Difference between revisions of "Checklist for the Construction of a Biogas Plant"
From energypedia
***** (***** | *****) |
***** (***** | *****) |
||
Line 7: | Line 7: | ||
= Checklist for the Construction = | = Checklist for the Construction = | ||
− | + | ||
− | + | *<u>'''Planning of the Biogas Plant'''</u><ul style="margin-left: 40px;"> | |
− | <li>i.e. [[Siting of the Biogas Unit|site evaluation]], </li> | + | <li>i.e. [[Siting of the Biogas Unit|site evaluation]],</li> |
− | <li>[[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield, </li> | + | <li>[[Balancing Biogas Production and Energy Demand|determination of energy demand and biomass supply]] / biogas yield,</li> |
− | <li>[[Sizing of the Biogas Plant|plant sizing]], </li> | + | <li>[[Sizing of the Biogas Plant|plant sizing]],</li> |
− | <li>selection of plant [[Types of Biogas Digesters and Plants#Biogas Plant Types and Design|design]], </li> | + | <li>selection of plant [[Types of Biogas Digesters and Plants#Biogas Plant Types and Design|design]],</li> |
<li>how and where to use the biogas, etc., in accordance with the [[Planning Guide for Biogas Plants|planning guide]]</li> | <li>how and where to use the biogas, etc., in accordance with the [[Planning Guide for Biogas Plants|planning guide]]</li> | ||
</ul> | </ul> | ||
− | |||
</ul> | </ul> | ||
+ | |||
<br/> | <br/> | ||
− | + | ||
− | + | *<u>'''Stipulate the plant's location and elaborate a site plan'''</u><ul style="margin-left: 40px;"> | |
<li>including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry</li> | <li>including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry</li> | ||
</ul> | </ul> | ||
− | |||
</ul> | </ul> | ||
+ | |||
<br/> | <br/> | ||
− | + | ||
− | + | *<u>'''Draft a technical drawing showing all plant components'''</u><ul style="margin-left: 40px;"> | |
<li>i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage</li> | <li>i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage</li> | ||
</ul> | </ul> | ||
− | |||
</ul> | </ul> | ||
+ | |||
<br/> | <br/> | ||
− | + | ||
− | + | *<u>'''Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant''':</u><ul style="margin-left: 40px;"> | |
<li>bricks / stones / blocks for walls and foundation<br/></li> | <li>bricks / stones / blocks for walls and foundation<br/></li> | ||
<li>sand, gravel<br/></li> | <li>sand, gravel<br/></li> | ||
Line 46: | Line 46: | ||
<li>workshop for metal (gas-holder) and pipe installation<br/></li> | <li>workshop for metal (gas-holder) and pipe installation<br/></li> | ||
</ul> | </ul> | ||
− | |||
</ul> | </ul> | ||
+ | |||
<br/> | <br/> | ||
− | + | ||
− | + | *<u>'''Material / personnel assignment planning''', i.e. procedural planning and execution of:</u><ul style="margin-left: 40px;"> | |
<li>excavation<br/></li> | <li>excavation<br/></li> | ||
<li>foundation slab<br/></li> | <li>foundation slab<br/></li> | ||
Line 61: | Line 61: | ||
<li>acceptance inspection<br/></li> | <li>acceptance inspection<br/></li> | ||
</ul> | </ul> | ||
− | |||
</ul> | </ul> | ||
+ | |||
<br/> | <br/> | ||
− | + | ||
− | + | *<u>'''Regular building supervision''' '''Commissioning'''</u><ul style="margin-left: 40px;"> | |
<li>functional inspection of the biogas plant and its components<br/></li> | <li>functional inspection of the biogas plant and its components<br/></li> | ||
<li>starting the plant<br/></li> | <li>starting the plant<br/></li> | ||
</ul> | </ul> | ||
− | |||
</ul> | </ul> | ||
+ | |||
<br/> | <br/> | ||
+ | |||
*<u>'''Filling the plant'''</u> | *<u>'''Filling the plant'''</u> | ||
''''''<br/> | ''''''<br/> | ||
+ | |||
*<u>'''Training the user'''</u> | *<u>'''Training the user'''</u> | ||
Line 80: | Line 82: | ||
= Further Information = | = Further Information = | ||
− | |||
+ | *[[Checklist for the Planning of a Biogas Plant|Checklist for the Planning of a Biogas Plant]] | ||
+ | |||
+ | <br/> | ||
= References = | = References = | ||
<references /><br/> | <references /><br/> | ||
+ | </div> | ||
[[Category:Biogas]] | [[Category:Biogas]] |
Latest revision as of 09:25, 7 December 2015
Overview
The checklist for the construction of a biogas plant is summarized below.
Checklist for the Construction
- Planning of the Biogas Plant
- i.e. site evaluation,
- determination of energy demand and biomass supply / biogas yield,
- plant sizing,
- selection of plant design,
- how and where to use the biogas, etc., in accordance with the planning guide
- Stipulate the plant's location and elaborate a site plan
- including all buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry
- Draft a technical drawing showing all plant components
- i.e. mixing pit, connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage
- Preparation of material / personnel requirements list and procurement of materials needed for the chosen plant:
- bricks / stones / blocks for walls and foundation
- sand, gravel
- inlet / outlet pipes
- metal parts (sheet metal, angle irons, etc.)
- gas pipes and fittings
- paint and sealants
- gas appliances
- tools
- mason and helper
- unskilled labor
- workshop for metal (gas-holder) and pipe installation
- Material / personnel assignment planning, i.e. procedural planning and execution of:
- excavation
- foundation slab
- digester masonry
- gasholder
- rendering and sealing the masonry
- mixing pit - slurry storage pit
- drying out the plant
- installing the gas pipe
- acceptance inspection
- Regular building supervision Commissioning
- functional inspection of the biogas plant and its components
- starting the plant
- Filling the plant
- Training the user
Further Information
References