General Information

Country: Ethiopia
City/Town: Oromiya
Coordinates (Powerhouse): The following coordinate was not recognized: Latitude= 9.558, Longitude= 37.3663..The following coordinate was not recognized: Latitude= 9.558, Longitude= 37.3663..
Year of Commission: 1974
Basin Name: Tana Lake
Stream Name:
Developer:
Operator: Ethiopian Electric and Power Company
Project Status:
Any other uses of the water source:
Contact:
Comment:
Link to Photos:

Technical Information

Power: (kW) 84,000
Energy (kWh/a): 532,000,000
Capacity Factor (%): 72
Penstock Diameter (mm):
Penstock Length (m):
Penstock Material (m³/s):
Maximum Flow of the Penstock (m³/s):
Minimum Flow of the Stream (m³/s):
Head (m):
Turbine Type: Pelton
Turbine Manufacturer:
Generator Type:
Generator Capacity (kW):
Generator Manufacturer:
Comment:

Mini/Island Grid Information

Mini Grid: No
Load Control Information:
Connection Type:
Public Lighting:
Length of Transmission Line (m):
Voltage (v):
Transmission Conductor (type) :
Diameter of Conductor (mm²):
Transformer Rating (kVA):
Link to Grid:
S.W.E.R:
Operational Period (Xdays/year):
Comment:

Dam Information

Dam Type:

Dam on river with reservoir
Dam Construction Material:
Dam Height [m]: 20
Length of Dam [m]: 340
Storage Volume of Reservoir (m³): 650,000,000
Flood Storage of Reservoir:
Channel Material:
Comment:

Economic Information

Cost (€): 32,797,514
Donor/Financier & Percentage:
Tariff Levels:
Connected Households:
Connection Cost (€):
Cost to be Covered by Households (%):
Comment:
Link to Cost Breakdown: