluation], [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/detincdem.html determination of energy demand and biomass supply] / biogas yield, [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/sizing.html plant sizing], selection of plant [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/design/digestypes2.html#APPRDES design], how and where to use the biogas, etc., in accordance with the [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/planguide.html planning guide]<br>
+
'''Finishing the planning''', i.e. [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/siting.html site evaluation], [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/detincdem.html determination of energy demand and biomass supply] / biogas yield, [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/sizing.html plant sizing], selection of plant [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/design/digestypes2.html#APPRDES design], how and where to use the biogas, etc., in accordance with the [http://intranet.gtz.de/umwelt/cd-rom44-2003/documents/af4454/Gate/biogas/appldev/planning/planguide.html planning guide]
'''Stipulate the plant's location and elaborate a site plan''', including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry  
+
 
'''Draft a technical drawing showing all plant components''', i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage<br>
+
'''Stipulate the plant's location and elaborate a site plan''', including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry
 +
 
 +
'''Draft a technical drawing showing all plant components''', i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage
 +
 
 
'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':  
 
'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':  
 +
 
*bricks / stones / blocks for walls and foundation  
 
*bricks / stones / blocks for walls and foundation  
 
*sand, gravel  
 
*sand, gravel  
Line 16: Line 20:
 
*mason and helper  
 
*mason and helper  
 
*unskilled labor  
 
*unskilled labor  
*workshop for metal (gas-holder) and pipe installation  
+
*workshop for metal (gas-holder) and pipe installation
 +
 
 
'''Material / personnel assignment planning''', i.e. procedural planning and execution of:  
 
'''Material / personnel assignment planning''', i.e. procedural planning and execution of:  
 +
 
*excavation  
 
*excavation  
 
*foundation slab  
 
*foundation slab  
Line 26: Line 32:
 
*drying out the plant  
 
*drying out the plant  
 
*installing the gas pipe  
 
*installing the gas pipe  
*acceptance inspection  
+
*acceptance inspection
'''Regular building supervision'''  
+
 
'''Commissioning'''  
+
'''Regular building supervision''' '''Commissioning'''  
 +
 
 
*functional inspection of the biogas plant and its components  
 
*functional inspection of the biogas plant and its components  
*starting the plant  
+
*starting the plant
'''Filling the plant'''
+
 
 +
'''Filling the plant
 +
 
 
'''Training the user'''
 
'''Training the user'''
 +
 +
</div>

Revision as of 15:46, 4 March 2009

Checklist for building a biogas plant

Finishing the planning, i.e. site evaluation, determination of energy demand and biomass supply / biogas yield, plant sizing, selection of plant design, how and where to use the biogas, etc., in accordance with the planning guide

Stipulate the plant's location and elaborate a site plan, including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry

Draft a technical drawing showing all plant components, i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage

Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant:

  • bricks / stones / blocks for walls and foundation
  • sand, gravel
  • inlet / outlet pipes
  • metal parts (sheet metal, angle irons, etc.)
  • gas pipes and fittings
  • paint and sealants
  • gas appliances
  • tools
  • mason and helper
  • unskilled labor
  • workshop for metal (gas-holder) and pipe installation

Material / personnel assignment planning, i.e. procedural planning and execution of:

  • excavation
  • foundation slab
  • digester masonry
  • gasholder
  • rendering and sealing the masonry
  • mixing pit - slurry storage pit
  • drying out the plant
  • installing the gas pipe
  • acceptance inspection

Regular building supervision Commissioning

  • functional inspection of the biogas plant and its components
  • starting the plant

Filling the plant

Training the user