Difference between revisions of "Kindergarten No. 11 Jargalant soum - Thermo-technical retrofitting of public buildings"

From energypedia
***** (***** | *****)
***** (***** | *****)
Line 5: Line 5:
 
|BSP Project Budget=426.233.228,00 MNT
 
|BSP Project Budget=426.233.228,00 MNT
 
|BSP Project Status=Completed
 
|BSP Project Status=Completed
 +
|BSP Project Start=18.06.2017
 
|BSP Project Type=other
 
|BSP Project Type=other
 +
|BSP Project End=09.09.2017
 
|BSP Project Picture=Khovd KG 11.png
 
|BSP Project Picture=Khovd KG 11.png
 
|BSP Province=46.862496, 103.846656
 
|BSP Province=46.862496, 103.846656
Line 14: Line 16:
 
==== Building data and geometry ====
 
==== Building data and geometry ====
  
*  Construction year: 1975
+
*  Construction year: 1969
*  Cross volume: 3,276.8
+
*  Cross volume: 4,174.6
*  Thermal envelope: 1,730.3
+
*  Thermal envelope: 2,137.1
*  Net volume: 2,835
+
*  Net volume: 3,0011.1
*  Net floor area: 799.3
+
*  Net floor area: 1003.7
  
Implemented measures:
+
==== Implemented measures: ====
  
 
*  Roof insulation with 20cm EPS- hard foam and waterproofing
 
*  Roof insulation with 20cm EPS- hard foam and waterproofing
 
*  Wall insulation with 15cm EPS- hard foam
 
*  Wall insulation with 15cm EPS- hard foam
 +
*  Floor insulatio with 10 cm EPS - hard foam 
 
*  New windows with 5-chamber plastic frame and double glazing
 
*  New windows with 5-chamber plastic frame and double glazing
 
*  New exterior doors
 
*  New exterior doors
 
*  Rehabilitation of the heating system
 
*  Rehabilitation of the heating system
*  Contracting company: Tulgat bagana LLC
+
*  Rehabilitation of the drinking water and sewage system
 +
 
 +
Contracting company: '''Tulgat bagana LLC'''
  
 
==== Energy consumption ====
 
==== Energy consumption ====
  
*  Before: 522 kWh/(m2 a) {calculated}
+
*  Before: 545 kWh/(m2 a) {calculated}
*  After: 140 kWh /(m2 a) {metred}
+
*  After: 224 kWh /(m2 a) {metred}
*  Energy saving per year: 305,332 kWh
+
*  Energy saving per year: 322,248 kWh
*  Coal equivalent saving: 75,020 kg / 75 t
+
*  Coal equivalent saving: 79,158.3 kg / 79.2 t
*  CO2 emission savings per year: 206 t CO2 {Estimated}
+
*  CO2 emission savings per year: 217.8 t CO2 {Estimated}

Revision as of 05:05, 23 November 2017

► Back to the Main Page

Key Project Data

Name
Kindergarten No. 11 Jargalant soum - Thermo-technical retrofitting of public buildings
Description
Within the project 'Energy efficiency in the grid-connected energy supply' implemented by GIZ on behalf of the German federal Ministry for Economic Cooperation and Development (BMZ) and Swiss Development Cooperation (SDC) sixteen (16) have been retrofitted. This one of these buildings.
Project No.
14.2128.8-002.00
Total Budget
426.233.228,00 MNT
Status
Icon Completed.png Completed
Timeframe
18.06.2017 - 09.09.2017
Type
other
Project Picture
Click to download picture

Location in Mongolia

Province
'
Loading map...

Further Information

Website
Factsheet
Organization

Tagging

Publications

Currently, there are no publications related to this project.

Events

Currently, there are no events organized by this project.

Additional Comments



Building data and geometry

  •   Construction year: 1969
  •   Cross volume: 4,174.6 m³
  •   Thermal envelope: 2,137.1 m²
  •   Net volume: 3,0011.1 m³
  •   Net floor area: 1003.7 m²

Implemented measures:

  •   Roof insulation with 20cm EPS- hard foam and waterproofing
  •   Wall insulation with 15cm EPS- hard foam
  •   Floor insulatio with 10 cm EPS - hard foam 
  •   New windows with 5-chamber plastic frame and double glazing
  •   New exterior doors
  •   Rehabilitation of the heating system
  •   Rehabilitation of the drinking water and sewage system

Contracting company: Tulgat bagana LLC

Energy consumption

  •   Before: 545 kWh/(m2 a) {calculated}
  •   After: 224 kWh /(m2 a) {metred}
  •   Energy saving per year: 322,248 kWh
  •   Coal equivalent saving: 79,158.3 kg / 79.2 t
  •   CO2 emission savings per year: 217.8 t CO2 {Estimated}