Knowledge fuels change - Support energypedia!
For over 10 years, energypedia has been connecting energy experts around the world — helping them share knowledge, learn from each other, and accelerate the global energy transition.
Today, we ask for your support to keep this platform free and accessible to all. Even a small contribution makes a big difference! If just 10–20% of our 60,000+ monthly visitors donated the equivalent of a cup of coffee — €5 — Energypedia would be fully funded for a whole year.
Is the knowledge you’ve gained through Energypedia this year worth €5 or more?
Your donation keeps the platform running, helps us create new knowledge products, and contributes directly to achieving SDG 7.


Donate now and support open access to energy expertise

Thank you for your support, your donation, big or small, truly matters!

Checklist for the Construction of a Biogas Plant

From energypedia
Revision as of 14:05, 9 July 2014 by ***** (***** | *****)

Overview

The checklist for the construction of a biogas plant is summarized below


  • Planning of the Biogas Plant

i.e. site evaluation, determination of energy demand and biomass supply / biogas yield, plant sizing, selection of plant design, how and where to use the biogas, etc., in accordance with the planning guide


  • Stipulate the plant's location and elaborate a site plan

including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry


  • Draft a technical drawing showing all plant components

i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage


  • Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant:

bricks / stones / blocks for walls and foundation

sand, gravel

inlet / outlet pipes

metal parts (sheet metal, angle irons, etc.)

gas pipes and fittings

paint and sealants

gas appliances

tools

mason and helper

unskilled labor

workshop for metal (gas-holder) and pipe installation


  • Material / personnel assignment planning, i.e. procedural planning and execution of:

excavation

foundation slab

digester masonry

gasholder

rendering and sealing the masonry

mixing pit - slurry storage pit

drying out the plant

installing the gas pipe

acceptance inspection


  • Regular building supervision Commissioning

functional inspection of the biogas plant and its components

starting the plant


  • Filling the plant


  • Training the user


-> Back to "Biogas Portal"